Pacific Hide & Fur Depot v. Emineth Custom Homes, Inc.

2016 MT 114, 373 P.3d 829, 383 Mont. 373, 2016 Mont. LEXIS 387, 2016 WL 2894094
CourtMontana Supreme Court
DecidedMay 17, 2016
DocketDA 15-0503
StatusPublished
Cited by3 cases

This text of 2016 MT 114 (Pacific Hide & Fur Depot v. Emineth Custom Homes, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Hide & Fur Depot v. Emineth Custom Homes, Inc., 2016 MT 114, 373 P.3d 829, 383 Mont. 373, 2016 Mont. LEXIS 387, 2016 WL 2894094 (Mo. 2016).

Opinion

CHIEF JUSTICE McGRATH

delivered the Opinion of the Court.

¶1 Emineth Custom Homes and Shane Emineth (Emineth) appeal from the District Court’s judgment of July 23, 2015, entered following the jury’s verdict rendered June 12,2015. We affirm in part, reverse in part, and remand.

¶2 We restate the issue on appeal as follows:

Whether the District Court properly enteredjudgment following the jury’s verdict rendered June 12, 2015.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 In about 2011 Pacific Steel & Recycling (Pacific) set about to expand its recycling and fabrication work in Williston, North Dakota, and foresaw the need for a warehouse and a remodeled office and shop. Pacific put the warehouse project out for bids and awarded the contract to Emineth as the low bidder. An unsuccessful bidder, unhappy about not getting the warehouse job, threatened to cancel a rail siding lease with Pacific if Emineth were allowed to proceed. Pacific revoked the contract award to Emineth in order to save the rail siding, but shortly thereafter entered into two contracts with Emineth, one to renovate the office and shop and the other to build four duplexes for employee housing.

¶4 In February 2012 Emineth and Pacific signed a contract which called for Emineth to build four duplex apartment units in Williston to house Pacific’s employees, for a price of approximately $1.9 million. The contract specified that Pacific would advance $474,625 to Emineth as a “down payment” upon execution of the contract. Under the contract Emineth was responsible for obtaining all necessary permits for the duplex project. The project required a zoning change, which proved difficult to obtain in a timely manner, although the local Zoning Board never denied the application.

¶5 There was testimony that the down payment was designed to fund work and materials required for the duplex project, as well as Emineth’s anticipated profit. Emineth testified that he used $7,000 of *375 it to pay for engineering work on the drain field plan for the project and spent $39,000 on equipment to be used on Pacific projects in the Williston area.

¶6 In July 2012 Pacific cancelled the contract for the duplexes, contending that Emineth had not performed in a timely manner, and demanded return of the down payment. The parties agreed to a few subsequent projects that resulted in Pacific forgiving $32,000 of its claim to the down payment, but the parties did not resolve the issue. Pacific asked Shane Emineth to come to Great Falls to discuss their relationship. At that meeting Pacific demanded return of the advance payment and presented a promissory note for Emineth to sign. After consultation with an attorney, Emineth declined to sign the note. Emineth estimated that cancellation of the duplex project cost the company at least $100,000 in lost income.

¶7 In April 2013 Pacific initiated the present case by bringing an action against Emineth, stating a number of claims including breach of contract, unjust enrichment, constructive trust, and breach of the covenant of good faith and fair dealing. Pacific sought recovery of $437,625 of the down payment made to Emineth under the contract. This lesser amount recognized that Emineth was entitled to $32,000 credit arising from the other jobs done for Pacific. Emineth appeared in the action, denied liability to Pacific, and counterclaimed, seeking damages from Pacific for breach of contract and other claims. Notably, when the parties signed the pretrial order, Pacific asserted claims that Emineth had been unjustly enriched in the amount of $437,625; that Emineth held at least $437,625 in constructive trust for the benefit of Pacific; and that Emineth breached the covenant of good fair and fair dealing by improperly retaining the down payment.

¶8 The parties tried the case to a jury in June 2015. Just prior to trial Pacific filed a trial brief in which it stated that it would present its claim for return of the down payment solely upon the theory of breach of contract. Pacific abandoned its other causes of action against Emineth, including the claim for unjust enrichment. Moreover, Pacific did not assert as an affirmative defense or otherwise explicitly plead the issues of offset or restitution in its answer to the counterclaim filed by Emineth.

¶9 The parties agreed to a special verdict form which limited the basis of the claims of both sides to breach of contract. The verdict asked the jury to determine whether Pacific or Emineth had breached the duplex contract and if so, the amount of damages caused. The special verdict provided (with the jury’s responses):

*376 BREACH OF CONTRACT (AGAINST EMINETH CUSTOM HOMES)
1. Did Emineth Custom Homes, Inc. (“ECH”) breach the duplex contract with Pacific Steel and Recycling (“Pacific”)? No
If “yes” proceed to Question 2. If “no” skip to Question 4.
2. Did ECH’s breach cause damages to Pacific?
If “yes,”proceed to Question 3. If “no,” skip to Question 4.
3. What amount of money will compensate Pacific for damages caused by ECH’s breach of the duplex contract?
Proceed to Question 4.
BREACH OF CONTRACT (AGAINST PACIFIC)
4. Did Pacific breach the duplex contract with ECH? Yes
If “yes” proceed to Question 5. If “no,” sign this verdict form and return it to the Bailiff
5. Did Pacific’s breach cause damages to ECH? Yes
If “yes” proceed to Question 6. If “no,” sign this verdict form and return it to the Bailiff.
6. What amount of money will compensate ECH for damages caused by Pacific’s breach of the duplex contract? $238,241.00

Pacific asserts in its brief on appeal that it offered an additional jury interrogatory that would have asked the jury to specifically determine the amount of the down payment that Emineth had to return. However, that interrogatory was not given; the parties agreed to the special verdict that was given; and Pacific does not appeal the issue.

¶10 The jury’s verdict determined that Emineth did not breach the contract with Pacific, but that Pacific breached the contract with Emineth. The jury further found that Pacific’s breach had caused Emineth damages of $238,241. After trial the parties could not agree upon the effect of the verdict. The District Court held a status conference with counsel, and entered judgment on the verdict in favor of Emineth for $238,241 as found by the jury. The District Court stated that the special verdict submitted to the jury was “appropriate under the circumstances”; that the case was a breach of contract case; and that the jury found that Pacific had breached the contract with Emineth. The District Court further noted that the jury found that Emineth suffered damages of $238,241 from the breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. T. Lafournaise
2022 MT 36 (Montana Supreme Court, 2022)
Kubicka v. Frazier Industries
2020 MT 95N (Montana Supreme Court, 2020)
Covey v. Brishka
2019 MT 164 (Montana Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 114, 373 P.3d 829, 383 Mont. 373, 2016 Mont. LEXIS 387, 2016 WL 2894094, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-hide-fur-depot-v-emineth-custom-homes-inc-mont-2016.