Kopplow Development, Inc. v. the City of San Antonio

399 S.W.3d 532, 56 Tex. Sup. Ct. J. 354, 2013 WL 854320, 2013 Tex. LEXIS 178
CourtTexas Supreme Court
DecidedMarch 8, 2013
Docket11-0104
StatusPublished
Cited by54 cases

This text of 399 S.W.3d 532 (Kopplow Development, Inc. v. the City of San Antonio) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kopplow Development, Inc. v. the City of San Antonio, 399 S.W.3d 532, 56 Tex. Sup. Ct. J. 354, 2013 WL 854320, 2013 Tex. LEXIS 178 (Tex. 2013).

Opinion

Justice GUZMAN

delivered the opinion of the Court.

In this case we determine whether an inverse condemnation claim is premature when premised on the owner’s inability to develop its property as the city previously approved. The landowner purchased the property for the purpose of developing the land, obtained permits, and filled the portion of the property at issue in this proceeding to the 100-year flood level. The municipality then constructed a facility partly on the property that would detain storm water on the property in a significant flood, thus causing the property to again be below the 100-year flood level and undevelopable without additional fill. The landowner sought damages under statutory and inverse condemnation theories. The jury awarded damages of $694,600 and the trial court entered judgment on the verdict. The court of appeals reversed as to the inverse condemnation claim, holding the claim was premature because the property had not yet flooded. Because we conclude that the landowner’s claim is for the present inability to develop the property as previously approved unless the property is filled, we hold the claim is not premature. Accordingly, we reverse the judgment of the court of appeals and *534 remand to the court of appeals for further proceedings.

I. Background

Kopplow Development, Inc. (Kopplow) purchased 18.451 acres of land adjoining Loop 410 in San Antonio in 1996 or early 1997. 1 After retaining an engineering firm, Kopplow filed a plat application on November 27, 1996 and obtained utility and construction easements on the adjoining tract south of its property to connect sewer service. Because Kopplow’s property was below the 100-year floodplain elevation of 741 feet above mean sea level, as defined by the Federal Emergency Management Agency (FEMA), Kopplow obtained a floodplain permit from the City of San Antonio (City) and filled most of the property to 741 feet in 2000. About one fourth of the property still fell within the 100-year floodplain, and Kopplow dedicated a drainage easement over this area. In 2004, the City granted Kopplow a vested rights permit, allowing it to develop the property under the rules in effect in November 1996 when Kopplow filed its plat application. A vested rights permit insulates pending development from most future ordinance changes. But certain floodplain regulation changes apply retroactively even against vested rights holders. See Tex. Loc. Gov’t Code §§ 245.002, 245.004(9).

San Antonio experienced 100-year floods in 1998 and 2002. The City then planned a regional storm water detention facility for the Leon Creek watershed south of Kopplow’s property to mitigate downstream flooding. It determined in 2002 that the project would inundate portions of Kopplow’s property and the tract south of Kopplow’s property. The City asked Kopplow in late 2008 to donate an easement that the City planned to inundate as part of the project. Kopplow refused. The City obtained a 207-acre drainage easement from the owner of the property south of the Kopplow tract in January 2004 and then built a concrete inflow wall on the portion of the adjoining tract that includes Kopplow’s easements (where Kopplow’s easements and the City’s drainage easement overlap on the property south of the Kopplow tract). The City also built a large berm or dam south of the Kopplow property. The dam’s peak elevation is 748 feet. Once Leon Creek reaches the height of the in-flow wall in a 10-year flood, the wall will guide storm water to be detained by the berm until storm water in Leon Creek subsides, allowing drainage pipes in the berm to open and slowly return the detained water into Leon Creek.

The parties agree the facility will cause increased inundation on Kopplow’s property and that the FEMA 100-year floodplain is two feet higher on Kopplow’s property because of the facility. But the City asserts that the in-flow wall does not cause the increased inundation because it is under water in a 100-year flood and instead that the berm causes the increased inundation.

The City also changed its regulatory 100-year floodplain to account for future, upstream development. 2 A City representative testified that, although Kopplow must file for a floodplain development per *535 mit to further develop its property, the City will permit Kopplow to develop its property if it fills the property to the new level of the 100-year floodplain. Ultimately, Kopplow must fill the portion of its property to be developed from the existing 741-foot level to 745.16 feet: two feet due to the detention facility and two feet due to the City’s ordinance change.

Kopplow sued the City for a taking in May 2004 while it was constructing the facility. The City counterclaimed for condemnation of Kopplow’s easement. Before trial, the trial court granted the City’s motion that Kopplow’s vested rights permit was not effective against subsequent floodplain ordinances and excluded Kop-plow’s evidence pertaining to two of the four feet of additional fill needed to develop the property. 3 The jury found that: (1) the value of the part taken was $4,600; (2) the City’s use of the part taken proximately caused damages to the remainder; and (3) Kopplow’s remainder damages were $690,000.

The City and Kopplow both appealed. The court of appeals affirmed the $4,600 damage award for the part taken under the statutory takings claim. 335 S.W.3d 288, 296. It reversed the award of remainder damages under the statutory takings theory, holding that the inflow wall would not inundate Kopplow’s property, even during a 100-year flood. Id. at 294-95. The court also held the remainder damages unrecoverable under Kopplow’s inverse condemnation theory because the property had not yet flooded and the inverse condemnation claim was therefore premature. Id. at 296. In light of its holding, the court of appeals did not reach the City’s factual sufficiency challenge or Kopplow’s two cross-appeal points. 4 Id. at 296-97.

II. Discussion

We have described the right to own private property as “fundamental, natural, inherent, inalienable, not derived from the legislature and as preexisting even constitutions.” Eggemeyer v. Eggemeyer, 554 S.W.2d 137, 140 (Tex.1977). One of the most important purposes of our government is to protect private property rights. Id. The Texas Constitution resolves the tension between private property rights and the government’s ability to take private property by requiring takings to be for public use, with the government paying the landowner just compensation. Tex. Const. art. I, § 17 (“No person’s property shall be taken, damaged, or destroyed for or applied to public use without adequate compensation being made.... ”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The City of Lake Jackson v. Ricky Adaway
Court of Appeals of Texas, 2023
Victor Antolik v. Dennis Antolik
Court of Appeals of Texas, 2021
Terry Aslin v. Coryell County, Texas
Court of Appeals of Texas, 2021
B.G.C. v. M.Y.R.
Court of Appeals of Texas, 2020
In re Odebrecht Constr., Inc.
548 S.W.3d 739 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
399 S.W.3d 532, 56 Tex. Sup. Ct. J. 354, 2013 WL 854320, 2013 Tex. LEXIS 178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kopplow-development-inc-v-the-city-of-san-antonio-tex-2013.