Lakewood Pipe of Texas, Inc. v. Conveying Techniques, Inc.

814 S.W.2d 553, 16 U.C.C. Rep. Serv. 2d (West) 1083, 1991 Tex. App. LEXIS 2143, 1991 WL 162337
CourtCourt of Appeals of Texas
DecidedAugust 22, 1991
Docket01-89-00995-CV
StatusPublished
Cited by27 cases

This text of 814 S.W.2d 553 (Lakewood Pipe of Texas, Inc. v. Conveying Techniques, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lakewood Pipe of Texas, Inc. v. Conveying Techniques, Inc., 814 S.W.2d 553, 16 U.C.C. Rep. Serv. 2d (West) 1083, 1991 Tex. App. LEXIS 2143, 1991 WL 162337 (Tex. Ct. App. 1991).

Opinion

OPINION ON MOTION FOR REHEARING

DUGGAN, Justice.

This is an appeal from a bench trial judgment awarding a manufacturer damages in the form of a cancellation charge for partially manufactured goods as a result of the buyer’s breach of an oral sales agreement. Appellant’s motion for rehearing is granted. We withdraw our earlier opinion, issued on July 3, 1991, and substitute this opinion in lieu thereof.

Appellee, Conveying Techniques, Inc. (“Conveying Techniques”), manufactures and fabricates conveying and material processing equipment. Appellant, Lakewood Pipe of Texas, Inc. (“Lakewood”), processes and sells steel pipe for the oil industry and agricultural irrigation. The two firms operate contiguous plants in Houston and occasionally sell goods and services to each other.

Conveying Techniques sold Lakewood a manual hydrostatic testing system in 1979. In April 1984, Conveying Techniques gave Lakewood a written proposal for the construction and installation of an automatic system. In May or June of 1984, the presidents of the two firms met at Conveying Techniques’ plant, where Conveying Techniques’ president, Roy Lee, demonstrated a prototype automated hydrostatic testing system to Lakewood's president, Frank Tybus. Lee testified that Tybus verbally agreed to buy the automated system for the $240,000 purchase price stated in the written proposal, by telling Lee to “go ahead with the project.” Tybus denied any such agreement and recalled only expressing an interest in the automated system. Conveying Techniques alleged that the automated system was designed expressly for Lakewood’s use.

Conveying Techniques began building the automated system in late 1984. Although Lakewood knew that Conveying Techniques was producing an automated system, Tybus testified for Lakewood that he and his firm did not know the system was being built expressly for Lakewood. On December 10, 1984, Lee wrote Earl Kimbal, Lakewood’s general manager, summarizing Conveying Techniques’ position regarding the agreement and reminding Kimbal that Conveying Techniques had agreed to start building the automatic system on the condition that all of Lakewood’s outstanding receivables would be paid. Lee noted that Conveying Techniques delayed building the system because Lakewood failed to pay, and was concerned that Lakewood would not pay before the system was installed. Lee requested that Lakewood complete payment so Conveying Techniques could build and install the equipment.

As of the date Lee’s letter was sent to Lakewood, December 10, 1984, Lakewood was $48,295.07 past due on its account with Conveying Techniques. 1 Lakewood made an additional purchase for $208.01 in January 1985, increasing its indebtedness to Conveying Techniques to $48,503.08. In turn, Conveying Techniques became indebted to Lakewood for a total of $62,672.63. In January 1985, the balance of accounts was in Lakewood’s favor by $14,169.55 ($62,672.63 - $48,503.08 = $14,169.55).

*555 Lakewood eventually notified Conveying Techniques in February 1985 that it “would not be in the market for the project.” Lee testified that Conveying Techniques stopped construction when Lakewood announced it could not satisfy its creditors. On March 5, 1985, Conveying Techniques invoiced Lakewood for $80,000, “30% of the Contract Sum of $240,000,” as “Cancellation Charges” on the automatic system.

