Howard v. City of Kerrville

75 S.W.3d 112, 2002 Tex. App. LEXIS 1636, 2002 WL 340580
CourtCourt of Appeals of Texas
DecidedMarch 6, 2002
Docket04-01-00063-CV
StatusPublished
Cited by19 cases

This text of 75 S.W.3d 112 (Howard v. City of Kerrville) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Howard v. City of Kerrville, 75 S.W.3d 112, 2002 Tex. App. LEXIS 1636, 2002 WL 340580 (Tex. Ct. App. 2002).

Opinion

Opinion by:

PAUL W. GREEN, Justice.

Appellant Louis M. Howard brought suit against the City of Kerrville (“the City”) and the Upper Guadalupe River Authority (“the UGRA”) claiming that the dam they constructed on the Guadalupe River and the concomitant city regulations have resulted in a taking of his river front property. The trial court granted the City’s and the UGRA’s motions for summary judgment, and it awarded them attorney’s fees. Howard now appeals the trial court’s denial of his takings claims and the award of attorney’s fees. After reviewing the record, we affirm the trial court’s judgment in part, and reverse it in part.

Statement of Facts

In 1977, the City of Kerrville entered into a water supply contract with the UGRA to build a dam on the Guadalupe River. Before constructing the dam, the UGRA acquired a permanent flood easement across 6.03 acres of land owned by Howard’s predecessor in title. The easement provided that the anticipated flood plain level for the 100 year flood plain was approximately 1640.5 feet mean sea level (m.s.l.) plus one foot. 2 Therefore, Howard’s predecessors in title were required to fill their property to 1641.5 m.s.l (the base flood elevation plus one foot).

In 1978, the City passed Ordinance No. 78-9, which adopted the first flood plain maps prepared by the Federal Emergency Management Agency (“FEMA”). According to the City’s interpretation, the FEMA map placed all but a narrow strip of the property at issue in the 100 year flood way. 3 Furthermore, under that ordinance *115 no development was permitted in the flood way without a permit from the City’s flood plain administrator.

In 1982, FEMA published findings of fact on the flood way and the base flood elevations of the Guadalupe River. These findings were predicated on a peak flood of 155,000 cubic feet per second (“c.f.s.”) which has a probability of occurring every 100 years. These 1982 findings were adopted in" a flood insurance rate map (“FIRM”). The 1982 FIRM also established that the base flood elevation for Howard’s property was at an approximate average level of 1640.5 feet.

In December of 1984, the original dam built was destroyed by a flood. In January 1985, Espey-Huston & Associates (“Espey-Huston”), an engineering and hydrology firm, assessed the damage, and eventually, the dam was rebuilt in its place, using the same general specifications as the original dam. In 1985, Howard’s predecessors obtained approval from the City of Kerrville for a subdivision plat, known as the K-Bob Addition. This plat showed the contours of the UGRA easement burdening the property and contained the express condition that any flood way fill or development required prior certification by an engineer and approval by the City and the UGRA.

In August of 1989 Howard bought the disputed property. Howard concedes that, at the time of his purchase, he was aware of the 1980 agreement and easement. Sometime after Howard purchased his property, the City and the UGRA discovered that the 1982 FEMA flood plain maps did not account for the impact that the original dam had on the flood plain. Accordingly, in 1993, the City commissioned Epsey-Huston to determine the accurate ements of the flood itigation, Espey-Hu-to update the flood ly indicated that the id the existing flood .1, which was above ⅛ property had been contours and measu plain. After its inv< ston issued a repor plain maps. The sti new dam had expan plain to 1646 feet m the level that Howar filled. After the Epsey-Huston report was published, the City petitioned FEMA to revise the map to include these changes. In addition, the City requested a separate delineation of the flood way and flood fringe for the Guadalupe River, the latter of which is subject to fewer development restrictions. As a result of the new study, the majority of Howard’s land was removed from its prior designation as “flood way” and consigned to “flood fringe.”

