City of Miami Beach v. Carner

579 So. 2d 248, 1991 WL 68575
CourtDistrict Court of Appeal of Florida
DecidedApril 30, 1991
Docket89-2726, 89-3003, 89-3004, 90-49, 90-50 and 90-126
StatusPublished
Cited by11 cases

This text of 579 So. 2d 248 (City of Miami Beach v. Carner) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Miami Beach v. Carner, 579 So. 2d 248, 1991 WL 68575 (Fla. Ct. App. 1991).

Opinion

579 So.2d 248 (1991)

CITY OF MIAMI BEACH, Florida, a Florida Municipal Corporation, and Miami Beach Redevelopment Agency, a Public Agency Existing under the Laws of Florida, Appellants,
v.
Stephen CARNER, Irwin H. Mason, and Lis, Inc., a Florida Corporation, As General Partners in Carner-Mason Associates, Ltd., a Florida Limited Partnership, D/B/a Miami Beach Marina, Appellees.

Nos. 89-2726, 89-3003, 89-3004, 90-49, 90-50 and 90-126.

District Court of Appeal of Florida, Third District.

April 30, 1991.

*249 Daniels & Talisman and Sam Daniels, Podhurst, Orseck, Josefsberg, Eaton, Meadow, Olin & Perwin and Joel S. Perwin, Miami, Laurence Feingold, Miami Beach, for appellants.

Steel, Hector & Davis and Gerry S. Gibson and Thomas M. Karr, Miami, for appellees.

Before NESBITT, BASKIN and JORGENSON, JJ.

NESBITT, Judge.

This is a consolidated appeal of orders entered on partial summary judgment and final judgment following a jury trial in a breach of contract case. Based on the following analysis, we reverse and remand for a new trial.

*250 Facts

While the specific facts relevant to each issue will be set forth within this opinion as necessary, the foundation facts are that in 1983 Carner-Mason Associates, appellee/plaintiff below, entered into a thirty-year lease under which the firm was to build and operate a marina on the City of Miami Beach's property. Various problems arose and in 1985, Carner-Mason stopped paying rent and filed a breach of contract suit against the City of Miami Beach and the Miami Beach Redevelopment Agency, appellants/defendants below. Carner-Mason remained on the property, however, and the city filed an eviction suit in 1986.[1] The firm ultimately remained on the property until 1989 when its mortgage was foreclosed.

The contract action alleged that the defendants had breached numerous provisions of the lease agreement. During the course of litigation, the trial court entered various rulings which were erroneous and which require a new trial. We shall address only those primary issues which control our decision and those secondary issues which may arise and impact the second trial.

Joint Liability of Redevelopment Agency and City

The first issue is whether the trial court correctly ruled that the redevelopment agency was a party to the lease and liable for any breach to the same extent as the city. We hold that the agency is jointly liable. While the directed verdict upon which this holding was based cannot stand, we treat the motion for directed verdict as if it were a motion for summary judgment on the issue and thus affirm that ruling. Cf. Harvey Bldg., Inc. v. Haley, 175 So.2d 780 (Fla. 1965) (Summary judgment may be categorized as a "pre-trial motion for a directed verdict." (citing to Locke v. Stuart, 113 So.2d 402 (Fla. 1st DCA 1959)).

The agency consists of the city commission and key members of the city administration, including the city manager, who is the executive director of the agency, and the assistant city manager, who is the agency's deputy director. After the lease was executed, the city and the agency entered into an agreement whereby the agency was to be completely responsible for administering and performing the contract and was to receive all income from the project. While the agency argues that it cannot be jointly liable with the city because its name is not listed as a party to the lease and because any warranties made were made exclusively by the city, the record shows that addenda to the lease which were incorporated into the final agreement define the city as both the city and its agency. The agency jointly invited bids; the lease's preamble stated that by resolution, the agency authorized and directed the city manager to negotiate with Carner-Mason and that the agency determined it was in South Beach's best interest to redevelop the marina on land subject to the control of the agency and pursuant to permits issued to the agency by the Department of Environmental Resources and the U.S. Corps of Engineers.

