Baker v. State

77 A.D. 528
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1902
StatusPublished
Cited by1 cases

This text of 77 A.D. 528 (Baker v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. State, 77 A.D. 528 (N.Y. Ct. App. 1902).

Opinion

Parker, P. J.:

' The contract, for the breach of which tin’s clnlm Ja-Brnd-e-Accfllust, the State, provides,Jn substance, that, if the execution—of. the contract shall be^uspended'by the State at any time for anv cause, im claim for m’ospectivg~TTronts on work not done shall be made and allowed, but the contractors shall complete the work when the State shall order it to be resumed, and the date of such completion shall be fixed by the Superintendent of Public Works. It is claimed on the part of the State that the breach complained of is but a suspension ” under the above provision. If such claim is correct, it is plain that not only could no prospective profits be now claimed as [531]*531damages, but neither could the sums which, by the terms of the contract are to be retained until the completion of the work, be now demanded. No breach of the contract would have occurred, nor would such sums have yet become due.

But I am of the opinion that the Action of the State upon and after the 14th of May, 1898, was an abandonment of the work referred to in_the contract instead of a mere “ suspension ” thereof. The contract was then terminated by the State, and the contractors were notified to that effect. No suggestion was made that the work provided for in the contract was to be thereafter completed, or that any time would be thereafter fixed for its completion.

They were simply notified that the work was to cease, and operation under the contract was then brought to an end. Chapter 544 of the Laws of 1899 seems to be a declaration on the part of the State that it so considered the situation, and that if the contractors were willing to adopt that view and take what was due them upon their contracts and release all further claims, they would be paid upon that basis, including all moneys held by the State as security for the performance of the contract on their part. . A clear abandonment of the scheme to improve the canal to the depth of nine feet is here shown; and it is very apparent that the breach of which the appellants complain is not theniere suspension above referred to.

We have then this situation: The contractors institute against the State these proceedings for a breach of its contract, and- they claim not only the amounts due for work actually done by them thereunder, but also such damages as have naturally accrued to them on account of such breach. The amount still unpaid for work actually done is conceded to be $8,881.23; and the amount of money deposited with the State as security for the work is conceded to be $5,100. It is also conceded that, so far as they were permitted, the contractors have well and faithfully performed the work. The State having abandoned the work and prevented further performance on the the part of the contractors, it is clear that both the sum of $5,100 and the $8,881.23 are due and payable by it to the contractors; and under this view of the case, it is difficult to see why they should not recover them untrammeled by a provision in the judgment that they release all further claim for damages against the State. [532]*532But the further claim that the contractors make in this proceeding, that they are entitled to recover the profits which they would have made had the work proceeded to full completion under the j contract, is not so clear.

On the face of the contract, and on the proof disclosed by the record before us, the total work which the contractors undertook to perform was, it seems to me, to construct and to finish” the improvement of a certain specified five and eighty-seven one-hundredths miles of the Erie canal according to plans and specifications submitted ! with and made a part of the contract. Such is their undertaking ,in the first provision of the contract. No change in such plans and (specifications has ever been made by the State, and it is conceded ¡that when abandoned such work had not been completed.

Such being the obligation on the part of the contractors, it would seem, from the proof disclosed by the record, that the reciprocal obligation on the part of the State to permit them to prosecute the work to completion, and to pay them for the same, exists, unless the State has reserved to itself the right to end the work at any period of its progress. If such right is reserved, undoubtedly, no loss of profits could be claimed as damages for a breach of the contract, because in that case there would be no breach. The court below has substantially held that such is the situation here, and has, therefore, rejected the contractors’ claim for such damages. If the solution of the question depends upon the construction of the terms of the contract alone, a careful study of that instrument will force the conclusion that no such reservation can be found within it.

Notice that bids for the performance of the work upon the five and eighty-seven one-hundredths miles covered by this contract would be received was published. Accompanying .that notice, the plans, specifications and statement of the engineer’s estimate for the work to be done thereon were submitted and filed as required by chapter 794 of the Laws of 1896 (amdg. Laws of 1895, chap. 79, §§ 4, 5). Under such notice and statement these claimants made a bid and affixed theiihpoicesjDer yard and per foot to the several estimated amounts of excavationTconstrucrion or material' contained» in such statement. They were awarded the work, and thereupon entered ..a into the contract which is set forth at length in the appeal book. U By such contract, such plans, specifications and statement are made [533]*533| a part of the contract. By such statement the total cost of the work and materials to be done and furnished, less value of old materials furnished by the State, amounted, at the agreed prices, to the sum of $98,760. The work done and materials furnished by the contractors up to the time the work was stopped amounted to $75,886.23. It is proven in the case that most of the estimated amounts given in such “statement” fell far short of the amounts actually necessary to finish the work according to the plans and specifications referred to in the contract. The total cost of such work, at the agreed prices, would amount to $165,953.75. Thus, at the time the work was abandoned, there was still unperformed and unfurnished of the estimated work and materials an amount equal to the sum of $22,873.77, and of the amount necessary to complete the actual work required an amount equal to $90,067.52.

t There are several provisions in the contract, specifications and I statement which it is claimed amount to a reservation by the State of the right to terminate at any time it desired the work under this contract. First. In the bid which is written and signed by the contractors, at the foot of the “ statement ” of estimated amounts,, etc., they offer “ to construct and to finish, so far as the superintendent of public works shall direct, all of the work to which prices are affixed in the above schedule in all respects according to the contract and specifications, etc., * * * this day exhibited. * * * ” But this offer is no part of the contract and it is to be noticed that in the contract their undertaking is to do all the labor, etc., necessary to “ construct and to Jmish in every respect ” the five and. eighty-seven one-hundredths miles in question, and such work is to be done according to the plans and specifications furnished, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langan Construction Corp. v. State
110 Misc. 177 (New York State Court of Claims, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
77 A.D. 528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-state-nyappdiv-1902.