Latex Construction Company v. Nexus Gas Transmission

District Court, S.D. Texas·Decided December 16, 2020·No. 4:20-cv-01788·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT December 16, 2020 David J. Bradley, Clerk FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION

LATEX CONSTRUCTION § COMPANY, § Plaintiff, § § v. § CIVIL ACTION NO. 4:20-1788 § NEXUS GAS TRANSMISSION, LLC, § Defendant. § MEMORANDUM AND ORDER Before the Court is Defendant Nexus Gas Transmission, LLC’s (“Defendant’s”) Motion for Partial Summary Judgment on Plaintiff’s Claim for Extra Compensation for Hard Trench Plugs and Foreign Line Crossings [Doc. # 27] (“Motion”). Plaintiff Latex Construction Company (“Plaintiff”) has timely responded,1 Defendant has replied,2 and Plaintiff has filed a sur-reply.3 The Motion is ripe for decision. Based on the parties’ briefing, pertinent matters of record, and relevant legal authorities, the Court denies Defendant’s Motion.

1 Plaintiff’s Response to Defendant’s Motion for Partial Summary Judgment [Doc. # 49] (“Plaintiff’s Response”). 2 Defendant’s Reply in Support of Motion for Partial Summary Judgment on Plaintiff’s Claim for Extra Compensation for Hard Trench Plugs and Foreign Line Crossings [Doc. # 50] (“Defendant’s Reply”). 3 Plaintiff’s Surreply in Response to New Evidence and Argument in Defendant’s Reply in Support of its Motion for Partial Summary Judgment [Doc. # 54] (“Plaintiff’s Surreply”). I. BACKGROUND This case arises out of a contract for construction of a gas transmission

pipeline in Ohio. Defendant, the owner of the Nexus Gas Transmission Pipeline, hired Plaintiff to construct the second of four segments of the pipeline (the “Pipeline”).4 Plaintiff and Defendant entered into a contract for construction of the Pipeline on February 17, 2016 (the “Contract”).5 The Contract provided that

Plaintiff would receive a “Contract Price,” defined as “the total amount paid by Company to Contractor for the Work” in exchange for Plaintiff performing “all of [Plaintiff’s] obligations, duties and responsibilities under this Agreement.”6

Exhibit C to the Contract listed all the payments Defendant would make to Plaintiff under the Contract, and the parties agreed that the payments listed in Exhibit C would be all the compensation Plaintiff was entitled to receive, unless the scope of Plaintiff’s work was modified through a Change Directive or a Change Order.7

4 Construction Agreement 15-7002: Nexus Gas Transmission Project [Docs. # 27-1, # 28-30] (“Contract”); Declaration of David Williams [Doc. # 49-6] (“Williams Decl.”), ¶ 4. 5 Id. 6 Contract § 1.1. 7 Id. §§ 13.7, 7.1; Exhibit C to Construction Agreement 15-7002: Nexus Gas Transmission Project [Doc. # 28] (“Exhibit C”). Exhibit C provided for different types of compensation: Primary Compensation, a lump sum base payment which “reimburse[d] [Plaintiff] fully to

complete the Work,” and “Unit Price Extra Work” compensation, which compensated Plaintiff on a per-unit basis for any work not included in the Primary Compensation.8 Exhibit C listed the unit prices at which Plaintiff would be paid for

35 different items or tasks that might be necessary for construction but were not included in the Primary Compensation.9 The unit prices included all labor, materials, and equipment needed to perform the additional work.10 The Contract anticipated that construction of the Pipeline would require a

number of hard trench plugs and foreign line crossings. Hard trench plugs are filled portions of the pipeline ditch that allow landowners and livestock to cross the ditch during construction.11 Foreign line crossings are preexisting pipes encountered

while digging the pipeline ditch.12 Hard trench plugs and foreign line crossings are common parts of pipeline construction and require line breaks in the construction

8 Exhibit C § 1. 9 Id. § 2. 10 Id. 11 A Practical Guide for Pipeline Construction Inspectors, CEPA Foundation, (March 2016) [Doc. # 42-2] (“CEPA Guide”), p. 68. 12 Id. process and additional welding work.13 The Primary Compensation due to Plaintiff included payment for 96 hard trench plugs and 73 foreign line crossings.14 Plaintiff

claims it is customary for pipeline owners to allow contractors to put hard trench plugs at “natural breaking points” so that the majority of the pipeline can be constructed using automatic welding.15 To the extent construction of the Pipeline

required more than 96 hard trench plugs or 73 foreign line crossings, Plaintiff would be paid Unit Price Extra Work compensation of $22,500 for each additional hard trench plug and $29,500 for each additional foreign line crossing.16 The Contract provided that the per-unit compensation applied to each

additional “unknown buried utility within a 50 ft. corridor” of the pipeline and charged Plaintiff with responsibility for “surface and subsurface ground and soil conditions on the Site, including all natural and manmade obstructions such as

utilities.”17 The Contract also required Plaintiff to investigate the site and identify

