JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.

255 So. 3d 448
CourtDistrict Court of Appeal of Florida
DecidedSeptember 7, 2018
Docket17-0353
StatusPublished
Cited by6 cases

This text of 255 So. 3d 448 (JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC., 255 So. 3d 448 (Fla. Ct. App. 2018).

Opinion

NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION AND, IF FILED, DETERMINED

IN THE DISTRICT COURT OF APPEAL

OF FLORIDA

SECOND DISTRICT

JAMES JAY FORBES and FAY ANNETTE ) FORBES, ) ) Appellants, ) ) v. ) Case No. 2D17-353 ) ) PRIME GENERAL CONTRACTORS, ) INC., a Florida corporation, ) ) Appellee. ) )

Opinion filed September 7, 2018.

Appeal from the Circuit Court for Lee County; Alane C. Laboda, Judge.

P. Brandon Perkins and E. Carson Lange of Rogers Towers P.A., Fort Lauderdale, for Appellants.

No appearance for Appellee.

SALARIO, Judge.

This is an appeal from a final judgment on a claim for breach of contract.

James and Fay Forbes sued Prime General Contractors, Inc. for breach after Prime

walked off a home construction job. The Forbeses sought damages that included

payments they made to Prime under the contract, payments they made for updated architectural plans, certain other expenses, and a loss of equity in their home. After a

bench trial, the trial court found that Prime had materially breached its contract with the

Forbeses but declined to award these three items of damage. We reverse the damage

award in the final judgment and remand with instructions to award the Forbeses such

damages as will restore them to the position they enjoyed right before they inked their

contract with Prime. We affirm the judgment in all other respects.

The Forbeses and Prime signed a written contract under which Prime

agreed to renovate the Forbeses' home in accord with plans drawn up by an architect.

In exchange, the Forbeses agreed to pay Prime a total of $276,000 in five separate

draws. Under the draw schedule, the Forbeses were to pay (a) 25% of the contract

price upon signing, (b) 25% upon completion of demolition, (c) 25% upon completion of

the "dry-in" stage of construction,1 (d) 15% after roofing and siding installation, and (e)

the remaining 10% upon completion of the job. The contract provided that "any

alteration or deviation from this agreement must be made in writing and signed by the

Parties." Prime began the job as agreed, and the Forbeses paid the first two contract

draws—totaling $138,000. They also paid an additional $6000 for updated architectural

plans.

Under the contract, the Forbeses should not have had to pay anything

more until the dry-in phase of the project was done. Unfortunately, things hit a snag

before then. Prime said that the cost of the materials it needed to do the job had gone

1The contract defines the "dry-in" stage as "demo, framing rough-in electric, plumbing and mechanical, roof sheeting and felt and exterior windows and doors if available."

-2- up. It told the Forbeses that the work would now cost at least $550,000—almost twice

the original contract price—and demanded that the Forbeses immediately pay the third

draw plus an additional $31,450 for work Prime had already done and for which the

Forbeses had already paid. Prime presented the Forbeses with a written change order

making these adjustments. The Forbeses refused to sign it and told Prime that they

were prepared to move forward at the contract price. Prime refused and walked off the

job, leaving the Forbeses' home unfinished and uninhabitable.

Because they could not live in their home, the Forbeses began renting a

house nearby so that they had somewhere to stay. In the meantime, they looked for

another contractor to finish the work on their home—ultimately talking with five potential

candidates to perform the service—but none was willing to handle the job. After five

months of living in a rental with no luck getting the work on their house finished, the

Forbeses bought a new house and moved into it. They were unable, however, to pay a

mortgage on their new house and another mortgage on the home that Prime left

uninhabitable. So they let the uninhabitable home go into foreclosure. At the time they

contracted with Prime, the Forbeses had about $45,000 in equity in the house. That

equity was lost in the foreclosure.

The Forbeses sued Prime for breach of contract, and the case went to a

bench trial at which the evidence was consistent with the facts related above. The

Forbeses argued that Prime materially breached the contract by demanding payments

to which it was not entitled under the contract and thereafter walking off the job. Prime

contended, among other things, that the Forbeses also failed to perform under the

contract, to which the Forbeses answered that they were entitled to suspend

performance due to Prime's material breach. The Forbeses requested the following

-3- items of damages: $138,000 in payments made pursuant to their contract with Prime,

$6000 for updated architectural plans, $45,000 of lost equity in their home, $5600 in

rent, and various other expenses incurred in reliance on their contract with Prime. It is

clear from the damages the Forbeses requested that they were asking to be put in the

position they would have occupied had they not contracted with Prime in the first place.

Prime asserted and litigated at trial an affirmative defense that the Forbeses failed to

mitigate their damages.

About a month after the bench trial wrapped, the trial court entered a final

judgment. It found that Prime had materially breached the contract as the Forbeses

argued. However, it awarded the Forbeses as damages only the $5600 in rent they

paid while searching for a new contractor. The trial court explained that "[t]he purpose

of contract damages is to put the injured party in as good a position as that in which full

performance would have put him" and concluded that the Forbeses

failed to offer persuasive or credible evidence at trial of the difference between the market value of the home had it been completed, less such part of the contract price that has not been paid, and the value of the construction that has been furnished by [Prime] thus far.

The court also found, without elaboration, that the Forbeses "made a financial decision

not to engage in reasonable mitigation efforts" with respect to their damages.

This is the Forbeses' timely appeal of the final judgment. They argue two

points: (1) by looking to place them in the position they would have occupied had Prime

fully performed instead of the position they would have occupied had they never

contracted with Prime, the trial court used an incorrect method of calculating damages;

and (2) the trial court's finding that the Forbeses failed to mitigate their damages is

unsupported by the evidence. We review the first point de novo, see Tubby's Customs,

-4- Inc. v. Euler, 225 So. 3d 405, 407 (Fla. 2d DCA 2017), and the second for competent

substantial evidence, cf. RNK Family Ltd. P'ship v. Alexander-Mitchell Assocs., 890 So.

2d 297, 299 (Fla. 2d DCA 2004). See also Craigside, LLC v. GDC View, LLC, 74 So.

3d 1087, 1089 (Fla. 1st DCA 2011) ("While the parties are entitled to de novo review of

the trial court's rulings with respect to the legal effect of the contract, we are bound by

the trial court's findings of fact in a case, like the present one, where competent,

substantial evidence supports the findings."). Both points have merit.

Method of calculating damages. In calculating damages, the trial court

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
255 So. 3d 448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-j-forbes-fay-annette-forbes-v-prime-general-contractors-inc-fladistctapp-2018.