DA 19-0416 Case Number: DA 19-0416

IN THE SUPREME COURT OF THE STATE OF MONTANA 2020 MT 155

DAVID E. STALOWY and JACQUELINE A. STALOWY,

Plaintiffs and Appellants,

v.

FLATHEAD CONSERVATION DISTRICT,

Defendant and Appellee.

APPEAL FROM: District Court of the Eleventh Judicial District, In and For the County of Flathead, Cause No. DV-16-953A Honorable Amy Eddy, Presiding Judge

COUNSEL OF RECORD:

For Appellants:

Marcel Quinn, Thomas Hollo, Hammer, Quinn & Shaw PLLC, Kalispell, Montana

For Appellee:

Caitlin Overland, Flathead County Deputy Attorney, Kalispell, Montana

Submitted on Briefs: March 4, 2020

Decided: June 16, 2020

Filed:

cir-641.—if __________________________________________ Clerk Justice Beth Baker delivered the Opinion of the Court.

¶1 David and Jacqueline Stalowy applied for permits with the Flathead Conservation

District (“District”) to conduct dredging activities on their Flathead County property. At

issue is whether North Bear Creek and other waterbodies on the Stalowy property meet the

definition of a “stream” subject to the regulatory provisions of The Natural Streambed and

Land Preservation Act of 1975 (“Act”), Title 75, chapter 7, MCA. The District found that

they did and asserted jurisdiction. The District Court affirmed, and Stalowys appeal. We

affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 The Stalowys’ property is in the Bear Creek drainage. Bear Creek is a large stream

system comprising North and South Bear Creeks, defined by a “number of small,

geographically isolated wetlands” known as the Slope Wetlands Complex. The largest

feature on the property is a naturally existing pond known as Beaver Lake. The

District Court described the waterway as follows:

Upstream of [the Stalowys’] property, Bear Creek flows in a perennial, defined channel. A short distance before the [Stalowys’] land, it forks, with the more surface flow laden channel splitting to the south. [The District] refers to this channel as South Bear Creek. [The Stalowys] refer to “South Bear Creek” as simply Bear Creek, and maintain the North Fork is an ephemeral offshoot. “North Bear Creek” enters Grassy Marsh, a wetland area partially on [Stalowys’] property. North Bear Creek exits Grassy Marsh and enters Upper Pond in a defined channel. During late summer and early fall, this section of North Bear Creek contains no surface flow. North Bear Creek then exits Upper Pond in a defined channel and enters either Beaver Lake or David’s Pond through a series of culverts. Below David’s Pond, North Bear Creek continues through multiple smaller channels that have migrated over time. North Bear Creek rendezvous[es] with South Bear Creek next to Highway 83, at the intersection with Landmark Lane.

2 ¶3 Over the years, the Stalowys have conducted various dredging projects where

North Bear Creek enters their property. For the District to have jurisdiction under the Act,

the proposed dredging work must result in a “change in the state” of a

“natural, perennial-flowing stream.” Section 75-7-103(5)(a), MCA. The District initially

determined in 2008 and 2009 that it did not have jurisdiction over the dredging activities

around Beaver Lake because there was no perennially flowing stream, but it did grant a

permit for the Stalowys to install a culvert.

¶4 In 2015, the Stalowys began an expanded dredging project of Beaver Lake and the

Upper Pond, which was to be followed by additional dredging in the wetland known as

Grassy Marsh. After receiving a number of complaints, the District reexamined its

jurisdiction, obtaining an independent consultant to study the stream.

¶5 The District determined that the work done on the property was a “project” under

the Act, thus invoking its jurisdiction, and required the Stalowys to apply for a permit for

their proposed dredging of Grassy Marsh and continuing work on Beaver Lake. In making

its jurisdictional determination, the District determined that the interconnected nature of

the bodies of water in North Bear Creek, which includes all stream channels, ponds,

wetlands, and waterbodies within the channels, comprised a natural, perennial-flowing

stream to the confluence with South Bear Creek. It reasoned that although

North Bear Creek shifts channels, and during dry periods flows partially in subterranean

form, it remains within the definition of a perennial stream because existing stream

channels containing historical surface flows were documented in the review process.

3 ¶6 The Stalowys filed a petition for a declaratory ruling regarding the District’s

jurisdictional determination under the Act’s declaratory ruling process. The District

determined the issue to be of significant public interest and appointed a hearing officer to

assist with the process and to make recommended findings of fact and conclusions of law.

After a public hearing on the issue, the District issued its Declaratory Ruling maintaining

its assertion of jurisdiction over the Stalowys’ property and projects. The Stalowys

petitioned the District Court for judicial review of the Declaratory Ruling.

¶7 The District Court affirmed the District’s Declaratory Ruling. It found evidence in

the record that North Bear Creek: (1) historically maintained surface flows; (2) is part of a

hydrologically connected landscape; and (3) contains multiple existing stream channels

that are susceptible to human influence; and that downstream flows have been impacted by

the Stalowy project. It found further that evidence in the record supported the District’s

position that human activities caused North Bear Creek to dry during summer months.

Thus, under these limited circumstances, groundwater flowing through North Bear Creek’s

historical channel supported a finding of jurisdiction, and the District was neither operating

under an error of law nor arbitrary and capricious in its decision-making. Further, the court

concluded that the record contained evidence that the Stalowys’ dewatering of Beaver Lake

and subsequent filling of David’s Pond modified the historical flow of Bear Creek and

resulted in discharges of sediment downstream. Thus, the District’s conclusion that the

Stalowys’ work was a project subjecting it to jurisdiction under the Act was substantially

supported by the record and was not arbitrary and capricious or affected by error of law.

4 STANDARDS OF REVIEW

¶8 Under the Act, a conservation district’s declaratory ruling regarding its jurisdiction

is subject to judicial review. Section 75-7-125(4), MCA. The proceeding is not a

contested case proceeding under the Montana Administrative Procedure Act (“MAPA”).

Section 75-7-125(3), MCA. A court may reverse or modify the District supervisors’

declaratory ruling only if substantial rights of the appellant have been prejudiced because

the ruling is: (1) arbitrary and capricious; (2) characterized by an abuse of discretion;

(3) an error of law; or (4) in violation of constitutional or statutory provisions.

Section 75-7-125(4)(a)-(d), MCA. This Court applies the same standard of review when

reviewing a district court’s decision to affirm the agency decision.

Bitterroot River Protective Ass’n v. Bitterroot Conservation Dist., 2008 MT 377, ¶ 18,

346 Mont. 507, 198 P.3d 219 (citation omitted).

¶9 Under these standards, the courts’ “inquiry must be searching and careful, but

Free access — add to your briefcase to read the full text and ask questions with AI

Stalowy v. Flathead Conservation, 2020 MT 155, 465 P.3d 1170, 400 Mont. 266 (Mo. 2020).

2020 MT 155 (Stalowy v. Flathead Conservation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burtons v. Flathead Conservation Dist.
Montana Supreme Court, 2026
Fortner v. Broadwater Conservation Dist.
2021 MT 240 (Montana Supreme Court, 2021)