Labrador Oil Co. v. Norton Drilling Co.

1 S.W.3d 795, 143 Oil & Gas Rep. 308, 1999 Tex. App. LEXIS 6297, 1999 WL 642215
CourtCourt of Appeals of Texas
DecidedAugust 24, 1999
Docket07-98-0142-CV
StatusPublished
Cited by40 cases

This text of 1 S.W.3d 795 (Labrador Oil Co. v. Norton Drilling Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Labrador Oil Co. v. Norton Drilling Co., 1 S.W.3d 795, 143 Oil & Gas Rep. 308, 1999 Tex. App. LEXIS 6297, 1999 WL 642215 (Tex. Ct. App. 1999).

Opinion

DON H. REAVIS, Justice.

Labrador Oil Company appeals from a judgment based in part upon a jury verdict in favor of Norton Drilling Company awarding recovery for balance owing for daywork charges under a standard IADC written contract 1 for the drilling of a well, and recovery for damage to or loss of Norton’s drill pipe. By five issues, Labrador contends the trial court erred (1) in disregarding the jury’s answer to Question 6 concerning Labrador’s mitigation of damages, (2) when it refused to reduce Norton’s judgment by the salvage value of the damaged drill pipe retained by Norton, (3) when it failed to establish the salvage value offset to which Labrador was entitled at $166,650.00, (4) by applying the wrong measure of prejudgment and post-judgment interest and granted an incorrect judgment for interest in favor of Norton, and (5) by refusing to grant Labrador leave to file a trial amendment. Norton also presents one cross-issue contending the trial court erred in rendering a judgment based on the jury’s answer to Question 7, which inquired as to the amount of reimbursement owed for the damage or loss of in-hole equipment belonging to Norton, because the jury’s answer lacked the requisite evidentiary support. Based upon the rationale expressed herein, we will affirm.

Labrador (as operator) and Norton (as contractor) entered into a written con *797 tract 2 for the drilling of a well to an anticipated depth of 19,000 feet, using the IADC form contract. In the oil and gas industry, wells are commonly drilled on “turnkey,” “footage,” or “day rate” contracts. 3 Here, the parties agreed to drill the well on a “daywork basis” under the “direction, supervision and control” of Labrador. As relevant, subparagraph 4.4 entitled “Operating Day Rate” provided that the day rate compensation would be $6,216.00 if Norton provided the drill pipe, but if Labrador’s drill pipe was used, the daily rate would be $6,000.00. Also, it contained a special provision that “after 100 days the dayrate will go to $6000.00/ day with or without drill pipe.” In addition, subparagraph 14.2 provided as follows:

14.2 Contractor’s In-Hole Equipment: Operator shall assume liability at all times for damage to or destruction of Contractor’s in-hole equipment, including, but not limited to, drill pipe, drill collars, and tool joints, and Operator shall reimburse Contractor for the value of any such loss or damage; the value to be determined by agreement between Contractor and Operator as current repair costs or 80 percent of current new replacement cost of such equipment delivered to the well site. 4

Norton’s rig inventory, which was attached to the IADC contract, showed among other things, 21,000 feet of drill pipe on hand. However, before Labrador signed the contract, Norton sent Labrador the following message:

Mike, I found 19 drill pipe inspections covering the period from February 1995 to present. I found 3227 jts inspected, 2786 jts premium for 86.33% good usable pipe and 13.67% unusable. If you agree we can use these figures to determine fair wear and tear. Any losses you will replace or pay for beyond 13.67%. Let me hear from you so we can get started moving the rig.

The contract also provided that Labrador would pay Norton $91,000.00 as a demobilization fee but by letter agreement dated May 10, 1996, the parties agreed that the fee would be $50,000.00 if only one well was drilled.

