Lacy Manufacturing Co. v. Gold Crown Mining Co.

126 P.2d 644, 52 Cal. App. 2d 568, 1942 Cal. App. LEXIS 648
CourtCalifornia Court of Appeal
DecidedJune 9, 1942
DocketCiv. 13452
StatusPublished
Cited by37 cases

This text of 126 P.2d 644 (Lacy Manufacturing Co. v. Gold Crown Mining Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lacy Manufacturing Co. v. Gold Crown Mining Co., 126 P.2d 644, 52 Cal. App. 2d 568, 1942 Cal. App. LEXIS 648 (Cal. Ct. App. 1942).

Opinions

MOORE, P. J.

Plaintiff instituted this action to recover the balance due upon a contract and for extra labor performed and materials used in the dismantling, removal, and reconstruction of a mining mill and equipment for defendant which operated certain mining properties in San Bernardino County. The controversy revolves primarily about the extra charges.

In early September, 1938, the officers of the two corporations negotiated with a view to contracting for the removal of defendant’s milling plant from location K to a new location some six miles distant, hereafter referred to as location Y. The removal could be made only over a desert road not exceeding 18 feet in width through hills and woodlands. The mass of the equipment to be removed to Y is as follows:

A Hardinge Ball Mill, weight about 30,000 pounds,

1-280 horsepower Fairbanks and Diesel engine, weight about 32,175 pounds,

1-Dorr Classifier, weight about 4,500 pounds,

1-Dorr Thickener.

The Thickener was the important item in the list of articles to be removed. The reason for the omission of its weight from the above list will appear as we proceed. It is a cylindrical-shaped unit, 30 feet in diameter and 30 feet in height. Its exterior was a steel shell 5/16 of an inch in thickness in its lower 10 feet and 1/4 of an inch thick in its upper 20 feet. Within the shell is a large tank near the top, below which are four steel trays horizontally placed across the [571]*571entire width of the interior. Through the center of the tank and trays extends a vertical revolving shaft to which are attached rakes which stir the material to a thick consistency as it descends through the tank and several trays. In order to move and reconstruct the Thickener, it was necessary to dismantle it by cutting the shell and trays with an acetylene torch into sections, removing the rakes from the vertical shaft and by withdrawing the shaft itself. After transporting the mill from location K to location Y, it was necessary to bottom the tank upon new foundations; to reassemble the rakes to their accustomed places on the shaft and to re-establish the tank, trays, and shell by welding them into their original forms.

To effect such removal and reconstruction, defendant procured plans and specifications to be prepared by the Southwest Engineering Company, of which blue prints were made, one set of which was delivered to plaintiff in the early part of September, 1938, with a request for a bid for removal and reconstruction of the plant. A modified bid was submitted in writing by plaintiff September 30. It was accepted by defendant on the 10th day of October. The total basic amount of the contract was $9,587 plus the amount of sales taxes on parts supplied. The work to he done, as described in the contract, consisted of 15 items. Inasmuch as the controversy involves only items 14 and 15, those parts of the contract, not in issue, are omitted.

The substance of the agreement was that plaintiff should furnish the items “as specifically outlined below and in full accordance with the Southwest Engineering Company’s drawings referred to; all equipment to be delivered to plant site in the Dale District, near 29 Palms, California.”

Each item, after describing the materials to be furnished and the labor to be performed in removal and reconstruction, closes with the price and the amount of the sales tax. Items 14 and 15 as they appear in the contract are as follows:

“Item 14: Moving of one Dorr 5-compartment Thickener 30'0" diameter x 30'0" high, from the old mill site to new mill site including: removal of stirring apparatus, beam supports and all piping immediately supported by tank. Cut down of tank and trays in sections permitting hauling over normal road widths. Hauling of all of above to new mill site. Reassembly of tank, trays, apparatus and above mentioned piping on foundations to be prepared by Purchaser. Leveling [572]*572and adjustment that may be required to put tank back into its present operating condition. PRICE: complete, as listed above. $2,800.00. No California Sales Tax on this item.
“Note: This figure is based on an estimated total weight of 42% tons. We agree, upon reassembling this unit, to make a slight change in location of over-flow box and tray center overflows, and to substitute new shoes to be furnished by purchaser, with the understanding that this work does not involve the furnishing of any new material and that the changes will not interfere with the normal procedure of our work.
“Item 15: Moving from present foundations at the old mill site to foundations to be prepared by purchaser at new mill site:
“1-Diesel Engine, weighing approx. 32,175 pounds.
“1-Hardinge 6x22 Ball Mill, with or without liners weighing not over 30,000 pounds
“1-CIassifier, 20' long x 4 wide, weighing approx. 4,500 pounds
Price : For complete handling of three units $ 340.00 Total Price: For 15 items 9,587.00
Total California Sales Tax 143.63 ’ ’

