JE Dunn Construction Company v. Owell Precast LLC

CourtDistrict Court, D. Idaho
DecidedAugust 3, 2020
Docket4:20-cv-00158
StatusUnknown

This text of JE Dunn Construction Company v. Owell Precast LLC (JE Dunn Construction Company v. Owell Precast LLC) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JE Dunn Construction Company v. Owell Precast LLC, (D. Idaho 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

JE DUNN CONSTRUCTION COMPANY, a foreign business Case No. 4:20-cv-00158-BLW corporation, MEMORANDUM DECISION AND ORDER Plaintiff/Counter Defendant,

v.

OWELL PRECAST LLC, dba OLYMPUS PRECAST, LLC,

Defendant/Counterclaimant/ Cross-Petitioner,

ERIKSSON TECHNOLOGIES, INC., a foreign business corporation,

Respondent on Cross-Petition,

INTRODUCTION Before the Court is JE Dunn’s Petition to Compel Arbitration. Dkt. 1. JE Dunn’s Motion to Compel Arbitration and Strike Defendant Olympus’ Counterclaims. Dkt. 8. Olympus’ Cross-Petition to Compel Arbitration. Dkt. 9. JE Dunn’s Motion to Strike Olympus’ Cross-Petition to Compel Arbitration. Dkt. 15. And, Eriksson Technologies Motion to Dismiss Olympus’ Cross-Petition. Dkt. 21. Briefing on all motions is complete.

Having fully reviewed the record, the Court finds that the facts and legal arguments are adequately presented in motions, the briefs on the merits, and the record. Accordingly, in the interest of avoiding delay, and because the Court

conclusively finds that the decisional process would not be significantly aided by oral argument, this matter will be decided on the record without oral argument. Dist. Idaho Loc. Civ. R. 7.1. For the reasons that follow, the Court will grant JE Dunn’s petition to compel arbitration, grant JE Dunn’s motion to strike Olympus’

counterclaims, require supplemental briefing on Olympus’ petition to compel arbitration, and deny the remaining motions. BACKGROUND The claims in this case arise out of a contract dispute between J.E. Dunn

(JED) and Olympus, related to precast concrete roof panels used in the Grey Wolf Project in Pocatello, Idaho. On August 1, 2017 Olympus entered into a contract with JED for the Grey

Wolf Project. Dkt. 8-2 at 4. The Contract was signed by the owner of Olympus and the vice president of JED. Id. at 7-8. The contract indicates that JED had the prime contract with a government client. In its contract with Olympus, JED is identified as the Design/Builder, and Olympus is identified as the Contractor. Id. at 4. Article 1.1.3 identifies “The Work” as the “construction and services required by the

Contract Documents, … required to fulfill the Contractor’s obligations.” Article 11.3 states that the contractor consents to joinder in any dispute or claim resolution process under the prime contract, including arbitration. Article 11.4 states:

Any claim or dispute not involving the Prime Contract or waived in this Contract shall be subject to arbitration unless the parties agree otherwise. The parties shall endeavor to resolve claims and disputes by mediation. Article 11.5 states that any arbitration award shall be final. Article 12.1 states that the contract shall be governed by the law of the place where the Work is located. On August 19, 2019 JED sent Olympus a letter alleging Olympus materially breached the contract. Dkt. 8-2 at 9. The letter alleges Olympus’s breach led to failure of the pre-cast in-plane roof connections at the project as well as delamination, effervescence, and bowing of precast panels. Id. JED sought to recover $1.58 million in overpayment due to the alleged breach. Id. at 16.

In December 2019 and continuing through early 2020 Olympus and JED discussed an arbitration agreement to resolve their disputes. Dkt. 8-2 at 17-29. It appears that the discussions related to the arbitration agreement broke down

because the parties could not agree on venue, the number of arbitrators, or including potentially liable third parties. Id. at 18. On February 28, 2020, Olympus filed a complaint alleging contract claims against JED and a Miller Act claim against various sureties in a separate case.1

Olympus Precast v. J.E. Dunn, et al., 1:20-cv-00103-SAB, Dkt. 1. On March 30, 2020, JED initiated the present case, Case No. 4:20-cv-00158-BLW, by filing a petition to compel arbitration. Dkt. 1. In its petition, JED alleges Olympus

proceeded with fabrication and installation of precast panels without fully approved shop drawings. Id. ¶ 14. The petition further alleges that Olympus continues to withhold its consent to enter into an arbitration agreement or select a panel of arbitrators. Id. ¶ 16. On May 1, 2020, Olympus filed an answer to the

petition and counterclaims, which are the same claims it had originally brought against JED in the case before Judge Bastian. Dkt. 6. On May 5, 2020, JED filed a motion to compel arbitration and to strike Olympus’ counterclaims. Dkt. 8.

