Jerry T. Beech, Concrete Contractor, Inc. v. Mary Henderson

CourtCourt of Appeals of Tennessee
DecidedJune 7, 1996
Docket01A01-9507-CH-00308
StatusPublished

This text of Jerry T. Beech, Concrete Contractor, Inc. v. Mary Henderson (Jerry T. Beech, Concrete Contractor, Inc. v. Mary Henderson) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry T. Beech, Concrete Contractor, Inc. v. Mary Henderson, (Tenn. Ct. App. 1996).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT NASHVILLE ______________________________________________

JERRY T. BEECH ) CONCRETE CONTRACTOR, INC. ) ) Appellant, ) ) Davidson No. 93-3316-1 v. ) ) C.A. No. 01A01-9507-CH-00308 MARY HENDERSON,

Appellee. ) ) ) FILED June 7, 1996

Cecil W. Crowson Appellate Court Clerk APPEAL FROM THE CHANCERY COURT, PART I THE HONORABLE IRVIN H. KILCREASE, JR., CHANCELLOR

Maclin P. Davis, Jr. Nashville, Tennessee Attorney For Appellee

Joseph K. Dughman Bruce, Weathers, Corley, Dughman & Lyle Nashville, Tennessee Attorney for Appellant

AFFIRMED IN PART, REVERSED IN PART, AND REMANDED

OPINION FILED:

WILLIAM H. WILLIAMS, SENIOR JUDGE

CONCUR:

HIGHERS, J.

FARMER, J.

PRELIMINARY STATEMENT

This case concerns the payment on a contract for installation of a concrete driveway. Jerry

1 T. Beech Concrete Contractor, Inc. (hereinafter, "Beech") filed suit against Mary Henderson

(hereinafter, "Henderson") on a sworn account for nonpayment of the contract price for installing

a concrete driveway and a box drain. Following a bench trial, the trial court found that Beech and

Henderson had contracted to install a driveway and a box drain, but the trial court determined that

Beech had installed the driveway in an unworkmanlike manner causing it to have defects. As a

result, the trial court awarded Beech the contract price offset by the amount of property damage

Henderson allegedly suffered. Beech appealed, and the appeal is properly before this Court. We

affirm in part and reverse in part.

ISSUES

Beech’s issues are as follows:

I. Whether the evidence preponderates against the Chancellor's finding that Beech installed the driveway in an unworkmanlike manner.

II. Whether the evidence preponderates against the Chancellor's finding that Beech orally agreed to insure that rainwater would not accumulate on the driveway.

III. Whether the Chancellor erred in failing to find that Beech and Henderson had entered into an oral contract providing for liquidated damages of $700.00 if repair of the footprints failed to satisfactorily cure the defect.

IV. Whether the Chancellor erred in awarding damages based on Henderson's testimony regarding the diminution in the value of the property.

V. The Chancellor should have awarded pre-judgment interest since the damages of $8,505.00 are certain.

Henderson's issues are as follows:

VI. Whether Beech's complaint should be dismissed and the judgment awarded Beech in the amount of $2,005 should be set aside (a) because the false testimony of Beech's president constituted unclean hands on the part of Beech; (b) because Beech was a subcontractor by contract with Mrs. Armistead and is not entitled to a personal judgment against Mrs. Henderson; and (c) because the cost of repairing the defective driveway exceeded the contract price.

VII. Whether the amount of the judgment should be reduced by $555, which was included in the judgment for the box drain and culvert because (a) there was no agreement to pay that amount for the box drain and culvert; (b) there was no evidence that the box drain and culvert were installed by Beech; and (c) it was established by undisputed evidence that Beech removed the culvert from Mrs.

2 Henderson's property.

STATEMENT OF FACTS

Appellee Henderson resides in a home located at the intersection of Tyne and Lynwood

Boulevards in Nashville, Tennessee. In the Spring of 1993, Henderson contracted with Tara

Armistead (hereinafter, "Armistead") to design a driveway and a landscape plan for her property.

One of the purposes of the driveway and landscape plan was to divert water away from the house.

The water was flowing onto the property from Tyne and Lynwood Boulevards. After developing

a landscaping plan, Armistead's office notified Clayton King (hereinafter, "King"), Beech's president,

and asked him to provide an estimate for the driveway, box drain and culvert. After reviewing the

blueprint plans provided by Armistead, Beech provided an estimate of $7,950.00 for installation of

the driveway. Beech also submitted an estimate for a culvert to be installed at a cost of $340.00

and a box drain and grate to be installed at a cost of $430.00. Beech's estimate was submitted to

Armistead who presented it to Henderson. Henderson agreed to the estimate, and Armistead

contacted King and told him that Henderson wanted Beech to do the work.