These facts indisputably show that the agency is jointly liable with the city for any breaches of the marina project lease agreement.

Partial versus Total Breach of the Contract

The trial court entered summary judgments as to liability for breach of the lease agreement against the city on five issues. Three issues of liability were left for trial. As to whether appellants would be liable for damages for total or partial breach, the lower court repeatedly ruled that Carner-Mason could recover for total breach of contract and that no issues as to *251 partial breach would be submitted to the jury. This was patently erroneous. The rule is quite clear that a contracting party, faced with a material breach by the other party, may treat the contract as totally breached and stop performance. However, if the complaining party continues to demand performance from the breaching party, damages can only be recovered for partial breach. Restatement (Second) of Contracts §§ 84, 243, 246, 247 (1981); see Johnson v. Dichiara, 84 So.2d 537 (Fla. 1955).

In this case, Carner-Mason claimed a total breach had occurred in August 1985 when the firm's principals decided the project was doomed and stopped construction. Nevertheless, by its actions, Carner-Mason did not treat any alleged breach as a total breach since it continued to stay on the property for four more years, until October 1989 when its mortgage was foreclosed.

Nevertheless, we do not hold as a matter of law that Carner-Mason is entitled to recover only for any partial breach which may be proven because it remains to be determined whether a non-waiver clause in the lease entitled Carner-Mason to remain on the property after declaring a breach and still recover total breach damages. The non-waiver clause states that failure of a party to enforce a lease provision would not waive a breach which may occur.

Defendants argue that the parties waived the non-waiver provision: Carner-Mason when it filed suit, and the defendants when they made written demand of eviction. They further argue that the provision is sufficiently ambiguous that it does not preclude the argument that Carner-Mason may be limited to damages for partial breach since it elected its remedy by choosing to remain on the property for four years after declaring a breach had occurred. See Protean Investors, Inc. v. Travel, Etc., Inc., 499 So.2d 49 (Fla. 3d DCA 1986); Doral Country Club, Inc. v. Curcie Bros., Inc., 174 So.2d 749, 751 (Fla. 3d DCA), cert. denied, 180 So.2d 656 (Fla. 1965). Thus, upon remand, both the significance of Carner-Mason's remaining on the property after declaring a breach and the significance of the lease agreement's non-waiver provision on the type of damages to which Carner-Mason should be entitled upon proof of a material breach must be determined.

Partial Summary Judgments

As to the summary judgments, we hold that all five bases upon which summary judgment on liability was entered for the plaintiff were erroneous because genuine issues of material fact remain to be decided. Each issue involved in the summary judgment will be addressed separately.

Failure of the City to Provide Survey Information

The trial court found that the city breached the contract by failing to provide Carner-Mason with adequate survey information on the marina site. The trial judge found that the city had a contractual obligation to have provided this information.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.
255 So. 3d 448 (District Court of Appeal of Florida, 2018)
Wilson v. Terwillinger
140 So. 3d 1122 (District Court of Appeal of Florida, 2014)
Asher v. Unarco Material Handling, Inc.
862 F. Supp. 2d 551 (E.D. Kentucky, 2012)
Citizens Property Insurance Corp. v. Ashe
50 So. 3d 645 (District Court of Appeal of Florida, 2010)
Nisenzon v. Morgan Stanley DW, Inc.
546 F. Supp. 2d 213 (E.D. Pennsylvania, 2008)
Murphy v. Implicito
920 A.2d 678 (New Jersey Superior Court App Division, 2007)
Midland Mutual Life Insurance Co. v. Mercy Clinics, Inc.
579 N.W.2d 823 (Supreme Court of Iowa, 1998)
Posik v. Layton
695 So. 2d 759 (District Court of Appeal of Florida, 1997)
Maxfly Aviation, Inc. v. Gill
605 So. 2d 1297 (District Court of Appeal of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
579 So. 2d 248, 1991 WL 68575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-miami-beach-v-carner-fladistctapp-1991.