Greenbelt Electric Cooperative, Inc. v. Johnson

608 S.W.2d 320, 1980 Tex. App. LEXIS 4032
CourtCourt of Appeals of Texas
DecidedOctober 31, 1980
Docket9156
StatusPublished
Cited by26 cases

This text of 608 S.W.2d 320 (Greenbelt Electric Cooperative, Inc. v. Johnson) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenbelt Electric Cooperative, Inc. v. Johnson, 608 S.W.2d 320, 1980 Tex. App. LEXIS 4032 (Tex. Ct. App. 1980).

Opinion

REYNOLDS, Chief Justice.

By this limited appeal, Greenbelt Electric Cooperative, Inc. seeks to overturn a judgment, rendered on a jury verdict, decreeing its monetary liability for breach of contract to furnish electric service to Bill Johnson. Because Johnson failed to prove a contractual duty by Greenbelt to furnish him electric service, we reverse and render.

In 1972, Johnson began the operation of Syd Blue’s Restaurant and Lounge in a building situated in Howardwick, Donley County. By written instrument, the building was leased to Johnson by George Howard, the owner, for a five-year term. On 24 March 1972, Greenbelt and Johnson contracted in writing for the furnishing and use of electric power and energy for the building. The contract was for a term of five years “and thereafter until terminated by either party giving to the other-months notice in writing.” A provision in the contract, known to Johnson at all times, specified that the bill for service shall be paid

*322 Monthly on the 25th of each month or as soon thereafter as the bill is received and 10% penalty will be added if not paid by the 10th of the following month, with service being disconnected on the 21st if no payment is received.

Greenbelt’s billings, made to Syd Blue’s Restaurant and Lounge, were paid by draft drawn on Johnson’s bank account.

In August of 1974, Johnson sold the business to Olin Castleberry, who began operating it at that time, although the written instruments of the transaction are dated 31 October 1974. 1 Johnson retained a security interest in the personalty sold to secure the payment of the deferred portion of the purchase price. The contract of sale contained Johnson’s agreement not to participate in a competing business within a fifty mile radius of Howardwick for a period of three years. Johnson ceased paying rent under his lease with Howard and, at Johnson’s request, Howard substituted Castleberry as the tenant with a new five-year lease beginning in August, 1974.

At the time of the sale, Johnson contacted Greenbelt, advising the office manager of the sale to Castleberry and that “the meter needed to be read out, and the future bills would be billed to him [Castleberry].” It was established that Johnson did not request the termination of his contract with Greenbelt. Johnson testified he did not intend that his contract with Greenbelt be terminated, and he intended to re-take possession if Castleberry defaulted. Johnson received the final bill requested and he did not, nor expect to, receive any more bills. He acknowledged that the payment of future bills would be between Greenbelt and Castleberry.

Castleberry executed an application for membership in Greenbelt, agreeing to purchase all electric energy used on the premises, and paid his membership fee in August, 1974. Castleberry did not pay for his elec-trie usage from January 5 to February 5, 1975. 2 A collection notice, which would have been mailed March 14 under Greenbelt’s procedure, was received .by Greenbelt’s area service representative, who went to see Castleberry. Castleberry said he would pay the bill the next day, but did not and, when again contacted, he requested, but was denied, another extension.

Meanwhile, about the first week in March, Castleberry had defaulted in his payments to Johnson. When, on or about March 6, Johnson inquired, Castleberry said he could not afford the payments, adding, “I am busted. I am through. It is all yours.” Castleberry gave the keys to Johnson.

Later, Johnson went upon the premises to clean up the equipment. He observed the perishable merchandise was stored in the freezers and iceboxes and there was electricity to the building. During the cleaning some two or three days before March 20, Johnson, who was not going to use the building any more, arranged with Howard to put a food service, a steak house, in the back of a nearby building being used as a lounge. Johnson was going to use the equipment and merchandise in the operation of the steak house, and Howard agreed the merchandise could be left while Johnson was remodeling the back portion of the nearby building. Johnson began remodeling on March 20, working several hours each day without going back to the building Castleberry had vacated until the first day of April. During this period of time, Johnson made no inquiry to Greenbelt; and neither he, nor anyone else so far as he knew, informed Greenbelt, and Greenbelt did not know, that perishables had been left in the building.

