James P. Sullivan v. Shell Oil Company, Herman R. Engberson v. Shell Oil Company

234 F.2d 733
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 31, 1956
Docket14571_1
StatusPublished
Cited by20 cases

This text of 234 F.2d 733 (James P. Sullivan v. Shell Oil Company, Herman R. Engberson v. Shell Oil Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James P. Sullivan v. Shell Oil Company, Herman R. Engberson v. Shell Oil Company, 234 F.2d 733 (9th Cir. 1956).

Opinion

JAMES M. CARTER, District Judge.

This appeal raises the question of the duty of an owner-occupier of premises to the employees of an independent contractor engaged in dismantling a tank on the premises. The action is one to recover damages for personal injuries sustained when the center column of one of defendant’s storage tanks on which plaintiffs were working, collapsed.

The question is here on appeal by plaintiffs, Sullivan and Engberson, from a directed verdict and judgment in favor of defendant, Shell. Jurisdiction of the District Court was based on diversity of citizenship.

Upon appeal from a judgment of dismissal entered upon the close of all the evidence, the appellant is entitled to the benefit of every inference which can reasonably be drawn from the evidence viewed in the light most favorable to the cause of action asserted. Gunning v. Cooley, 1930, 281 U.S. 90, 94, 50 S.Ct. 231, 74 L.Ed. 720; Schnee v. Southern Pacific Co., 9 Cir., 1951, 186 F.2d 745, 746; Graham v. Atchison, T. & S. F. Ry. Co., 9 Cir., 1949, 176 F.2d 819, 823; Kingston v. McGrath, 9 Cir., 1956, 232 F.2d 495.

Viewing the evidence in such light, the record discloses the following: Plaintiffs were employees of Southwest Welding & Manufacturing Company, hereafter referred to as Southwest. Southwest, in 1952, contracted with the defendant, Shell, to dismantle and rebuild a number of storage tanks including Tank 1006, a steel tank 24 feet high and 24 feet in diameter.

The center column, the main support for the roof, consisted of six inch channel backed by four inch channel. The column was anchored at the bottom of the tank, and welded at the top to a circular piece of metal, 24 inches in diameter, called the “dollar plate.” Twelve rafters were bolted to the dollar plate at one end, and, spreading out like the spokes of a wheel, were welded to clips on the inside of the shell of the tank at the other end. The steel roof was welded to the sides or shell of the tank. The roof thus was supported by the center column, the rafters and the sides of the tank.

Tank 1006 was put in service by Shell in May of 1951 and used for the storage of hydro-carbons and sulphuric acid. In January 1952 the tank was inspected by Shell. The inspection, conducted by Shell employees, was made in order to establish the corrosive rate of the metal, thereby enabling Shell to determine the approximate retirement date of the tank. *736 Following the inspection, it was concluded that the tank should be taken out of service in August of 1952. A further inspection in August of 1952 by Shell, revealed that the metal was extremely corroded and in places the center column was corroded through, leaving holes the size of baseballs or golf balls. The tank was then withdrawn from service and bids let for dismantling and rebuilding.

The customary procedure in dismantling such a tank is as follows: The roof of the tank is cut in half with acetylene torches; then the workers burn around the shell of the tank where the roof joins the shell; next the halves are themselves cut in half and lift pads are welded onto each quarter and removed by crane. At the start of the operation a hole is burnt in the center of the roof to allow fumes to escape. This exposes the dollar plate with the rafters resting on top of the dollar plate and bolted thereto.

While there is still some roof there to work on, the heads of the bolts that hold the inside edge of the rafter to the dollar plate are burnt off. The bolt itself does not drop through. Pressure keeps the bolt in place, holding the rafter to the dollar plate. Following the complete removal of the roof the rafters are removed one by one by burning the clip off at the outside edge of the rafter, and the rafter is then hit up or down, or jiggled to drop the bolts, and then removed.

Following this, the center column is taken out by wrapping a sling around it. Lastly, the outside shell itself is removed by burning off portions of the plate, piece by piece. With everything moving smoothly, a tank such as that Tank 1006 could be dismantled in one day.

On the particular day in question, the following work had been done. The hole was cut in the center of the roof, half of the roof had already been removed and the other half had been burnt almost all the way around the outside edge. The heads of the bolts that connected the rafters to the center column had been burnt off. Sullivan was starting to burn the remaining half into quarters when Engberson came up on top of the roof. It was at this time that the center column collapsed, resulting in the injuries to the appellants.

As to appellants’ knowledge, if any, of the defective column, the record shows: Both appellants were experienced in the field of repairing, dismantling and constructing tanks, Sullivan having performed this work for eleven years and Engberson for twelve or thirteen.

Sullivan testified that prior to the accident no one from Shell had talked to him about the tank; that he knew nothing of its prior condition, or what its contents had been; that he had no knowledge of the condition of the center column and that although he knew the center column was to be scrapped, and the top, bottom, and rafters saved for rebuilding, this meant nothing to him insofar as the condition of the center column as a support member was concerned; that there were two open manholes at the bottom of the tank, but he did not look inside, nor make any examination of the center column; that it was not his job to inspect the center column; that he had not investigated because “we start work on a tank, the tank is supposed to be O.K. to go on, reasonably safe to go on, and furthermore, we aren’t inspectors, we aren’t qualified as inspectors to go in and inspect the tank. It is supposed to be done by men that are qualified and if it is safe or not safe to tell us about it.”

Engberson testified that he was never at the tank with anybody from Shell to make an inspection of the tank; that he talked with Mr. Slobodnick of Shell as to what fittings he wanted saved; that Cady of Southwest gave him the work order the day before the accident; that he knew that the top, bottom and rafters of the tank were to be reused in rebuilding the tank; that he had been inside the tank for about ten minutes with Cady on a date two or three days before the accident happened and that from what he could see everything looked all right; that it was fairly dark inside the tank and one could not see very well; *737 one could not see the top six or eight feet of the center column; that Cady-asked him how much of the column he wanted to save; that he replied that as long as part was going to be scrapped, they might as well scrap all of it; that no one at Southwest told him anything about the center column and that he never saw any of Shell’s inspection reports; that he only had the work order in his possession; that he had heard this was an acid tank; that instructions to scrap a center column did not mean to him that the center column was no good insofar as support was concerned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edward J. Rich v. United States Lines, Inc.
596 F.2d 541 (Third Circuit, 1979)
Frasca v. Prudential-Grace Lines, Inc.
394 F. Supp. 1092 (D. Maryland, 1975)
Hite v. Maritime Overseas Corporation
380 F. Supp. 222 (E.D. Texas, 1974)
Garner v. Pacific Electric Railway Co.
202 Cal. App. 2d 720 (California Court of Appeal, 1962)
Gulf Oil Corporation v. Kenneth C. Bivins
276 F.2d 753 (Fifth Circuit, 1960)
Bedford v. Bechtel Corp.
342 P.2d 495 (California Court of Appeal, 1959)
Zimmer v. California Company
174 F. Supp. 757 (D. Montana, 1959)
Star v. Rogalny
162 F. Supp. 181 (E.D. Illinois, 1957)
Benson v. United States
150 F. Supp. 610 (N.D. California, 1957)
John Furukawa v. Yoshio Ogawa
236 F.2d 272 (Ninth Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
234 F.2d 733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-p-sullivan-v-shell-oil-company-herman-r-engberson-v-shell-oil-ca9-1956.