Lee testified that he calculated the cancellation charge by “estimation.” He believed Conveying Techniques had spent more than $80,000 on the automatic system to this point, although he produced no records of actual expenses. He stated that installation of the unit, for which he had quoted $95,000, had not been started, and that a small amount of work on the system was still incomplete. Lee estimated that Conveying Techniques would “normally” have expended between $125,000 and $135,-000 in direct equipment costs from the time it started to the commencement of installation, not including overhead. Lee also testified that Conveying Techniques had pumps and other equipment intended for use in the job, containing approximately 30,000 pounds of steel, still situated at its place of business, for which Lakewood had not been given credit on its account. Lee stated that he could not testify as to what quantity of the materials had been used in the Lakewood project because he had not inventoried the remaining supplies. Lee thought that he could eventually sell some of the parts, although he had been unable to do so in the intervening five years before trial.

Based on this evidence, the trial court made the following findings:

(1) Lakewood entered into an oral agreement with Conveying Techniques to purchase the automated system;
(2) The two companies’ usual and customary manner of conducting business was by oral agreement;
(3) Tybus [on behalf of Lakewood] can-celled the order when the system was approximately three-fourths completed;
(4) Conveying Techniques spent approximately $125,000 in construction costs on the project before cancellation;
(5) $80,000 was a reasonable and necessary charge for cancellation of the agreement, based on the cost incurred in constructing the system;
(6) After allowing all offsets, Lakewood owed Conveying Techniques a balance of $65,830.45; and
(7) The automatic hydrostatic pressure testing system was specially manufactured for Lakewood and was not suitable for sale to others in the ordinary course of Conveying Techniques’ business.

The trial court allowed Lakewood no credit for pumps and other materials Conveying Techniques retained or used elsewhere.

In three points of error, Lakewood alleges (1) the use of an incorrect measure of damages (2) applied to damage findings supported by legally and factually insufficient evidence (3) destroys the basis for damages, attorney’s fees, and prejudgment interest.

The purpose of damages, including the remedies provided under the Texas Business and Commerce Code, is to place the injured party in as good a position as it would enjoy if the other party had fully performed under the contract. Stewart & Stevenson Servs., Inc. v. Enserve, Inc., 719 S.W.2d 337, 343 (Tex.App.—Houston [14th Dist.] 1986, writ ref’d n.r.e.); Tex.Bus. & Com.Code Ann. § 1.106(a) (Vernon 1968). To place the injured party in that position, damages must be measured by a “legal standard to guide the fact finder” in determining what sum would compensate for the injury. Turner v. PV Int’l Corp., 765 S.W.2d 455, 465 (Tex.App.—Dallas 1988), writ denied per curiam, 778 S.W.2d 865 (Tex.1989) (citing Jackson v. Fontaine’s Clinics, Inc., 499 S.W.2d 87, 90 (Tex.1973)). Thus, the facts of each case dictate the correct measure to be applied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrington Group, Ltd. v. Classic Cruise Holdings S De RL
435 F. App'x 382 (Fifth Circuit, 2011)
Dalisa, Inc. v. Bradford
81 S.W.3d 876 (Court of Appeals of Texas, 2002)
Cook Composites, Inc. v. Westlake Styrene Corp.
15 S.W.3d 124 (Court of Appeals of Texas, 2000)
In Re El Paso Refinery, L.P.
220 B.R. 37 (W.D. Texas, 1998)
El Paso Natural Gas Co. v. Minco Oil & Gas Co.
964 S.W.2d 54 (Court of Appeals of Texas, 1998)
Stamp-Ad, Inc. v. Barton Raben, Inc.
915 S.W.2d 932 (Court of Appeals of Texas, 1996)
General Electric Supply Co. v. Gulf Electroquip, Inc.
857 S.W.2d 591 (Court of Appeals of Texas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
814 S.W.2d 553, 16 U.C.C. Rep. Serv. 2d (West) 1083, 1991 Tex. App. LEXIS 2143, 1991 WL 162337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lakewood-pipe-of-texas-inc-v-conveying-techniques-inc-texapp-1991.