Lawson v. Excel Contractors

CourtCourt of Appeals for the Fifth Circuit
DecidedJune 2, 2022
Docket21-30438
StatusUnpublished

This text of Lawson v. Excel Contractors (Lawson v. Excel Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lawson v. Excel Contractors, (5th Cir. 2022).

Opinion

Case: 21-30438 Document: 00516341340 Page: 1 Date Filed: 06/02/2022

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED June 2, 2022 No. 21-30438 Lyle W. Cayce Clerk

William B. Lawson,

Plaintiff—Appellant,

versus

Excel Contractors, L.L.C.,

Defendant—Appellee.

Appeal from the United States District Court for the Western District of Louisiana USDC No. 2:19-CV-834

Before Barksdale, Stewart, and Dennis, Circuit Judges. Per Curiam:* William Lawson worked as a welding inspector for Excel Contractors, L.L.C., from April 2016 until August 2017, when he took a two-week leave of absence after experiencing heart problems. During Lawson’s leave, Excel hired someone to temporarily replace him and promoted one of his peers; both individuals were substantially younger than Lawson. When Lawson

* Pursuant to 5th Circuit Rule 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Circuit Rule 47.5.4. Case: 21-30438 Document: 00516341340 Page: 2 Date Filed: 06/02/2022

No. 21-30438

returned to work, Excel assigned him to office tasks; he had previously worked primarily in the field. Excel terminated Lawson four months later, citing the need to downsize. However, Excel did not terminate Lawson’s replacement, who had transitioned to permanent work, or his recently promoted peer. Lawson filed this suit five months later. He alleged that, by failing to promote or retain him, Excel unlawfully discriminated against him because of his age and disability and retaliated against him for taking leave. Excel moved for summary judgment, which the district court granted. Lawson timely appeals. For the following reasons, we AFFIRM the district court. I. Facts & Procedural History Lawson is a certified welding inspector who is in his sixties. He started working for Excel in April 2016, after Excel acquired Lawson’s previous employer, Ron Williams Construction. Excel is a Baton Rouge–based construction company that provides pipefitting and welding services for a varying number of new and maintenance contracts. Excel hired Lawson as a Quality Assurance/Quality Control (“QA/QC”) Inspector. At the time, Excel employed only one other QA/QC Inspector, George “Gene” Anderson, who also came from Ron Williams Construction. Anderson, who is twenty years younger than Lawson, oversaw Excel’s pipe fabrication shop. Lawson, in contrast, floated from project to project while also supervising Excel’s Firestone maintenance contract. Lawson and Anderson worked under the supervision of a QA/QC Manager, until that person resigned in June 2017. Allegedly, rather than promote someone to replace the QA/QC Manager, Excel gave Lawson and Anderson both raises and told them that they would be equal in rank going forward. On August 21, 2017, Lawson became dizzy and started feeling chest pains while on a jobsite. He went home to recover and see a doctor. The next

2 Case: 21-30438 Document: 00516341340 Page: 3 Date Filed: 06/02/2022

day, Lawson saw his family physician, who referred him to a cardiologist. The cardiologist conducted an angiogram on Lawson, revealing some arterial blockage that the cardiologist described as “pretty much normal” for someone of Lawson’s age and mobility. The cardiologist prescribed Lawson statin, increased the dosage of his blood pressure medicine, and cleared him to work beginning the first week of September. Lawson subsequently received a second return-to-work slip from Excel’s company physician. Both the cardiologist and company physician cleared Lawson’s return without restriction. He returned to work at Excel on September 6, 2017. Excel made some changes while Lawson was out. Within a few days of Lawson leaving work, Excel hired David Currie to temporarily replace him as the QA/QC Inspector at its Westlake Petrochem project. Allegedly, that project temporarily shut down shortly after Excel hired Currie, meaning Currie mostly worked in the office until Lawson returned. When Lawson did return, Excel retained Currie and transferred him to its Indorama project. Currie is seventeen years younger than Lawson. Meanwhile, sometime in August 2017, Excel promoted Anderson to the recently vacated QA/QC Manager position, effective September 1, 2017. Excel says that it selected Anderson for the position because he had more seniority within the organization: Anderson began working for Ron Williams Construction, which Excel acquired, several years before Lawson. Additionally, Lawson was having trouble completing critical paperwork for the Firestone contract in a timely fashion whereas Anderson was current on his work. Lawson alleges, however, that he was more qualified for the promotion than Anderson. Although Anderson had worked as a QA/QC Inspector for nearly twenty years, Lawson had worked in the industry longer than Anderson and had once been Anderson’s interim supervisor at Ron Williams Construction.

