CANO, INC. v. MICHEL JUDET

CourtDistrict Court of Appeal of Florida
DecidedSeptember 22, 2021
Docket20-1509
StatusPublished

This text of CANO, INC. v. MICHEL JUDET (CANO, INC. v. MICHEL JUDET) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CANO, INC. v. MICHEL JUDET, (Fla. Ct. App. 2021).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

CANO, INC., Appellant,

v.

MICHEL JUDET, Appellee.

No. 4D20-1509

[September 22, 2021]

Appeal from the Circuit Court for the Nineteenth Judicial Circuit, St. Lucie County; Barbara W. Bronis, Judge; L.T. Case No. 562017CA001434AXXXHC.

Christopher B. Hopkins of McDonald Hopkins LLC, West Palm Beach, Ryan V. Kadyszewski of Ryan V. Kadyszewski, P.A., Palm Beach Gardens, and Mike Piscitelli and Jodi Cohen of Vezina, Lawrence & Piscitelli, P.A., Fort Lauderdale, for appellant.

Michael G. St. Jacques, II of MGS Law, P.A., Jupiter, for appellee.

WARNER, J.

Cano, Inc. appeals a final judgment in favor of Michel Judet for the amount that Judet overpaid Cano for work done pursuant to a construction contract which Cano breached. Cano claims that the trial court used the wrong measure of damages for breach of a construction contract. The trial court awarded damages to return Judet to his pre- contract position less the quantum meruit value of Cano’s services. Under the circumstances of this case, the measure of damages was proper. We also find no reversible error as to the other issues raised. We thus affirm.

In 2016, Judet’s home was damaged by lightning, and he entered into a written contract with Cano to repair the damage for a fixed price of $300,000 payable in $30,000 increments. Pursuant to the contract, Cano started work. Judet made $90,000 in payments. When Judet discovered that Cano had not obtained some of the building permits for the construction, he terminated Cano. As a result, Cano filed a construction lien on the property for $40,000 which it claimed was due. Cano sued Judet seeking to foreclose on the lien and sued Judet for breach of contract and unjust enrichment. Judet answered and counterclaimed for breach of contract. Judet sought discharge of the lien, restitution for the amount he paid Cano in excess of the value of the work, costs of storage of his household goods during construction, and disgorgement of monies paid for unpermitted work. Cano answered, denying it had breached the contract.

In the pre-trial stipulation, the parties stipulated that permits had not been obtained for the electrical or plumbing work. At the non-jury trial, both parties presented experts as to the reasonable value of the work performed. Judet’s expert placed the value of the work performed by Cano at $49,150. The expert also testified that Judet contracted with him to finish the repairs on the house at a cost of approximately $160,000 with extras. At the close of the evidence, the court expressed the opinion that Judet’s expert was more knowledgeable about the values in the community than Cano’s expert.

The court requested each party to submit a proposed final judgment. After receiving the proposed final judgments and waiting approximately thirty days, the court entered the final judgment proposed by Judet. 1 The trial found that Cano committed the first material breach of the contract by failing to obtain the required permits and by failing to substantially perform its obligations under the contract. Thus Cano was only entitled to the value of the work performed which the court found to be $49,150, consistent with Judet’s expert. The court found Cano’s expert not to be credible.

As Judet had already paid Cano $90,000, the court entered a judgment of $40,850 in favor of Judet on his counterclaims, the difference between the quantum meruit value of the work and what Judet paid. It found in favor of Judet on all of Cano’s claims and found Cano’s claim of lien invalid. Cano appeals the final judgment.

1 Cano claims that the court violated Perlow v. Berg-Perlow, 875 So. 2d 383 (Fla. 2004), in entering Judet’s proposed final judgment. Perlow is inapposite. What occurred in this case is more in line with Strand v. Escambia County, 992 So. 2d 150 (Fla. 2008). Here, the trial court did indicate some findings on the record, including that Judet’s expert was more believable than Cano’s expert. It also accepted proposed final judgments from both parties and then did not sign Judet’s proposed final judgment for another thirty days after they both were submitted, giving each party ample time to object.

2 Cano contends that the court used the wrong measure of damages in entering judgment for Judet. “Whether the trial court applied the correct measure of damages is a question of law reviewed de novo.” DFG Grp., LLC v. Heritage Manor of Mem’l Park, Inc., 237 So. 3d 419, 421 (Fla. 4th DCA 2018) (citing Del Monte Fresh Produce Co. v. Net Results, Inc., 77 So. 3d 667, 673 (Fla. 3d DCA 2011)).

Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contract. See Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039–40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargain. See McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).

Forbes v. Prime General Contractors, Inc., 255 So. 3d 448 (Fla. 2d DCA 2018), explains the alternative measures of damages in a construction contract case. In that case, the homeowners, the Forbeses, hired a contractor, Prime, to remodel their home and entered into a contract with periodic draws. Before the job was very far along, Prime determined that the cost of materials had increased and demanded almost twice the contract price. The Forbeses refused to sign a change order to that effect, and Prime walked off the job, leaving the home “unfinished and uninhabitable.” Eventually, the Forbeses sued Prime for breach of contract. After trial, the court found that Prime had materially breached, but awarded only a small amount of damages. The trial court concluded that “[t]he purpose of contract damages is to put the injured party in as good a position as that in which full performance would have put him” and the Forbeses had not presented evidence of the difference between the market value of the home had it been completed and the value of the construction which the contractor had furnished.

Reversing the trial court, the Second District noted that an owner had two alternative remedies:

When a party seeks damages for a total breach, “[the party] may treat the contract as void and seek the damages that will

3 restore [the party] to the position he was in immediately prior to entering the contract.” Rector [v. Larson’s Marince, Inc.], 479 So. 2d [783,] 785 [Fla. 2d DCA 1985]; see also McCray v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCray v. Murray
423 So. 2d 559 (District Court of Appeal of Florida, 1982)
Lotspeich Co. v. Neogard Corp.
416 So. 2d 1163 (District Court of Appeal of Florida, 1982)
Perlow v. Berg-Perlow
875 So. 2d 383 (Supreme Court of Florida, 2004)
Grossman Holdings Ltd. v. Hourihan
414 So. 2d 1037 (Supreme Court of Florida, 1982)
Strand v. Escambia County
992 So. 2d 150 (Supreme Court of Florida, 2008)
Broche v. Cohn
987 So. 2d 124 (District Court of Appeal of Florida, 2008)
Citizens Property Insurance Corporation v. Amat
198 So. 3d 730 (District Court of Appeal of Florida, 2016)
Federal Land Bank of Columbia v. Brooks
190 So. 737 (Supreme Court of Florida, 1939)
JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.
255 So. 3d 448 (District Court of Appeal of Florida, 2018)
Del Monte Fresh Produce Co. v. Net Results, Inc.
77 So. 3d 667 (District Court of Appeal of Florida, 2011)
DFG Grp., LLC v. Heritage Manor of Mem'l Park, Inc.
237 So. 3d 419 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
CANO, INC. v. MICHEL JUDET, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cano-inc-v-michel-judet-fladistctapp-2021.