Other covenants of the writing are: that plaintiff agrees “to complete delivery and installation of all items as listed above within 30 working days from date of contract”;

Terms :
“On the first day of each calendar month, sixty-five per cent (65%) of the price of all materials shipped and of all labor expended during the preceding month shall be invoiced for payment within 10 days after date of invoice. Balance of contract price shall be invoiced for payment forty-five (45) days after completion of contract.”

Upon the trial two factual conflicts developed: (1) whether defendant exhibited the blue print showing the changes to be made in the Thickener before the execution of the contract; (2) whether the contract price for item 14 was reduced by plaintiff from its original bid of $3,200 to the sum of $2,800 by reason of statements made by the president of defendant to the effect that the Thickener did not weigh 61 tons but only weighed 42% tons. The fabrication of the items was commenced by plaintiff immediately upon the execution of the contract by reason of untreated ore in its bins at location K. Defendant agreed to commence the removal on the [573]*57310th day of November. On the later date workmen appeared at location K and began the work of dismantling. Because of a water shortage the operations were closed down for some days. On the 21st day of January defendant accepted the plant as reconstructed at T. Other facts material to the controversy will appear in the recitals that follow but suffice it to say here that, after service of a statement of the full amount due only the sum of $6,361.80 was paid prior to the impasse that subsequently developed because of which plaintiff instituted this action.

Its complaint contained four counts, namely: (1) for the balance due on the basic charges in the sum of $3,368.83; (2) for the value of the extra services performed and materials furnished in the sum of $1,048.92; (3) for interest on the unpaid balances in the sum of $608.30; (4) upon an account stated in the sum of $5,026.05.

At the trial the court found the facts as contended by plaintiff and entered judgment thereon in its favor in the sum of $5,281.82.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NICO Alloys v. American Metal Group CA2/2
California Court of Appeal, 2015
Malmstrom v. Kaiser Aluminum & Chemical Corp.
187 Cal. App. 3d 299 (California Court of Appeal, 1986)
Chesapeake Industries, Inc. v. Togova Entreprises, Inc.
149 Cal. App. 3d 901 (California Court of Appeal, 1983)
Leaf v. Phil Rauch, Inc.
47 Cal. App. 3d 371 (California Court of Appeal, 1975)
Gerwin v. Southeastern California Ass'n of Seventh Day Adventists
14 Cal. App. 3d 209 (California Court of Appeal, 1971)
Biltmore Press v. Usadel
6 Cal. App. 3d 896 (California Court of Appeal, 1970)
Overland Machined Products, Inc. v. Swingline, Inc.
263 Cal. App. 2d 642 (California Court of Appeal, 1968)
Engle v. City of Oroville
238 Cal. App. 2d 266 (California Court of Appeal, 1965)
General Electric Co. v. Central Surety & Insurance
232 Cal. App. 2d 590 (California Court of Appeal, 1965)
Goble v. Dotson
203 Cal. App. 2d 272 (California Court of Appeal, 1962)
Mahoney v. Founders' Insurance
190 Cal. App. 2d 430 (California Court of Appeal, 1961)
Handley v. Guasco
332 P.2d 354 (California Court of Appeal, 1958)
Anderson-Prichard Oil Corp. v. Parker
245 F.2d 831 (Tenth Circuit, 1957)
Norman v. Tully
308 P.2d 875 (California Court of Appeal, 1957)
Muller v. Barnes
294 P.2d 505 (California Court of Appeal, 1956)
Ward Manufacturing Co. v. Miley
281 P.2d 343 (California Court of Appeal, 1955)
Abramowitz v. Bank of America
281 P.2d 380 (California Court of Appeal, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
126 P.2d 644, 52 Cal. App. 2d 568, 1942 Cal. App. LEXIS 648, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lacy-manufacturing-co-v-gold-crown-mining-co-calctapp-1942.