Kiely Construction, L.L.C. v. City of Red Lodge Ex Rel. Red Lodge City Council

2002 MT 241, 57 P.3d 836, 312 Mont. 52, 2002 Mont. LEXIS 502
CourtMontana Supreme Court
DecidedNovember 1, 2002
Docket01-200
StatusPublished
Cited by94 cases

This text of 2002 MT 241 (Kiely Construction, L.L.C. v. City of Red Lodge Ex Rel. Red Lodge City Council) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiely Construction, L.L.C. v. City of Red Lodge Ex Rel. Red Lodge City Council, 2002 MT 241, 57 P.3d 836, 312 Mont. 52, 2002 Mont. LEXIS 502 (Mo. 2002).

Opinions

JUSTICE COTTER

delivered the Opinion of the Court.

¶1 This appeal arises from decisions by the Red Lodge City Council and rulings by the Twenty-Second Judicial District Court concerning an application for a subdivision, its conditioned approval, and ultimate denial, as well as from special and advisory jury verdicts. We affirm in part and reverse in part.

¶2 After receiving a preliminary plat application for a proposed subdivision from Kiely Construction (Kiely), the Carbon County Planning Board recommended approval of the proposed subdivision, subject to eighteen conditions, to the City of Red Lodge (Red Lodge). Red Lodge received the application in the Summer of 1996, but failed to act upon it within sixty days. Kiely obtained a Writ of Mandamus in August of 1997, compelling Red Lodge to act upon the application, and Red Lodge conditionally approved Kieiys application, subject to twenty-six conditions. On October 14, 1997, Kiely filed a complaint, alleging that Red Lodge failed to act within the mandatory sixty-day time frame, that imposition of some conditions were an abuse of discretion, and that its due process rights were violated.

¶3 Following mediation in the Fall of 1998, the parties negotiated a subdivision improvements agreement, which Red Lodge conditionally [58]*58accepted, but Kiely then rejected. On March 20, 1999, the District Court entered partial summary judgment, ordering Red Lodge to review and “approve, conditionally approve or deny,” Kiely’s application within thirty days. Following a public hearing, Red Lodge City Council unanimously denied Kiely’s application without written findings. Kiely then filed an amended complaint, alleging constitutional violations and requesting damages and approval of its application. Prior to trial, the District Court entered partial summary judgment, dismissing Kiely’s claims against the individually named defendants.

¶4 At trial, Kiely sought damages for the alleged arbitrary or capricious denial of its application. The jury’s special verdict awarded Kiely $292,170.00 in damages for Red Lodge’s arbitrary and capricious actions pursuant to state law, and also found for Kiely on its constitutional claims under 42 U.S.C. § 1983, but awarded damages in the sum of only $1.00. Kiely had also appealed to the District Court from Red Lodge’s denial of its preliminary plat application. The District Court accepted the jury’s advisory verdict on this issue, and concluded that Red Lodge acted arbitrarily, capriciously and unlawfully, and ordered Red Lodge to conditionally approve Kiely’s preliminary plat application, subject to the original eighteen conditions. The District Court awarded Kiely $250,243.50 in attorney’s fees pursuant to 42 U.S.C. § 1988, and also awarded costs. Red Lodge appeals several of the District Court’s pre-trial, trial, and post-trial rulings, while Kiely cross-appeals two of the court’s summary judgment rulings.

¶5 We restate the issues as follows:

1. Whether the District Court erred in submitting Kiely’s 42 U.S.C. § 1983 claims to the jury;

2. Whether the District Court erred in awarding Kiely attorney’s fees pursuant to 42 U.S.C. § 1988;

3. Whether the District Court abused its discretion when instructing the jury on Kiely’s state law claims;

4. What relief Kiely is entitled to under its state law claims;

5. Whether the District Court erred in dismissing the individual defendants by order of summary judgment;

6. Whether the District Court abused its discretion regarding admission of evidence; and

7. Whether the District Court erred by not modifying the damage award.

[59]*59FACTUAL AND PROCEDURAL BACKGROUND

¶6 In the Spring of 1996, Kiely initiated the approval process for its proposed subdivision, referred to as Kiely Island at Rock Creek, and located within the City of Red Lodge, Carbon County, Montana. On May 16, 1996, Kiely submitted a preliminary subdivision plat application to the Carbon County Planning Board, because at the time, Red Lodge did not have a city planning board in place. Following a public hearing on June 18, 1996, the County Planning Board recommended approval of the proposed subdivision to the City of Red Lodge, subject to eighteen conditions. The recommendation was transmitted to the Red Lodge City Council (City Council) on July 2, 1996. Although § 76-3-604, MCA, requires the city to act upon such an application within sixty days, Red Lodge let the time pass without action. After the City of Red Lodge Planning Board was in place, it issued a staff report on July 15, 1997, wherein it recommended the City Council approve Kiely’s preliminary plat application with the same eighteen conditions proposed by the County Planning Board.

