John L. Roper Lumber Co. v. Lawson

143 S.E. 847, 195 N.C. 840, 67 A.L.R. 984, 1928 N.C. LEXIS 218
CourtSupreme Court of North Carolina
DecidedJune 23, 1928
StatusPublished
Cited by15 cases

This text of 143 S.E. 847 (John L. Roper Lumber Co. v. Lawson) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John L. Roper Lumber Co. v. Lawson, 143 S.E. 847, 195 N.C. 840, 67 A.L.R. 984, 1928 N.C. LEXIS 218 (N.C. 1928).

Opinion

ClabicsoN, J.

Defendants, Lawson & Brooke, a partnership, on or about 12 May, 1926, Uiade a contract with the State Highway Commission to construct or improve a certain section of the State highway system project No. 112, between South Mills, N. C., and the Virginia State line, in Camden County, 7.67 miles long, in accordance with certain proposals, plans and specifications, at a cost approximately estimated at $234,230.00. For the faithful performance of the contract, and to pay materialmen and laborers, for which the contractors were liable, the defendant, United States Fidelity and Guaranty Company, entered into a bond with the State Highway Commission in the penal sum of $117,115.00. In carrying out the contract it is alleged that Lawson & Brooke were guilty of actionable negligence in burning over a large portion of plaintiff’s land, some 854 acres. Lawson & Brooke have completed the work contracted to be done. A statement of plaintiff’s claims has been filed in accordance with the statutes. Is the bond liable for the tort? We think not.

The material part of the bond in controversy for the determination of the case, is as follows: -“Now, therefore, the conditions of this obligation *843 are such, that if the above bonded ‘principal’ as contractor, shall in all respects comply with the terms of the contract and conditions of said contract, and bis’ their and its obligations thereunder, including the specifications and plans therein referred to and made a part thereof, and sirch alterations as may be made in' said specifications and plans as therein provided for, and shall well and truly, and in a manner satisfactory to the State Highway Engineer, complete the work contracted for, and shall save harmless the State Highway Commission of North Carolina from any expense incurred through the failure of said contractor to complete the work as specified, and from any damage growing out of the carelessness of said contractor, or his, their or its servant, and from any liability for payment of wages or salaries due or for material furnished said contractor, and shall well and truly pay all and every person furnishing material or performing labor in and about the construction of said roadway all and every sum or sums of money due him, them or any of them, for all such labor and materials for which the contractor is liable, and also shall save and keep harmless the said State Highway Commission of North Carolina against and from all losses to it from any cause whatever, including patent, trade mark and copyright infringements in the manner of constructing said project, then this obligation shall be void, or otherwise to be and remain in full force and virtue.” Ordinarily a penal bond must be strictly construed and sureties have a right to stand on the terms of their contract. Edgerton v. Taylor, 184 N. C., 571; Insurance Co. v. Durham County, 190 N. C., at p. 61; S. v. Carnegie, 193 N. C., 467; Ingram v. Bank, ante, 357.

In recognition of the fact .that those furnishing labor and material ordinarily can take no- lien on public property, in their behalf a more liberal construction has prevailed. See United States Code, Annotated, Title 40, p. 95, and eases cited.

In Brick Co. v. Gentry, 191 N. C., at p. 639, it is said: “The obligation of the bond is to be read in the light of the contract it is given to secure, and ordinarily the extent of the engagement, entered into by the surety, is to be measured by the terms, of the principal’s agreement. Brown v. Markland, 22 Ind., App., p. 655; Dixon v. Horne, 180 N. C., 585; Scheflow v. Pierce, 176 N. C., 91.”

We are not dealing with C. S., 2445, relating to bonds required to be given by any contractor with surety to any county, city, town or other municipal corporation, for the building, repairing, or altering any building, public road or street. See Supply Co. v. Plumbing Co., ante, 629.

