Lang Bros. v. United States

36 Cont. Cas. Fed. 75,872, 20 Cl. Ct. 551, 1990 U.S. Claims LEXIS 215, 1990 WL 72509
CourtUnited States Court of Claims
DecidedJune 1, 1990
DocketNo. 170-88 C
StatusPublished
Cited by1 cases

This text of 36 Cont. Cas. Fed. 75,872 (Lang Bros. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lang Bros. v. United States, 36 Cont. Cas. Fed. 75,872, 20 Cl. Ct. 551, 1990 U.S. Claims LEXIS 215, 1990 WL 72509 (cc 1990).

Opinion

OPINION

RADER, Judge.

Lang Brothers Inc. (plaintiff) contracted with the Soil Conservation Service (SCS) of the United States Department of Agriculture to construct an earthen dam across the Tug Fork River near Statts Mill, West Virginia. The construction process required plaintiff to build a cofferdam upstream from the permanent dam. The contract discussed liability for damages to the cofferdam resulting from water rising to an elevation of 642 feet or less. Heavy rains caused flood water to crest at 630.4 feet on July 9, 1985. On July 10,1985, the unfinished cofferdam collapsed. Plaintiff now seeks reimbursement for the cost to repair the cofferdam and to replace equipment damaged in the flood. Defendant contends that the contract did not cover plaintiff’s losses.

After oral argument, this court denies plaintiff’s motion for summary judgment. This court grants in part defendant’s cross-motion for summary judgment.

FACTS

Lang Brothers is a contractor with over 30 years’ experience constructing dams. Lang Brothers has built other dams for [552]*552SCS both before and after the case at bar. Thus, plaintiff has extensive experience with dam building.

On September 23, 1983, plaintiff contracted with SCS to construct an earthen dam in the Mill Creek Watershed near Statts Mill, West Virginia. Plaintiff began work in 1983. The contract contemplated construction in incremental stages over a three-year period. The project required plaintiff to build both a permanent dam, a dike, and a cofferdam. The cofferdam was a temporary measure designed to rechan-nel water during construction of the permanent dam. The cofferdam, located upstream from the permanent dam, diverted water into a 66-inch concrete pipe. This diversion provided a dry streambed at the permanent construction site.

The contract placed the new dam at the end of a narrow valley. The parties envisioned that the project would be vulnerable to floods during the construction phase. Therefore, the contract contained a provision assigning risk:

RISK OF WEATHER

The construction of the dike to elevation 625' provides protection at the elevation of an approximate 10 year annual storm. The construction of the sheet piling coffer dam at elevation 642' provides protection at the elevation of an approximate one year annual storm. The Government assumes the risk of damage to the permanent work at crest below the elevations stated due to the failure of the dike or coffer dam. If either the dike or the coffer dam fail, due to no fault of the Contractor, at or below the above stated elevations, a modification will be issued by the Contracting Officer to provide an equitable adjustment in costs to restore the damaged works. The Contractor remains responsible for storm damages caused by a crest greater than elevation 625' during the second construction season or greater than elevation 642' during the third construction season. Damage to the permanent works resulting from conditions not herein provided for remain the responsibility of the contractor.

Construction Contract, No. 170-88 C, filed May 21, 1990, Special Provision 35.

Because this provision shifted some risk to SCS during the construction phase, the contract also set forth specifications for construction of the cofferdam to narrow the window of vulnerability. Plaintiff would construct the cofferdam by driving steel pilings vertically into the streambed. The contract required plaintiff to drive these pilings to refusal (until they would sink no further). On the downstream side of these pilings, the contract demanded placement of rockfill support. To ensure timely completion of the project, the contract required plaintiff to work double shifts, six days a week.

The contract required Lang Brothers to submit a construction schedule. Plaintiff gave SCS a target date of June 22,1985 for completion of the cofferdam. Plaintiff began construction of the cofferdam on June 14, 1985, during the third construction season, but did not complete construction by the target date. During this period, plaintiff worked neither double shifts nor six days a week.

During installation, plaintiff did not drive all pilings to refusal. Rather, plaintiff intended to drive some pilings to refusal later. By June 28, 1985, however, some of the pilings had begun to bend and lean. In a letter dated July 2, 1985, SCS threatened to withhold payment if plaintiff did not immediately drive all pilings to refusal. SCS also reminded plaintiff of the vulnerability of the cofferdam to floods and its unwillingness to be responsible for damages due to failure of the pilings. Defendant’s Cross-Motion for Summary Judgment and Defendant’s Response to Plaintiff’s Motion for Summary Judgment, filed August 28, 1989 Exhibit 2, Appendix, at 3.

On July 9, 1985 — the onset of the heavy rain — plaintiff had installed all of the pilings. Plaintiff had not yet driven to refusal the pilings on the west section of the cofferdam. The rockfill — a necessary support behind the pilings — was not in place.

Plaintiff contends that the rockfill was not in place because the streambed had not yet been inspected. Plaintiff was respon[553]*553sible for arranging inspection of the streambed.

On July 9 and 10, 1985, heavy rains caused flooding at the construction site. The water crested at 630.4 feet. Plaintiff installed a drainage ditch to prevent the cofferdam’s collapse. This effort, however, was unsuccessful. The cofferdam collapsed. The pilings that collapsed had been driven to refusal. The pilings that were not driven to refusal were not affected by the flood.

On July 11, 1985, plaintiff petitioned the contracting officer for a modification of the contract. Plaintiff sought compensation for repairs to the damaged cofferdam and replacement of equipment. Plaintiff claimed entitlement to the modification under special provision 35 of the contract.

On January 6,1986 plaintiff made a $59,-030.44 claim for an equitable modification pursuant to special provision 35 of the contract and 41 U.S.C. § 605 (1978). The contracting officer denied plaintiffs claim on March 31, 1987. Plaintiff then filed this action in the United States Claims Court.

Plaintiff seeks payment for the cost of repairs to the cofferdam and replacement of damaged equipment. Plaintiff contends that special provision 35 assigns to SCS the risk of damages due to failure of the cofferdam. Plaintiff relies on the language of special provision 35 that provides an “equitable adjustment in costs to restore the damaged works.”

Plaintiff denies any fault for the cofferdam’s collapse. Plaintiff contends the contract did not specify when plaintiff had to drive the pilings to refusal. Moreover, plaintiff contends that it was not required to place the rockfill support concurrent with the pilings. Finally, plaintiff asserts that if the contract is ambiguous that SCS — as the drafter of the contract— should answer for the ambiguity.

In its cross motion for summary judgment, defendant contends that the contract read as a whole does not shift risk of loss to SCS until completion and acceptance of the work. Defendant also asserts that special provision 35 is unambiguous and only shifts risk to the Government for damage to the permanent dam.

Defendant contends further that plaintiff was at fault for the damage to the cofferdam.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nebco & Associates v. United States
23 Cl. Ct. 635 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,872, 20 Cl. Ct. 551, 1990 U.S. Claims LEXIS 215, 1990 WL 72509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lang-bros-v-united-states-cc-1990.