Lee Sapp Leasing, Inc. v. Catholic Archbishop of Omaha

540 N.W.2d 101, 248 Neb. 829, 28 U.C.C. Rep. Serv. 2d (West) 474, 1995 Neb. LEXIS 228
CourtNebraska Supreme Court
DecidedDecember 1, 1995
DocketS-93-781
StatusPublished
Cited by46 cases

This text of 540 N.W.2d 101 (Lee Sapp Leasing, Inc. v. Catholic Archbishop of Omaha) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee Sapp Leasing, Inc. v. Catholic Archbishop of Omaha, 540 N.W.2d 101, 248 Neb. 829, 28 U.C.C. Rep. Serv. 2d (West) 474, 1995 Neb. LEXIS 228 (Neb. 1995).

Opinions

Lanphier, J.

The Catholic Archbishop of Omaha, doing business as Daniel J. Gross High School (Gross High) refused to make payments to Lee Sapp Leasing, Inc. (LSL), due under a “lease.” Under the agreement, Gross High was to purchase surge suppressors from Midwest Energy Controls, Inc. (Midwest Energy), and LSL was to finance the sale. Payment was to be made by LSL to Midwest Energy when Gross High accepted delivery. After some of the suppressors blew up on installation, Gross High asked Midwest Energy to remove the suppressors, refused to accept delivery, and refused to pay LSL. LSL filed a collection action against Gross High in the district court for Sarpy County.

[831]*831Both parties waived jury trial. After a bench trial, the district court found that under the Nebraska Uniform Commercial Code, the agreement was intended as security governed by article 9 rather than a lease governed by article 2, and that, therefore, Gross High’s only remedies were against the true seller of the goods, Midwest Energy. Gross High was ordered to pay the purchase price of the equipment, plus court costs, to LSL. Gross High appealed to the Nebraska Court of Appeals, and we removed the case to our docket. Finding that the duties to perform under the agreement were subject to a condition precedent of Gross High’s acknowledgment of delivery which did not occur, we reverse, and remand the cause with directions.

BACKGROUND

In September 1990, Midwest Energy approached Gross High for the purpose of selling to Gross High surge suppressors which would purportedly save Gross High money on electric bills. Gross High did not want to pay cash for the suppressors, so in order to consummate the sale to Gross High, Midwest Energy contacted LSL for financing. LSL was not in the energy or equipment business, but it agreed to provide financing for the surge suppressors in the form of a lease. Dennis Monahan, general manager of LSL, prepared a lease, dated November 15, 1990.

The agreement provided for 39 surge suppressors made by Redi-Volt and sold by Midwest Energy to be famished to Gross High in return for monthly rental. The terms of the agreement provided for monthly rental payments of $846.72 for 48 months.

The scheduled payments would return to LSL the cost of the equipment, plus interest. Gross High would become owner of the surge suppressors at the end of the term without additional consideration. Gross High, through its agent, signed the lease.

The language of the lease stated: “22. INTEGRATION. This lease and any schedules or addendums attached hereto constitutes the full agreement of the parties . . . .” LSL presented a letter of acceptance and delivery with the lease. The acceptance and delivery letter was attached to the lease, referred to the lease, and was presented to Gross High at the same time as the lease. The letter stated:

[832]*832ACCEPTANCE AND DELIVERY LETTER
The undersigned Lessee hereby acknowledges receipt of the equipment described below or on any attached schedule (the “Equipment”) fully installed and in good working condition, and Lessee hereby accepts the Equipment after full inspection thereof as satisfactory for all purposes of the above referenced lease executed by Lessee with Lee Sapp Leasing, Inc. (the “Lessor”). . . .
. . . [Gross High] understands that [LSL] is relying upon this receipt as a condition for making payment for the cost of the leased Equipment to [Midwest Energy],

(Emphasis supplied.)

Although the letter was dated November 15, 1990, the same date as the lease, a handwritten notation stated it was to be signed when the equipment was delivered. LSL does not dispute that the acceptance and delivery letter was a part of the transaction. LSL did maintain that contrary to the language of the documents, the receipt of the letter was a condition of LSL paying only the final 10 percent due to Midwest Energy.

Gross High neither signed nor returned this letter to LSL. Notwithstanding that fact, LSL paid Midwest Energy. Midwest Energy paid the first month’s rent and a security deposit to LSL. Midwest Energy’s employees attempted to install the surge suppressors at Gross High, but encountered problems. Robert Priborsky, Midwest Energy’s installer, wrote to LSL and stated:

As you know, I have been trying desperately to get Global Marketing [Midwest Energy’s supplier] to replace the Redi-Volt units, that went out during installation at Gross High School.
So in closing, because of Global Marketings [sic], lack of interest and support of their product, I am unable to complete the installation at Gross High School, for Midwest Energy Controls, Inc.