3 Case: 21-30438 Document: 00516341340 Page: 4 Date Filed: 06/02/2022

Upon his return to work, Lawson completed paperwork related to winding down the Firestone contract, which Excel had recently lost. As noted above, Lawson had mostly worked in the field before this change. Although Lawson also did some work for the Westlake Petrochem project, which had resumed, that project shut down again soon after he returned. As a result, Lawson stayed in the office closing out the Firestone contract, which he completed in January. Around the same time, Excel’s work started drying up in southwest Louisiana, where Lawson was based. Given the nature of Excel’s business, it regularly increases and decreases its workforce to account for fluctuating market conditions. In January 2018, Excel submitted Lawson’s resume in connection with a “seven figure bid” for the proposed Juniper construction project. If Excel won the project, it would have chosen Lawson as its lead QA/QC Inspector. But Excel was not selected, causing it to consider Lawson for termination under an ongoing workforce reduction once he closed the Firestone project. On January 25, 2018, less than two hours after he completed the Firestone project, Excel terminated Lawson. In the six months preceding Lawson’s termination, Excel laid off 564 employees, 64 percent of whom were under the age of forty. Although Excel did not fire Anderson or Currie during this downsizing, Anderson resigned in February 2018 and Currie resigned in March 2018. Excel did not fire Currie because it had submitted his resume in connection with its bid for the smaller Juniper planning project, which it still hoped to win. After exhausting his administrative remedies, Lawson sued Excel in federal court, asserting claims under the Americans with Disabilities Act (“ADA”), the Age Discrimination in Employment Act (“ADEA”), and the Family and Medical Leave Act (“FMLA”). Excel moved for summary judgment. The district court granted Excel’s motion and entered final judgment.

4 Case: 21-30438 Document: 00516341340 Page: 5 Date Filed: 06/02/2022

II. Standard of Review This court reviews orders granting summary judgment de novo. Griggs v. Brewer, 841 F.3d 308, 311 (5th Cir. 2016). “Summary judgment is appropriate only when ‘the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.’” Shepherd ex rel. Estate of Shepherd v. City of Shreveport, 920 F.3d 278, 282–83 (5th Cir. 2019) (quoting Fed. R. Civ. P. 56(a)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mauder v. Metropolitan Transit Authority
446 F.3d 574 (Fifth Circuit, 2006)
McDonnell Douglas Corp. v. Green
411 U.S. 792 (Supreme Court, 1973)
Gross v. FBL Financial Services, Inc.
557 U.S. 167 (Supreme Court, 2009)
David Atkins v. Ken Salazar, Secretary
677 F.3d 667 (Fifth Circuit, 2011)
Jackson v. Cal-Western Packaging Corp.
602 F.3d 374 (Fifth Circuit, 2010)
Pete Keller, Jr. v. Coastal Bend College
629 F. App'x 596 (Fifth Circuit, 2015)
Tanner Griggs v. Charley Brewer
841 F.3d 308 (Fifth Circuit, 2016)
Tyler Renwick v. P N K Lake Charles, L.L.C.
901 F.3d 605 (Fifth Circuit, 2018)
Rhonda Lamb v. Ashford Place Apartments LLC
914 F.3d 940 (Fifth Circuit, 2019)
Marjorie Shepherd v. City of Shreveport
920 F.3d 278 (Fifth Circuit, 2019)
Leah Amedee v. Shell Chemical, L.P.
953 F.3d 831 (Fifth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Lawson v. Excel Contractors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lawson-v-excel-contractors-ca5-2022.