Beech installed the driveway and box drain in July, 1993. During the course of the project,

Henderson objected to some prints from a workman's shoe that had been made in the wet concrete

along the driveway. Beech offered to repair the shoeprints, but Henderson wanted the entire section

of concrete replaced or $1,000 deducted from the cost of the project. Eventually, Beech repaired the

shoeprints and finished the project. Henderson found the repairs to the driveway to be unsightly and

unsatisfactory. Further, Henderson found that the driveway did not drain properly. Instead, the

driveway retained water in some sites causing pooling for up to one hour following a rainstorm.

Because of the shoeprints and the drainage problems, Henderson refused to pay Beech for the work

done to her property.

On November 10, 1993, Beech filed a complaint on sworn account against Henderson to

recover $8,505.00 for the installation of the concrete driveway and the box drain. In her Answer,

Henderson alleged that she never contracted with Beech for installation of a driveway and box drain,

and that Beech had contracted with Armistead, not Henderson. Subsequently, Beech amended its

complaint to pray for pre-judgment interest and to add Armistead as a defendant. Beech alleged that

Armistead acted as an agent for Henderson in contracting with Beech for the installation of the

driveway and that Henderson was, thus, liable for the payment.

3 A trial was held in this cause in the Chancery Court of Davidson County in December, 1994.

Beech's claims against Tara Armistead were dismissed at the conclusion of the Plaintiff's proof. On

January 11, 1995, the trial court entered a memorandum making its findings of fact and conclusions

of law wherein the Chancellor found that there was a contract between Beech and Henderson to

install a driveway for $7,950.00 and a culvert and box drain for an additional $555.00. The trial

court further found that Beech installed the driveway in an unworkmanlike manner resulting in

$6,500.00 in damages to Henderson's property. Therefore, the trial court awarded a judgment to

Beech in the amount of $2,005.00, which is the contract price of $7,950.00 minus $6,500.00 in

damages to Henderson's property, plus $555.00 for installation of the box drain. The trial court did

not grant the claim for pre-judgment interest and the costs were split equally between the parties.

An Order consistent with the opinion was entered on January 26, 1995. After timely filing a motion

to alter or amend the judgment, which the trial court later denied, Beech timely filed a notice of

appeal on April 12, 1995.

This Court is bound by Rule 13(d), T.R.A.P., upon our review of this record.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

V. L. Nicholson Co. v. Transcon Investment & Financial Ltd.
27 Cont. Cas. Fed. 80,250 (Tennessee Supreme Court, 1980)
Adams v. Dean Roofing Co., Inc.
715 S.W.2d 341 (Court of Appeals of Tennessee, 1986)
Haynes v. Cumberland Builders, Inc.
546 S.W.2d 228 (Court of Appeals of Tennessee, 1976)
Williams v. Southern Railway Company
396 S.W.2d 98 (Court of Appeals of Tennessee, 1965)
Inman v. Union Planters National Bank
634 S.W.2d 270 (Court of Appeals of Tennessee, 1982)
McKinnon v. Michaud
260 S.W.2d 721 (Court of Appeals of Tennessee, 1953)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Inman v. Inman
811 S.W.2d 870 (Tennessee Supreme Court, 1991)
Rich Printing Company v. McKellar's Estate
330 S.W.2d 361 (Court of Appeals of Tennessee, 1959)
Otis v. Cambridge Mutual Fire Insurance Co.
850 S.W.2d 439 (Tennessee Supreme Court, 1993)
Thornburg v. Chase
606 S.W.2d 672 (Court of Appeals of Tennessee, 1980)
Mink v. Majors
279 S.W.2d 714 (Court of Appeals of Tennessee, 1953)
Killian v. Campbell
760 S.W.2d 218 (Court of Appeals of Tennessee, 1988)
Fuller v. Orkin Exterminating Co., Inc.
545 S.W.2d 103 (Court of Appeals of Tennessee, 1975)
American Buildings Co. v. White
640 S.W.2d 569 (Court of Appeals of Tennessee, 1982)
Redbud Cooperative Corp. v. Clayton
700 S.W.2d 551 (Court of Appeals of Tennessee, 1985)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
Wilhite v. Brownsville Concrete Co., Inc.
798 S.W.2d 772 (Court of Appeals of Tennessee, 1990)
Smith v. Tennessee Coach Co.
194 S.W.2d 867 (Tennessee Supreme Court, 1946)
Estate of Jessee v. White
633 S.W.2d 767 (Court of Appeals of Tennessee, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Jerry T. Beech, Concrete Contractor, Inc. v. Mary Henderson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerry-t-beech-concrete-contractor-inc-v-mary-hende-tennctapp-1996.