Langan Construction Corp. v. State

110 Misc. 177
CourtNew York Court of Claims
DecidedJanuary 15, 1920
DocketClaim No. 14927
StatusPublished
Cited by4 cases

This text of 110 Misc. 177 (Langan Construction Corp. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Langan Construction Corp. v. State, 110 Misc. 177 (N.Y. Super. Ct. 1920).

Opinion

Ackerson, P. J.

The facts of this case are briefly as follows: The claimant is a domestic corporation. On November 1, 1915, it entered into a contract with the state of New York for the improvement of a highway in the county of Erie known as Transit, Part four, Highway No. 1334.” The state thereby agreed to pay it for the necessary labor and materials to perform the work mentioned in the contract the sum of $70,033.09.

The highway to be improved was four and thirty one-hundredths miles in length and divided into three parts, as follows: One and eighty-five one-hundredths miles water-bound macadam, one and thirty-three one-hundredths miles concrete, one and twelve one-hundredths miles asphalt to be laid on an old macadam road.

On April 6, 1916, the claimant notified the state that it was ready to proceed with the work. Previous to this time it had moved its asphalt plant there from Alexandria, Va., leased land from the New York Central Railroad Company on which to operate it and made ready to perform the work it had contracted to do.

The state, after waiting twenty days, informed claimant that the macadam base for the asphalt was [179]*179not sufficient, and submitted proposed prices for making it sufficient. The claimant replied the next day, April 27, 1916, that it could not do the additional work for the price mentioned by the state, and made an offer to do it for a higher price.

On April twenty-eighth, the next day, claimant was notified by the division engineer that the matter of the additional work had been referred to the Albany office and that if the department did not wish to pay a higher price for the additional work than he had already offered there was one other course open, and that was the cancellation of that part of the contract calling for the asphalt.

Claimant replied the next day after that, April twenty-ninth, that it objected to the cancellation of the asphalt portion of the contract and would be glad to discuss.the matter of price to be stipulated in the supplemental contract for the additional work.

Nothing more was heard from the state until May tenth, when claimant and its surety were notified by the state to proceed with the macadam and concrete portions of the highway and that the asphalt section was eliminated.

This order of the state virtually destroyed the contract the claimant had entered into. It removed from the contract most, if not all, of the work on which the claimant could make any profit. The part of the work thus eliminated constituted forty-three per cent of the work under the contract. Of the $70,033.09 which the claimant was to receive for the work included in the contract, $30,739.50 of it was for building the asphalt section eliminated, and on which work claimant would have made a profit of about $13,000 if he had been allowed to carry out his contract.

The claimant refused to go on with the work with the asphalt portion thus eliminated, and on June 2, [180]*1801916, the state commission of highways made an order formally cancelling the whole contract.

The state attempts to justify the action of its officers in relation to this contract by contending that it had the right to eliminate the asphalt section of the road under section 4 of the contract, which reads as follows:

4. The said work shall be performed in accordance with the true intent and meaning of the plans and specifications therefor, which are hereby referred to and made a part of this contract. The State, however, reserves the right to make such additions, deductions or changes as it deems necessary, making an allowance for deductions therefor at the price named in the proposal for this work and this contract shall in no way be invalidated thereby and no claim shall be made by the contractor for any loss of-anticipated profits because of any such change or by reason of any variation between the approximate quantities and the quantities of the work as done. It is further agreed that an increase in quantities or extra work performed or extra materials furnished shall be covered by a supplemental contract, as provided in chapter 30 of the Laws of 1909, and the amendments thereto, and that no claim will be made by the contractor for any such items performed or furnished before such supplemental contract shall have been approved by the Comptroller of the State of New York and executed by the Commissioner of Highways as provided by chapter 342 of the Laws of 1913 and the amendments thereto.”

It further contends that the case of Kinser Construction Co. v. State of New York, 204 N. Y. 381, sustains it in this view. We are unable to agree with this contention of the state.

The state was bound by its contract and by it guar[181]*181anteed the sufficiency of the macadam base for the asphalt. MacKnight Flintic Stone Co. v. City of New York. 160 N. Y. 72.

When it determined that such macadam base was insufficient, it seems to us that it must have done one of three things, viz.:

(1) Permitted claimant to make it sufficient under a supplemental contract;

(2) Performed such work itself or by an independent contractor;

(3) Cancelled the contract and thereby became liable to claimant for its damages.

The deficient macadam base, if it was deficient, could have easily been made sufficient by the state at an expense that would have kept the whole contract within the engineer’s estimate. The estimate of the state’s engineer of the cost of the work to be done under this contract was $83,807.50. The amount of this claimant’s bid and the contract price with it for doing the work was $13,774.41 less than that, or $70,033.09.

Section 4 of the contract clearly cannot protect the state in such a case as this, as we read the eases. National Contracting Co. v. Hudson River Water Power Co., 192 N. Y. 209. Neither does the opinion in the Kinser Construction Co. Case, supra, disclose any reason why that case should be followed as a precedent in a ease such as the one we are now considering. Here was a matter which lay right on the surface. There was no reason why the state should not have fully understood what it was doing when it contracted with claimant to place asphalt on this old macadam highway. There was no reason, when it changed its mind about it, why the weakness that it then claimed to exist should not have [182]*182been remedied and the claimant permitted to go on with its contract.

There was no necessity here to warrant the state in suddenly confronting the contractor without warning with an entirely different situation than he had contracted to meet nearly six months before.

For these six months the claimant had been preparing to perform a contract from which it hoped to derive considerable profit. Suddenly, on the eve of commencing the work, forty-three per cent of the contract is cut out, the whole nature of it is changed, and the claimant is confronted with the proposition of being compelled to perform a contract such as he never had in mind when he bid, and one which could bring him but little, if any, profit.

There must be a rational and just ground for deeming a change necessary. The contractor is protected against arbitrary, capricious and unreasonable action by the officers of the state. Kinser Construction Co. v. State of New York, 204 N. Y. 381-391.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensler v. City of Los Angeles
268 P.2d 12 (California Court of Appeal, 1954)
People v. Rockwood
126 Misc. 542 (New York Supreme Court, 1925)
Beskin v. State
119 Misc. 209 (New York State Court of Claims, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
110 Misc. 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/langan-construction-corp-v-state-nyclaimsct-1920.