We are not discussing the liability of the contractors, Lawson & Brooke, but the liability on the present bond to plaintiffs. The bond is not as clear as it could be written, but, under well settled law, its provisions should not be extended beyond the reasonable intent gathered *844 from the purpose and language of the bond, and construed in connection with the proposals, plans and specifications and contract. It has been the policy of long standing in this jurisdiction, that liens are given to mechanics, laborers and materialmen. Even the homestead exemption cannot be claimed against mechanics’ and laborers’ liens. Art. 10, sec. 4, is as follows: “The provisions of sections one and two of this article shall not be construed as to prevent a laborer’s lien for work done and performed for the person claiming such exemption, or a mechanic’s lien for work done on the premises.” Art. 14, sec. 4, is as follows: “The General Assembly shall provide, by proper legislation, for giving to mechanics and laborers an adequate lien on the subject-matter of their labor.”

C. S., chap. 49, makes ample provision for “mechanics’, laborers’ and materialmen’s liens.” Ordinarily on public works, a lien statute did not apply, bonds were taken. The bond was intended to provide an equivalent or substitute for the legislation for the protection of laborers and materialmen. Mfg. Co. v. Blaylock, 192 N. C., 407; U. S. Code, Anno., supra. Usually, the contractor’s bond was given guaranteeing the performance of the work on the part of the contractor, as in McCausland v. Construction Co., 172 N. C., 708, and cases cited, and Warner v. Halyburton, 187 N. C., 414.

In Gastonia v. Engineering Co., 131 N. C., at p. 365; it is said: “Though no mechanic’s lien could be filed against the property, in the hands of the town, it was competent for the parties to contract, and they did contract that the engineering company should pay for ‘all materials used and wages of all laborers employed, by said contractor,’ and the surety company became responsible for the execution of that stipulation.” . . . (p. 367) “It would be well if every municipality which has public works executed should insert a similar provision in its contract for the protection of labor and materialmen, who are usually its own citizens. Indeed, in this contract it is further provided that all labor employed shall be ‘home labor,’ except as to such skilled labor as could not be found there, thus showing throughout that the labor and material-men are beneficiaries in contemplation of the contracting parties.”

In Supply Co. v. Plumbing Co., supra, at p. 635, it is said: “The General Assembly of 1923, chap. 100, Public Laws, supra, amended C. S., 2445, as we construe the matter, to meet the decisions in the above cases, so as to protect the laborers and materialmen, where the bond does not make provisions to pay them.”

C. S., 2445, does not apply to the State Highway Commission. Carrying out the well known policy of the State, the State Highway Commission has had the bonds so drawn as to protect those who furnish mate *845 rial and perform labor in and about the construction of the roadway.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long v. City of Midway
311 S.E.2d 508 (Court of Appeals of Georgia, 1983)
State Highway Administration v. Transamerica Insurance
367 A.2d 509 (Court of Appeals of Maryland, 1976)
Interstate Equipment Co. v. Smith
229 S.E.2d 241 (Court of Appeals of North Carolina, 1976)
Tri-State Insurance Company v. United States
340 F.2d 542 (Eighth Circuit, 1965)
American Bridge Division United States Steel Corp. v. Brinkley
120 S.E.2d 529 (Supreme Court of North Carolina, 1961)
AMERICAN BRIDGE DIVISION US STEEL CORP. v. Brinkley
120 S.E.2d 529 (Supreme Court of North Carolina, 1961)
United States, for Use of Gibson v. Harman
192 F.2d 999 (Fourth Circuit, 1951)
Davis v. Radford
63 S.E.2d 822 (Supreme Court of North Carolina, 1951)
Chozen Confections, Inc. v. . Johnson
19 S.E.2d 866 (Supreme Court of North Carolina, 1942)
Cavarnos-Wright Co. v. . Blythe Brothers Co.
8 S.E.2d 924 (Supreme Court of North Carolina, 1940)
Cantey v. Newell Contracting Co.
178 S.E. 342 (Supreme Court of South Carolina, 1935)
Ulmen v. National Surety Co.
3 F. Supp. 348 (D. Montana, 1933)
Overman & Co. v. Great American Indemnity Co.
155 S.E. 730 (Supreme Court of North Carolina, 1930)
McCausland v. . Construction Co.
90 S.E. 1010 (Supreme Court of North Carolina, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
143 S.E. 847, 195 N.C. 840, 67 A.L.R. 984, 1928 N.C. LEXIS 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-l-roper-lumber-co-v-lawson-nc-1928.