Keiland Construction v. Weeks Marine

109 F.4th 406
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 25, 2024
Docket23-30357
StatusPublished
Cited by19 cases

This text of 109 F.4th 406 (Keiland Construction v. Weeks Marine) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keiland Construction v. Weeks Marine, 109 F.4th 406 (5th Cir. 2024).

Opinion

Case: 23-30357 Document: 88-1 Page: 1 Date Filed: 07/25/2024

United States Court of Appeals for the Fifth Circuit ____________ United States Court of Appeals Fifth Circuit No. 23-30357 ____________ FILED July 25, 2024 Keiland Construction, L.L.C., Lyle W. Cayce Clerk Plaintiff—Appellant/Cross-Appellee,

versus

Weeks Marine, Incorporated,

Defendant—Appellee/Cross-Appellant. ______________________________

Appeal from the United States District Court for the Western District of Louisiana USDC No. 2:20-CV-827 ______________________________

Before Willett, Wilson, and Ramirez, Circuit Judges. Cory T. Wilson, Circuit Judge: Keiland Construction sued Weeks Marine Inc. for breach of a construction contract. The district court held a bench trial and concluded that the contract was ambiguous, construed it against Keiland as the drafter, and determined Weeks prevailed. After cross-motions for summary judgment on damages, the court awarded Keiland damages, but in accord with Weeks’s interpretation of the contract. The court also awarded Weeks attorneys’ fees and costs, though less than the amount Weeks requested, and denied Weeks’s motion for post-offer-of-judgment attorneys’ fees and costs pursuant to Federal Rule of Civil Procedure 68(d). Case: 23-30357 Document: 88-1 Page: 2 Date Filed: 07/25/2024

No. 23-30357

The parties cross-appeal. Keiland contends the district court erred in holding the contract ambiguous, determining Weeks prevailed on the contract interpretation issue, and granting partial summary judgment for Weeks as to damages. Weeks contests the district court’s attorneys’ fees calculation, as well as the court’s award of prejudgment interest to Keiland and denial of post-offer attorneys’ fees. We affirm in all respects. I. A. In December 2019, Weeks Marine, Inc., as general contractor, entered a construction subcontract (the Contract) with Keiland Construction for a project in Cameron Parish, Louisiana. Weeks’s vice-president David Hafner and Keiland’s president Keith DuRousseau signed the Contract for their respective companies. In March 2020, Weeks terminated the Contract “for convenience,” invoking Section 9 of the Contract. Traveling under Section 5, Keiland submitted to Weeks three pay applications, one just prior to termination and two afterwards, totaling more than $570,000. Keiland also submitted a request for $25,210.35 in demobilization costs. The parties disputed the total compensation due. The parties’ dispute centered on the interplay between Sections 5 and 9 of the Contract. Section 5, “COMPENSATION,” outlines how Weeks was to pay Keiland for the work to be performed: COMPENSATION: As full consideration for the satisfactory performance by [Keiland] of this subcontract, [Weeks] shall pay to [Keiland] compensation in accordance with the prices set forth below.

2 Case: 23-30357 Document: 88-1 Page: 3 Date Filed: 07/25/2024

All pricing is firm for the duration of the project. All unit priced quantities listed above are estimated quantities only. Payment will be made in accordance with actual quantities performed by [Keiland] and approved by [Weeks]. Unit pricing shall remain the same irrespective of final quantities performed. [Keiland] shall provide monthly invoices for work completed and payment shall be made within fourteen (14) days of [Weeks’s] receipt of payment from the OWNER . . . .

The “LS” moniker in Table 1 means “Lump Sum”; the charged work was to be compensated by the indicated lump sum amount. Section 9, “TERMINATION FOR CONVENIENCE,” allowed Weeks, “at its option, [to] terminate for convenience any of the Work under this subcontract in whole or in part at any time.” Section 9 also delineated post-termination compensation: [Keiland] shall be entitled to the actual and necessary expense of finishing its Work through the date of termination, the actual and necessary expenses of withdrawing from the Project site, and twenty-one percent (21%) for overhead and profit associated with its Work through the date of termination . . . .

In Keiland’s reading, Section 5 entitled Keiland to payment on a lump-sum basis for work completed at the time of termination, and Section 9 provided for cost-plus compensation for all work performed thereafter. Weeks countered that upon termination, Section 9 converted the Contract’s lump-

3 Case: 23-30357 Document: 88-1 Page: 4 Date Filed: 07/25/2024

sum payment structure to a cost-plus basis for both pre- and post-termination work. In January 2021, Weeks paid Keiland $200,000 “in the spirit of good faith after being unable to calculate Keiland[’s] actual costs.” Weeks asserts that this payment was intended to cover all of Keiland’s costs, including Keiland’s claimed demobilization costs, but Keiland contests what costs were included. Weeks also made direct payments to some of Keiland’s vendors. B. Meanwhile, Keiland filed suit in Louisiana state court in May 2020, alleging that Weeks breached the Contract, defamed Keiland, and violated the Louisiana Unfair Trade Practices and Consumer Protection Law. 1 Weeks removed the action to federal court in June 2020. The parties filed competing motions for summary judgment in May and June 2021. They “agree[d] that Section 5 creates a lump sum contract, but disagree[d] as to when Section 9 might allow termination to convert that contract to a cost- plus compensation structure.” The district court denied the parties’ cross-motions for summary judgment, concluding that Section 9’s compensation terms were ambiguous. It found the phrase “[Keiland] shall be entitled to the actual and necessary expense of finishing its Work through the date of termination” supported Keiland’s interpretation that it was entitled to lump-sum payment for all work completed through termination. But the court noted that the allowance of 21% for overhead and profit associated with “Work through the date of termination” supported both parties’ interpretations. The court found _____________________ 1 Keiland moved to dismiss its Louisiana Unfair Trade Practices Act and defamation claims, which the court granted.

4 Case: 23-30357 Document: 88-1 Page: 5 Date Filed: 07/25/2024

Weeks’s proffered parol evidence to be “self-serving and vague,” and in any event, “[t]he language of the [C]ontract remain[ed] too ambiguous to be clarified by this evidence.” Keiland requested a trial setting and bifurcation of the issues of contract interpretation and resulting damages. Weeks opposed bifurcation of the issues as premature. After a status conference with the parties, the court granted Keiland’s motion in September 2021. On July 1, 2022, prior to the trial setting, Weeks offered a $100,000 judgment, “inclusive of all costs, fees, and interest,” under Federal Rule of Civil Procedure 68. Keiland did not accept. In November 2022, the district court conducted a bench trial on the Contract’s interpretation. Considering the parties’ evidence, the court found that “there was no meeting of the minds with respect to [the Contract’s] interpretation.” The court construed the Contract against Keiland, which had drafted the relevant language, and held that the entire Contract converted to a “cost-plus” arrangement after termination. Tracking Contract Section 9, the court determined Weeks owed Keiland only for the “work completed through the effective date of termination [plus 21% for overhead and profit,] and [Keiland was] not entitled to payment on the lump-sum basis for any work completed under the subcontract.” After trial, both parties moved for summary judgment on damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
109 F.4th 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keiland-construction-v-weeks-marine-ca5-2024.