During installation of 24 of the 39 surge suppressors by Midwest Energy, 3 of the suppressors “blew up.” Midwest Energy never completed installation of all 39 suppressors. Gross. High requested that Midwest Energy remove the installed surge [833]*833suppressors, but Midwest Energy did not comply. Gross High never accepted delivery of the suppressors or made a payment to LSL on the agreement.

ASSIGNMENTS OF ERROR

Gross High contends that the trial court erred (1) in refusing to recognize that article 2 of the Nebraska Uniform Commercial Code governed the sales aspects of the agreement transaction, (2) in concluding that Gross High’s defenses amounted to a breach of warranty, and (3) in refusing to apply the provisions of Neb. U.C.C. § 2-606 (Reissue 1992), entitled “What constitutes acceptance of goods,” to the evidence presented at trial.

STANDARD OF REVIEW

In a bench trial of a law action, the trial court’s factual findings have the effect of a jury verdict and will not be set aside on appeal unless they are clearly wrong. Lincoln Lumber Co. v. Fowler, ante p. 221, 533 N.W.2d 898 (1995); First Westside Bank v. For-Med, Inc., 247 Neb. 641, 529 N.W.2d 66 (1995); Label Concepts v. Westendorf Plastics, 247 Neb. 560, 528 N.W.2d 335 (1995).

However, when reviewing a question of law, an appellate court reaches a conclusion independent of the lower court’s ruling. Eggers v. Rittscher, 247 Neb. 648, 529 N.W.2d 741 (1995); Dolan v. Svitak, 247 Neb. 410, 527 N.W.2d 621 (1995); Hausse v. Kimmey, 247 Neb. 23, 524 N.W.2d 567 (1994).

ANALYSIS

Gross High urges that it has certain rights under article 2 of the Nebraska Uniform Commercial Code which govern the defects in the goods and its nonacceptance of same. LSL urges that article 9 of the Nebraska Uniform Commercial Code governs and that LSL as a financing entity has no responsibility for a defect in the goods and, in any event, that Gross High’s refusal to accept delivery and the fact that the goods may have been defective are affirmative defenses which were not pled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dick v. Koski Prof. Group
307 Neb. 599 (Nebraska Supreme Court, 2020)
Digital Ally, Inc. v. Z3 Technology, LLC
754 F.3d 802 (Tenth Circuit, 2014)
Digital Ally, Inc. v. Z³ Technology, LLC
864 F. Supp. 2d 1050 (D. Kansas, 2012)
Norwest Corp. v. State, Dept. of Ins.
571 N.W.2d 628 (Nebraska Supreme Court, 1997)
Estate of Stine v. Chambanco, Inc.
560 N.W.2d 424 (Nebraska Supreme Court, 1997)
Blanchard v. City of Ralston
559 N.W.2d 735 (Nebraska Supreme Court, 1997)
Simonsen v. Hendricks Sodding & Landscaping Inc.
558 N.W.2d 825 (Nebraska Court of Appeals, 1997)
Daehnke v. Nebraska Department of Social Services
557 N.W.2d 17 (Nebraska Supreme Court, 1996)
Poppen v. Residential Mortgage Services, Inc.
556 N.W.2d 49 (Nebraska Court of Appeals, 1996)
Heins v. Webster County
552 N.W.2d 51 (Nebraska Supreme Court, 1996)
Scholl v. County of Boone
549 N.W.2d 144 (Nebraska Supreme Court, 1996)
Blanchard v. City of Ralston
549 N.W.2d 652 (Nebraska Court of Appeals, 1996)
Nelson v. Metropolitan Utilities District
547 N.W.2d 133 (Nebraska Supreme Court, 1996)
ACME Investment, Inc. v. Southwest Tracor, Inc.
911 F. Supp. 1261 (D. Nebraska, 1995)
Lee Sapp Leasing, Inc. v. Catholic Archbishop of Omaha
540 N.W.2d 101 (Nebraska Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
540 N.W.2d 101, 248 Neb. 829, 28 U.C.C. Rep. Serv. 2d (West) 474, 1995 Neb. LEXIS 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-sapp-leasing-inc-v-catholic-archbishop-of-omaha-neb-1995.