Inspections of Norton’s drill pipe components were made by Labrador and Labrador accepted the components as in compliance with industry standards before commencement of drilling operations on June 28, 1996. A few days after drilling commenced, drilling operations were suspended and “fishing” commenced because a shock sub furnished by Labrador parted. Drilling operations resumed but problems impaired operations from time to time. Labrador ceased using some of the components provided by Norton; however, Labrador continued using other components provided by Norton until the hole had reached a depth of near 13,000 feet. After Labrador determined that Norton’s drill pipe had worn below industry standards and was no longer suitable, it ceased using Norton’s damaged drill pipe. Labrador recognized its responsibility to repair or replace the drill pipe, but decided at that time to continue drilling operations with rented replacement pipe instead of repairing or replacing the damaged pipe on site. However, drilling ceased after several thousand feet of drill pipe, which included some components supplied by Norton, fell into the hole after a rental component failed, and the rig was released November 1, 1996. Following Labrador’s failure to pay Norton’s invoices and replacement of the lost or damaged portion of Norton’s drill pipe, Norton filed suit.

*798 By its trial pleading, Norton sought to recover $50,000.00 for demobilization expense, the balance owing on the daywork contract in the amount of $302,298.97, and 80% of the new replacement cost of its damaged or lost equipment which included 439 joints of drill pipe, interest and other damages. Labrador responded by alleging numerous affirmative defenses, set off and a counterclaim, including Norton’s negligence, fraud, breach of contract and Deceptive Trade Practices Act violations. 5 Upon completion of a six-day trial, the trial court submitted its charge which included eight questions. By its answers, the jury found that (1) both Labrador and Norton failed to comply with the written agreement, which the court instructed included the IADC contract, the rig inventory, and the May 10, 1996 letter agreement; (2) Norton engaged in false, misleading or deceptive acts or practices which was a producing cause of damages; (3) Norton did not knowingly engage in such conduct; (4) Norton made a negligent misrepresentation on which Labrador justifiably relied; (5) the balance owing to Norton for day-work charges was $302,298.97; (6) the reasonable and necessary expense of Labrador in renting replacement drill pipe was $60,406.99, and that the reasonable value of time spent by Labrador due to the problems caused by Norton’s failure to comply with the agreement was $7,456.00; (7) the value of the replacement pipe due to Norton was $127,400.00; and (8) the salvage value of Norton’s drill pipe was $26,895.00.

Following consideration of Norton’s motion to disregard jury findings to Questions 2, 4, 6, 7, and 8, the trial court granted the motion as to Question 8 ($26,-895.00 salvage value of Norton’s drill pipe), and partially granted the motion as to Question 6, disregarding the jury finding that $60,406.99 was the reasonable cost of renting replacement drill pipe, and denied the motion as to the remaining questions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rebeca D. Balderas-Ramirez v. Anthony CarlDP
537 S.W.3d 625 (Court of Appeals of Texas, 2017)
Minor, Ex Parte Juliane Myra
Court of Appeals of Texas, 2015
Paul Edward Hudson v. Dallas County
Court of Criminal Appeals of Texas, 2015
Doreatha Walker v. Hitchcock ISD
Court of Appeals of Texas, 2013
Rene Daniel Sandoval v. State
Court of Appeals of Texas, 2005
Daniel Lewis Leal v. State
Court of Appeals of Texas, 2005
Akinwamide v. Transportation Insurance Co.
147 S.W.3d 623 (Court of Appeals of Texas, 2004)
in the Interest of S. G., a Child
153 S.W.3d 479 (Court of Appeals of Texas, 2004)
Dunn v. Bank-Tec South
134 S.W.3d 315 (Court of Appeals of Texas, 2003)
Tom Richard Doyle, Jr. v. State
Court of Appeals of Texas, 2003
State v. Detria McIntosh
Court of Appeals of Texas, 2003
Jim Stacy Smith v. State
Court of Appeals of Texas, 2003

Cite This Page — Counsel Stack

Bluebook (online)
1 S.W.3d 795, 143 Oil & Gas Rep. 308, 1999 Tex. App. LEXIS 6297, 1999 WL 642215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/labrador-oil-co-v-norton-drilling-co-texapp-1999.