Sunshine-Jr. Stores, Inc. v. Autopump Services Co. (In Re Sunshine-Jr. Stores, Inc.)

240 B.R. 788, 13 Fla. L. Weekly Fed. B 17, 1999 Bankr. LEXIS 1376
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedNovember 2, 1999
DocketBankruptcy No. 92-16406-8B1. Adversary No. 95-400
StatusPublished

This text of 240 B.R. 788 (Sunshine-Jr. Stores, Inc. v. Autopump Services Co. (In Re Sunshine-Jr. Stores, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunshine-Jr. Stores, Inc. v. Autopump Services Co. (In Re Sunshine-Jr. Stores, Inc.), 240 B.R. 788, 13 Fla. L. Weekly Fed. B 17, 1999 Bankr. LEXIS 1376 (Fla. 1999).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND MEMORANDUM OPINION

THOMAS E. BAYNES, Jr., Bankruptcy Judge.

INTRODUCTION

THIS MATTER came on for consideration upon Complaint brought by Debtor/Plaintiff, Sunshine-Jr. Stores, (“Sunshine-Jr.”) against the Defendant, Autopump Services Company, Inc. (“Au-topump”) for breach of contract. 1 The Court, having considered arguments by counsel, the entire record in this case, testimony of live witnesses, and all other relevant evidence, enters the following memorandum opinion.

BACKGROUND

Sunshine-Jr. operated convenience stores, a number of which were equipped with self service gasoline stations. Auto-pump is in the business of selling and installing equipment and canopies for gasoline service stations. On May 22, 1992, Sunshine-Jr. entered into a written Purchase Order (“the Contract”) with Auto-pump. 2 The Contract required Autopump to remove the old tanks and canopy, to install new tanks, and to construct islands and a new canopy at Sunshine-Jr.’s Store No. 20 in Apalachicola. The price for the work to be performed by Autopump was $67,500. 3 Approximately one month later, prior to beginning the project, Autopump subcontracted much of the construction to Phelps Petroleum (“Phelps”).

Autopump’s principal hired Phelps to perform all the work under Autopump’s agreement with Sunshine-Jr. except for mounting the canopy. This activity specifically included, among other things, removing the old gas tanks, pumps, and canopy, installing the new tanks and pumps, performing the electrical work, building the footers, and mounting the canopy columns. 4 In late June, Phelps obtained a permit and commenced work on the project.

FINDINGS OF FACT

The Beginning of the Project

On June 23, 1992, Phelps applied for a building permit with the city of Apalachicola. According to Mr. Phelps’ testimony, the building inspector issued a permit based on Mr. Phelps’ oral description of the project. 5 Apparently no design plans or written specifications were ever initially submitted to the city for inspection. In fact, the only design plan that appears to have existed at the beginning of the project is a layout sketch provided by Sunshine-Jr. to Phelps. 6 Later that same day, after obtaining the permit, Phelps commenced work on the project.

Phelps began by excavating, removing the old tanks, and installing the new tanks. In connection with installing the new tanks, Phelps performed plumbing and electrical work. The plumbing work consisted of laying underground field pipe *791 leading from the tanks to openings at ground level where gas trucks would insert supply lines. The electrical work consisted of routing conduit from the pumps through the walls and ceiling of the store, and exiting behind the checkout counter. The record indicates Phelps had to redo some of its plumbing and electrical work several times because of layout changes by Sunshine-Jr. after the Phelps’ work had been completed. 7

Phelps then performed the foundation and concrete work for the canopy. First, Phelps built the footers, or foundations, for the canopy columns. After excavating, Phelps created the skeleton of the footers by placing plywood boxes into the holes and inserting rebar in preparation for pouring the concrete. 8 Mr. Phelps testified that, prior to pouring the concrete, the city building inspector inspected the footer skeletons. 9 Next, Phelps mounted the canopy columns to the footers. With an excavator, Phelps lined up the columns with the anchor bolts and then tightened them down. 10 Finally, Phelps poured the concrete islands and slab on a day when the temperature was over one hundred degrees. 11 Mr. Phelps admitted at trial that because of the heat, the concrete slab never set properly and needed to be redone. 12

Erection of the Canopy and the Hurst Drawing

At this point in the project, Autopump sent a crew to the site to erect the canopy. 13 Autopump bought most of the materials for the canopy from Mason Corporation (“Mason”). 14 Autopump erected the high beams, the purlins, the pans that attach underneath the purlins, and some of the facia. Mr. Jones testified that, at this point in construction, the city of Apalachicola red-tagged the project for Autopump’s failure to submit an engineering drawing for the canopy. As a result, Autopump contracted with John Hurst of Hurst Engineering, Inc. for sealed plans and specifications of the canopy (“Hurst drawing”). 15 Mr. Hurst produced the signed and sealed drawing on July 21,1992. 16

Mr. Jones admits that after receiving the Hurst Drawing, he did not pay much attention to it. 17 Mr. Jones forwarded the Hurst drawing to Sunshine-Jr. who submitted it to the city for approval. 18 Based on the Hurst drawing, the city issued a permit, removed the stop order, and allowed Autopump to proceed with *792 the project. 19 Soon after, Autopump’s crew returned to the site and worked on the canopy for several more days. 20

Autopump’s Final Days on the Project

The record indicates on August 3, 1992, Christian Fenot (“Frenchy”), a long time subcontractor for Sunshine-Jr., 21 sent Au-topump’s canopy crew away. 22 The next morning, after being notified that his crew had been sent away, Mr. Jones contacted Mr. Phelps to find out what transpired on the site. 23 Shortly thereafter, Mr. Wanzo, Sunshine-Jr.’s Director of Operations, contacted Mr. Jones to arrange a meeting at the project site. 24 On August 7, the Wan-zo-Jones meeting took place at the project site. 25 The accounts in testimony of the representations made at this meeting are conflicting.

According to Mr. Wanzo’s testimony, he expressed concerns to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMC Industries, Inc. v. Barth Industries, Inc.
160 F.3d 1322 (Eleventh Circuit, 1998)
Hawaiian Inn of Daytona Beach, Inc. v. ROBERT MYERS, INC.
363 So. 2d 125 (District Court of Appeal of Florida, 1978)
JM Beeson Co. v. Sartori
553 So. 2d 180 (District Court of Appeal of Florida, 1989)
Braverman v. Van Bower, Inc.
583 So. 2d 381 (District Court of Appeal of Florida, 1991)
WW Gay Mech. Contr., Inc. v. Wharfside Two, Ltd.
545 So. 2d 1348 (Supreme Court of Florida, 1989)
Grossman Holdings Ltd. v. Hourihan
414 So. 2d 1037 (Supreme Court of Florida, 1982)
AIB MORTG. CO. v. Sweeney
687 So. 2d 68 (District Court of Appeal of Florida, 1997)
City of Miami Beach v. Carner
579 So. 2d 248 (District Court of Appeal of Florida, 1991)
Lonnie D. Adams Building Contractor, Inc. v. O'Connor
714 So. 2d 1178 (District Court of Appeal of Florida, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
240 B.R. 788, 13 Fla. L. Weekly Fed. B 17, 1999 Bankr. LEXIS 1376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunshine-jr-stores-inc-v-autopump-services-co-in-re-sunshine-jr-flmb-1999.