At approximately the same time Espey Huston published its study, Howard applied for a permit to build a shopping center on his property. Initially, Howard submitted his application to the City, but the City’s staff recommended revisions. Howard apparently implemented those recommendations and then resubmitted his application to the City Council. After Howard’s proposal was placed on the City Council’s agenda, however, the City passed Ordinance No. 94-105, which declared a temporary moratorium on all land development believed to be in the expanded flood plain. The moratorium lasted approximately seven months. Howard’s permit was therefore denied pending the outcome of the FEMA flood plain map revisions.

In 1995, Espey-Huston issued another report that indicated that the probable flow rate in the Guadalupe River was 215,-000 c.f.s. and that the base flood elevation of Howard’s property was 1648 feet m.s.l. As a result, the City Council passed anoth- *116 expanded the scope the new base flood City submitted the study to FEMA an flood way and flood er ordinance, Ordin; ice No. 95-30, which if the moratorium to elevation line. The 1995 Espey-Huston 1 requested that the plain relative to the area upstream of tqe dam be revised in accordance with the new data.

In April 1997, FEMA published new findings of fact regarding the base flood elevation of the Guadalupe River, which took into account the presence of the dam and the increased flow rate of the Guadalupe River. The findings of the flood way and the base flood elevation were predicated upon a peak flood of 215,000 c.f.s. Because neither the City nor the UGRA appealed these findings, they became final by operation of law, on July 27, 1997. The 1997 base flood elevation determined for Howard’s property was approximately 1648.5 feet, and so he was required to fill his property to the level of 1649.5 feet m.s.l. (the required base flood elevation plus one foot). After these new regulations were adopted, Howard did not ask the City to reconsider his original permit application. Howard later applied for a permit to build a used car dealership, but he subsequently withdrew that application claiming that the regulations were “too extraordinary to comply with.”

On or about October 29, 1997, Howard notified the City and the UGRA, in writing, that the new water elevation exceeded the easement previously granted by Howard’s predecessors in title and the new elevation requirement threatened his property with flooding. He also notified them that he intended to seek damages or in-junctive relief if the threat of flood was not abated. The City and the UGRA never responded to his notice.

Therefore, in September 1998, Howard sued the City and the UGRA, alleging constitutional takings, threat of trespass, and breach of contract (to which Howard claimed to be a third party beneficiary). The City and the UGRA both filed motions for summary judgment on all claims against them. Howard filed a motion for partial summary judgment on his taking of an easement claim. The trial court granted the City’s and the UGRA’s motions, denied Howard’s motion, and awarded the City and the UGRA attorney’s fees. Howard now appeals the trial court’s judgment on his takings claims under Article I, section 17 of the Texas Constitution and the award of attorney’s fees.

STANDARD OP REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Buda v. N. M. Edificios, LLC
Court of Appeals of Texas, 2024
Cenizo Corporation v. City of Donna
Court of Appeals of Texas, 2013
Kopplow Development, Inc. v. the City of San Antonio
399 S.W.3d 532 (Texas Supreme Court, 2013)
Bexar County v. Dominick Colombrito
Court of Appeals of Texas, 2012
SM Energy Co. v. Sutton
376 S.W.3d 787 (Court of Appeals of Texas, 2012)
City of San Antonio v. Kopplow Development, Inc.
335 S.W.3d 288 (Court of Appeals of Texas, 2010)
Lacey Kersey v. State
Court of Appeals of Texas, 2006
Oscar M. Telfair, III, P.C. v. Bridges
161 S.W.3d 167 (Court of Appeals of Texas, 2005)
Flagship Hotel, Ltd. v. City of Galveston
117 S.W.3d 552 (Court of Appeals of Texas, 2003)
Flagship Hotel, Ltd. v. the City of Galveston
Court of Appeals of Texas, 2003

Cite This Page — Counsel Stack

Bluebook (online)
75 S.W.3d 112, 2002 Tex. App. LEXIS 1636, 2002 WL 340580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/howard-v-city-of-kerrville-texapp-2002.