13 Id. 14 Exhibit C § 2.28; Contractor Requested Change No. 036R2 [Doc. # 31] (“CRC- 036R2”); Contractor Requested Change No. 036R [Doc. # 31-3] (“CRC-036R”). 15 Williams Decl. ¶ 15. 16 Exhibit C §§ 2.18, 2.28; February 13, 2018 Change Order [Doc. # 31-3] (“True-Up Amendment”) §§ 2.18, 2.28. 17 Exhibit C §§ 2.28, 3.15(c). “obstacles to construction or other general local conditions that may affect performance of the Work or cost of the Project.”18

The Contract required that Plaintiff complete construction by a scheduled date and allowed Defendant to hold Plaintiff to this schedule if Plaintiff was delayed for reasons within Plaintiff’s control.19 The Contract provided that Plaintiff could

receive compensation for Defendant’s acceleration so long as the cause of the delays were outside Plaintiff’s reasonable control.20 After the Contract was executed, construction was delayed indefinitely because Defendant had not obtained the required permits.21 On February 22, 2017,

the parties met to discuss pricing changes due to events that had occurred during the delay.22 Defendant memorialized in its notes from that meeting that “[Plaintiff] needs indicator on temporary plugs so not missed during construction in the field”

and that Defendant would “provide count on temporary plugs by ROW track to

18 Id. § 3.16(b). 19 Contract § 5.4. 20 Id. 21 Williams Decl. ¶ 4. 22 Id. ¶ 5. Contractor for purposes of pricing.”23 Later that day, Defendant provided Plaintiff with a list showing that 61 hard trench plugs would be required.24

Over the course of the next year, Plaintiff and Defendant exchanged pricing and scheduling estimates while Defendant waited to receive the necessary permits.25 In June and September 2017, Defendant provided Plaintiff with Construction Line

Lists (“CLLs”), which identified special concerns for each landowner over which the Pipeline was to cross.26 The June 2017 CLL indicated that a total of 176 hard trench plugs would be needed for the Pipeline.27 The September 2017 CLL indicated that 207 hard trench plugs would be needed.28

Work began on the project in February of 2018.29 On February 13, 2018, Plaintiff and Defendant executed a “True-Up Amendment” to account for cost and

23 Id.; February 22, 2017 Meeting Notes [Doc. # 49-2]. 24 February 22, 2017 Email from Jolene Packard to Chip Prosser and Shawn Pomerleau [Doc. # 49-2]; List of Temporary Crossings as of February 22, 2017 [Doc. # 49-2]; Williams Decl. ¶ 5. 25 Williams Decl. ¶¶ 4–6. 26 June 6, 2017 Construction Line List [Docs. # 32-35] (“June 2017 CLL”); September 6, 2017 Construction Line List [Docs. # 36-41] (“September 2017 CLL”). 27 June 2017 CLL. 28 Sept. 2017 CLL. 29 Williams Decl. ¶ 13. schedule adjustments since the Contract was executed approximately two years earlier.30 The True-Up Amendment “resolved between [Defendant] and [Plaintiff]”

Free access — add to your briefcase to read the full text and ask questions with AI

Latex Construction Company v. Nexus Gas Transmission, (S.D. Tex. 2020).

Latex Construction Company v. Nexus Gas Transmission (Latex Construction Company v. Nexus Gas Transmission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Little v. Liquid Air Corp.
37 F.3d 1069 (Fifth Circuit, 1994)
Littlefield v. Forney Independent School District
268 F.3d 275 (Fifth Circuit, 2001)
Oliver v. Scott
276 F.3d 736 (Fifth Circuit, 2002)
Malacara v. Garber
353 F.3d 393 (Fifth Circuit, 2003)
General Universal Systems, Inc. v. Lee
379 F.3d 131 (Fifth Circuit, 2004)
Boudreaux v. Swift Transportation Co.
402 F.3d 536 (Fifth Circuit, 2005)
Interstate Contracting Corp. v. City of Dallas
407 F.3d 708 (Fifth Circuit, 2005)
DIRECTV, Inc. v. Robson
420 F.3d 532 (Fifth Circuit, 2005)
Tamez Ex Rel. Estate of Tamez v. Manthey
589 F.3d 764 (Fifth Circuit, 2009)
Chaney v. Dreyfus Service Corp.
595 F.3d 219 (Fifth Circuit, 2010)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
P. L. Saddler v. United States
287 F.2d 411 (Court of Claims, 1961)
Air-A-Plane Corporation v. The United States
408 F.2d 1030 (Court of Claims, 1969)