Jewel M. Cooper v. Diamond M Company

799 F.2d 176, 1987 A.M.C. 525, 1986 U.S. App. LEXIS 29770
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 8, 1986
Docket85-3299
StatusPublished
Cited by30 cases

This text of 799 F.2d 176 (Jewel M. Cooper v. Diamond M Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jewel M. Cooper v. Diamond M Company, 799 F.2d 176, 1987 A.M.C. 525, 1986 U.S. App. LEXIS 29770 (5th Cir. 1986).

Opinion

RANDALL, Circuit Judge:

Appellant Jewel M. Cooper appeals from the district court’s entry of summary judg *177 ment. We affirm in part, and reverse and remand in part.

I.

Jewel M. Cooper was employed as a steward by appellee Diamond M Company. On April 4, 1979, Cooper sustained injuries on the Diamond M vessel, Century, when she slipped and fell in water that had allegedly leaked from a refrigeration unit. The accident was not witnessed; another employee walked into the refrigeration unit to find Cooper already on the floor. Cooper explained that she had slipped and fallen, and reported the accident to the barge captain.

According to an affidavit filed by Cooper, Diamond M assured Cooper that she would have a job as long as she wanted. Cooper continued to work for Diamond M “in pain” until April 27, 1983, receiving “compensation” of two hundred dollars per week from Diamond M from May 20, 1983, until September of 1983, when she was fired.

On November 14, 1983, over four years after the accident, Cooper sued Diamond M for personal injury pursuant to the Jones Act, 46 U.S.C. § 688, and general maritime law. Diamond M moved for summary judgment, claiming that Cooper’s suit was untimely. The district court granted the motion as to the Jones Act claim, but denied it as to the unseaworthiness claim, allowing Cooper an additional ten days to amend her complaint to show that this latter claim was not barred by laches. Cooper amended her complaint to allege that her delay in filing suit was excusable and that the delay did not prejudice Diamond M. In a later amendment, Cooper added a maintenance and cure claim.

Diamond M again moved for summary judgment in July 1984, maintaining that Cooper’s claim was barred either by laches or by the statute of limitations embodied in 46 U.S.C. § 763a. To support its claim of laches, Diamond M relied primarily on the affidavit of Kenneth A. Bradley, the claims manager of Diamond M. The affidavit stated that Cooper’s supervisor, Hubert Boeckle, an important witness, had died on April 23, 1982. According to the affidavit, Boeckle would have had knowledge both of Cooper’s post-accident condition and of the state of the equipment that had allegedly led to Cooper’s accident.

In August 1984, the district court orally denied in part Diamond M’s motion, ruling that 46 U.S.C. § 763a, enacted October 6, 1980, did not apply to bar Cooper’s claim. Turning to the laches issue, the court ruled that Cooper’s delay in filing suit was not excusable. The court, however, gave Cooper additional time for discovery on the question of prejudice to Diamond M.

On March 7, 1985, Cooper and Diamond M filed a joint motion for summary judgment. Cooper had submitted no additional affidavits or depositions contradicting the evidence of prejudice contained in the Bradley affidavit. Accordingly, on April 1, 1985, the district court granted summary judgment for Diamond M, ruling that Cooper had failed to carry her burden of showing that Diamond M had not been prejudiced by the delay in suit. The court also rejected Cooper’s claim that the obligation to provide maintenance and cure was contractual and therefore governed by the ten-year Louisiana prescriptive period for contractual claims rather than by laches. Cooper now appeals the district court’s entry of summary judgment against her on the unseaworthiness and maintenance and cure claims.

II.

Summary judgment is appropriate if the full record discloses that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). On review, we apply the same test as does the district court. Because we find Cooper’s unseaworthiness claim to be time-barred by 46 U.S.C. § 763a, we affirm the district court’s entry of summary judgment against Cooper on this claim. 1 However, because we conclude that the district court did not apply the correct legal standard in determining when the maintenance and *178 cure cause of action accrued, we must reverse the district court’s entry of summary judgment on the maintenance and cure claim.

Section 763a, enacted October 6, 1980, provides:

Unless otherwise specified by law, a suit for recovery of damages for personal injury or death, or both, arising out of a maritime tort, shall not be maintained unless commenced within three years from the date the cause of action accrued.

Only two circuit courts have addressed, with differing conclusions, the question whether § 763a should be applied to a cause of action, such as Cooper’s unseaworthiness action, which accrued prior to the statute’s date of passage. In Fordham v. Belcher Towing Co., 710 F.2d 709 (11th Cir.1983), the Eleventh Circuit refused to apply § 763a to a negligence claim which had accrued in 1978, instead remanding the suit for determination of whether it was time-barred in accordance with the law of laches. In Friel v. Cessna Aircraft Co., 751 F.2d 1037 (9th Cir.1985), the Ninth Circuit did apply § 763a to extend the period of limitations applicable to a cause of action which accrued in July 1980, three months prior to the passage of § 763a, explaining: “when a statute is addressed to remedies or procedures and does not otherwise alter substantive rights, it will be applied to pending cases.” 751 F.2d at 1039.

We find that § 763a applies to Cooper’s unseaworthiness claim. A newly-created statute of limitation will not violate the Constitution by divesting a vested right if it allows a reasonable time for those affected by the Act to assert their rights. Fust v. Arnar-Stone Laboratories, Inc., 736 F.2d 1098, 1100 (5th Cir.1984). In the instant case, Congress, by the very terms of § 763a, indicated that three years would be a reasonable prescriptive period for asserting an unseaworthiness claim. We thus find that a claim which accrued prior to the date of passage of § 763a remains viable for three years after the date of passage of that statute and thereafter succumbs to the absolute bar impressed by Congress. See Fust, 736 F.2d at 1100. 2 Because Cooper filed suit in November 1983, more than three years after the passage of § 763a, we find her unseaworthiness claim to be time-barred. 3

We find that Cooper’s maintenance and cure claim, however, was timely filed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Darryle Spencer v. Grand River Navigation Co.
644 F. App'x 559 (Sixth Circuit, 2016)
Powell v. Global Marine, LLC
671 F. Supp. 2d 830 (E.D. Louisiana, 2009)
Cunningham v. Interlake Steamship Co.
567 F.3d 758 (Sixth Circuit, 2009)
Jones v. Tidewater Marine LLC
262 F. App'x 646 (Fifth Circuit, 2008)
Loftin v. Kirby Inland Marine, L.P.
568 F. Supp. 2d 754 (E.D. Texas, 2007)
Frank Brooks v. Raymond Dugat Company L C
336 F.3d 360 (Fifth Circuit, 2003)
Dolling v. Amanda Hess Corp.
83 F. Supp. 2d 843 (S.D. Texas, 2000)
Prejean v. Industrial Cleanup, Inc.
721 So. 2d 1273 (Supreme Court of Louisiana, 1998)
Sample v. Freeman
873 S.W.2d 470 (Court of Appeals of Texas, 1994)
O'Brien v. City of New York
822 F. Supp. 943 (E.D. New York, 1993)
Logwood v. Apollo Marine Specialists, Inc.
772 F. Supp. 925 (E.D. Louisiana, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
799 F.2d 176, 1987 A.M.C. 525, 1986 U.S. App. LEXIS 29770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jewel-m-cooper-v-diamond-m-company-ca5-1986.