Because, according to Greenbelt’s records, the $383.18 Castleberry owed for electric usage since January 5 remained unpaid on March 31, the area representative was instructed to “pull the meter.” He did so, as *323 recorded, on March 31. Greenbelt gave no notice to nor contacted anyone at that time; however, some two hours later, Howard, who fixed the date as March 20 or 21, became aware that the electric service was terminated. He inquired of, and was informed by, Greenbelt’s representative of the reason. Howard then requested the reinstallation of the meter because his son, Jeff Howard, “was going to open [a beer and wine store in the building] in about ten days.” After being told that Castleberry’s bill would have to be paid, Howard asked the representative to see his son. Jeff Howard, fixing the date as March 19 or 20, requested electric service to the building for his proposed operation, and was told that Castleberry’s bill would have to be paid before service would be supplied to the building. No one reported these events to Johnson.

When Johnson returned to the building on April the first, or perhaps the second, he found the perishable food was spoiled. In his opinion, the electricity had been off for several days. The perishables had a pre-spoilage value, he opined, of about $4,000.

Thereafter, the cause underlying this appeal came before the court on pleadings filed by Johnson and others. 3 In answering the special issues submitted on the cause, the jury found that (1) at the time the meter was removed, Johnson and Greenbelt had a contract for Greenbelt to furnish electric service to the building; (2) the removal of the meter by Greenbelt was a breach of such contract; and (3) Johnson suffered damage as a result of the breach (4) in the amount of $4,000. 4 Judgment was rendered on the verdict, decreeing, inter alia, that Johnson recover $4,000 from Greenbelt, to which Greenbelt has limited its appeal.

The threshold inquiry is whether Greenbelt was obligated by the 1972 contract to furnish Johnson electric service at the time the meter was removed in 1975. Johnson supplies an affirmative answer on the theory that the meter was placed at his request and serviced under the contract, he had committed no breach, and neither party had notified the other of the termination of the contract. A negative answer is required, Greenbelt theorizes, because Johnson and Greenbelt had no contract at the time the meter was removed, the substitution of Castleberry for Johnson as a party to the contract operating, if not to terminate the contract, 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FPL Farming Ltd. v. Environmental Processing Systems, L.C.
383 S.W.3d 274 (Court of Appeals of Texas, 2012)
Wes-Tex Tank Rental, Inc. v. Pioneer Natural Resources USA, Inc.
327 S.W.3d 316 (Court of Appeals of Texas, 2010)
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 2007
Opinion No.
Texas Attorney General Reports, 2006
Flagship Hotel, Ltd. v. City of Galveston
117 S.W.3d 552 (Court of Appeals of Texas, 2003)
Flagship Hotel, Ltd. v. the City of Galveston
Court of Appeals of Texas, 2003
Jack Lewis v. Normandy Apartments
Court of Appeals of Texas, 2003
Labrador Oil Co. v. Norton Drilling Co.
1 S.W.3d 795 (Court of Appeals of Texas, 1999)
Ghidoni v. Stone Oak, Inc.
966 S.W.2d 573 (Court of Appeals of Texas, 1998)
Boudreaux Civic Ass'n v. Cox
882 S.W.2d 543 (Court of Appeals of Texas, 1994)
M.N. Dannenbaum, Inc. v. Brummerhop
840 S.W.2d 624 (Court of Appeals of Texas, 1992)
Sowell v. Northwest Central Pipeline Corp.
703 F. Supp. 575 (N.D. Texas, 1988)
Villa Nova Resort, Inc. v. State
711 S.W.2d 120 (Court of Appeals of Texas, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
608 S.W.2d 320, 1980 Tex. App. LEXIS 4032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenbelt-electric-cooperative-inc-v-johnson-texapp-1980.