On May 12, 2020, Olympus filed a cross-petition to compel arbitration. Dkt. 9. The cross-petition seeks to compel Eriksson Technologies to join in arbitration of the Olympus/JED dispute. Olympus alleges that it subcontracted its design

1 On May 1, 2020, Olympus filed a motion to consolidate both cases. 1:20-cv-00103- SAB, Dkt. 15. On June 22, 2020, Judge Bastian granted JED’s motion to stay that case pending a decision on the petition to compel arbitration in this case. 1:20-cv-00103-SAB, Dkt. 24. obligations for the project to Eriksson.2 Id. at 3. In the cross-petition Olympus states that it entered into a contract with JED, as described above, which included

an arbitration provision regarding any disputes arising from the project. Id. ¶¶ 8-9. Olympus alleges Eriksson was aware of, relied on, and substantially benefited from, the JED-Olympus Contract, and that JED relied on the Olympus-Eriksson

Contract. Id. ¶¶ 11-15. On June 2, 2020, JED filed a motion to strike Olympus’ cross-petition alleging it was procedurally improper. Dkt. 15. On June 19, 2020, Eriksson filed a motion to dismiss the Olympus’ cross-petition. Dkt. 21. Eriksson’s motion alleges

that it never agreed to arbitration and is not a party to the JED-Olympus contract. Dkt. 21-1. LEGAL STANDARD The Federal Arbitration Act provides that “any arbitration agreement within

its scope ‘shall be valid, irrevocable, and enforceable’ and permits a party ‘aggrieved by the alleged ... refusal of another to arbitrate’ to petition any federal district court for an order compelling arbitration in the manner provided for in the

agreement.” Chiron Corp. v. Ortho Diagnostic Sys., Inc., 207 F.3d 1126, 1130 (9th

2 Olympus has not included its contract with Eriksson as an exhibit so the Court relies on the allegations in the cross-petition. Cir. 2000) (citing 9 U.S.C. §§ 2 and 4). By its terms, the FAA “leaves no place for the exercise of discretion by a

district court, but instead mandates that district courts shall direct the parties to proceed to arbitration on issues as to which an arbitration agreement has been signed.” Dean Witter Reynolds Inc. v. Byrd, 470 U.S. 213, 218 (1985).

Accordingly, the Court’s role under the FAA is limited to determining “(1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement encompasses the dispute at issue.” Chiron Corp., 207 F.3d at 1130. The party seeking to compel arbitration has the burden of proving each requirement.

Ashbey v. Archstone Prop. Mgmt., Inc., 785 F.3d 1320, 1323 (9th Cir. 2015). If the Court answers yes to each of the above questions, the FAA requires that the Court enforce the arbitration agreement in accordance with its terms. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington Mutual Finance Group, LLC v. Bailey
364 F.3d 260 (Fifth Circuit, 2004)
General Atomic Co. v. Felter
434 U.S. 12 (Supreme Court, 1977)
Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Fogerty v. Fantasy, Inc.
510 U.S. 517 (Supreme Court, 1994)
Vaden v. Discover Bank
556 U.S. 49 (Supreme Court, 2009)
Whittlestone, Inc. v. Handi-Craft Co.
618 F.3d 970 (Ninth Circuit, 2010)
Fantasy, Inc. v. Fogerty
984 F.2d 1524 (Ninth Circuit, 1993)
ISC Holding AG v. Nobel Biocare Finance AG
688 F.3d 98 (Second Circuit, 2012)
Broadcort Capital Corp. v. Dutcher
859 F. Supp. 1517 (S.D. New York, 1994)
Dean Witter Reynolds Inc. v. Prouse
831 F. Supp. 328 (S.D. New York, 1993)
Aaacon Auto Transport, Inc. v. Barnes
603 F. Supp. 1347 (S.D. New York, 1985)
Platte Anchor Bolt, Inc. v. IHI, INC.
352 F. Supp. 2d 1048 (N.D. California, 2004)
Michael Ashbey v. Archstone Property Management
785 F.3d 1320 (Ninth Circuit, 2015)
Dinkins v. Schinzel
362 F. Supp. 3d 916 (D. Nevada, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
JE Dunn Construction Company v. Owell Precast LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/je-dunn-construction-company-v-owell-precast-llc-idd-2020.