¶7 On August 26,1997, upon Kiely’s request, the Thirteenth Judicial District Court1 issued a Writ of Mandamus, compelling Red Lodge to act upon Kiely’s preliminary plat application within ten days by approving, conditionally approving, or denying the application. Following a public hearing on September 10,1997, Kiely’s application was conditionally approved, subject to twenty-six conditions. Apparently, Red Lodge reviewed Kiely’s application under the City of Red Lodge Development Code (1997 Development Code), which was adopted in April of 1997, and effective May 22,1997.

¶8 On October 14,1997, Kiely commenced this action appealing the twenty-six final conditions adopted by Red Lodge on September 10, 1997. Kiely brought the action under §§ 76-3-625(1) and (2), MCA, and 42 U.S.C. § 1983 (§ 1983), maintaining that Red Lodge acted arbitrarily and capriciously in imposing the conditions. Kiely sought the following relief: (1) an order requiring Red Lodge to apply the regulations in effect at the time the application was submitted, and revise the “final conditions” to comply with such regulations; and (2) damages incurred as a result of the delay (caused by Red Lodge’s violation of sixty-day requirement), and the final twenty-six conditions imposed, and also damages for Kiely’s deprivation of property rights [60]*60under § 1983. Red Lodge responded that the adoption of interim zoning ordinances on April 8,1997, allowed it to prohibit any uses in conflict with the ordinances, and that the individual council members were entitled to qualified immunity.

¶9 In a motion for partial summary judgment filed on August 18, 1998, Kiely requested the District Court deem its preliminary plat application approved, subject to the original eighteen conditions recommended by the County Planning Board, because Red Lodge failed to act within the mandatory sixty days.

¶10 The parties commenced mediation in the Fall of 1998. Following negotiations on September 14, 1998, the parties entered into a subdivision improvements agreement (SLA), which Red Lodge conditionally accepted on January 12,1999, by adding seven conditions that were not considered in the original agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy Prop. v. Painted Rocks
2025 MT 43 (Montana Supreme Court, 2025)
Protect the Gallatin v. Gallatin Co.
2025 MT 34 (Montana Supreme Court, 2025)
Tam v. Missoula County
2022 MT 229 (Montana Supreme Court, 2022)
Stalowy v. Flathead Conservation
2020 MT 155 (Montana Supreme Court, 2020)
In Re the Estate of Edwards
2017 MT 93 (Montana Supreme Court, 2017)
Pacific Hide & Fur Depot v. Emineth Custom Homes, Inc.
2016 MT 114 (Montana Supreme Court, 2016)
Lewis & Clark County v. Hampton
2014 MT 207 (Montana Supreme Court, 2014)
Boyne USA, Inc. v. Spanish Peaks Development, LLC
2013 MT 1 (Montana Supreme Court, 2013)
McEwen v. MCR, LLC
2012 MT 319 (Montana Supreme Court, 2012)
Arlington v. MILLER'S TRUCKING, INC.
2012 MT 89 (Montana Supreme Court, 2012)
Heffernan v. Missoula City Council
2011 MT 91 (Montana Supreme Court, 2011)
State v. Dethman
2010 MT 268 (Montana Supreme Court, 2010)
Mm & I, LLC v. Cty. Com'rs of Gallatin Cty.
2010 MT 274 (Montana Supreme Court, 2010)
Griffith v. Butte School District No. 1
2010 MT 246 (Montana Supreme Court, 2010)
DiMarzio v. CRAZY MOUNTAIN CONST., INC.
2010 MT 231 (Montana Supreme Court, 2010)
Dimarzio v. Crazy Mountain Construction, Inc.
2010 MT 231 (Montana Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
2002 MT 241, 57 P.3d 836, 312 Mont. 52, 2002 Mont. LEXIS 502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiely-construction-llc-v-city-of-red-lodge-ex-rel-red-lodge-city-mont-2002.