COUSINS CONST. v. Black, Crow & Eidsness, Inc.

488 So. 2d 838
CourtDistrict Court of Appeal of Florida
DecidedApril 9, 1986
Docket85-1215
StatusPublished
Cited by5 cases

This text of 488 So. 2d 838 (COUSINS CONST. v. Black, Crow & Eidsness, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
COUSINS CONST. v. Black, Crow & Eidsness, Inc., 488 So. 2d 838 (Fla. Ct. App. 1986).

Opinion

488 So.2d 838 (1986)

COUSINS CONSTRUCTION CO. NO. III, INC., of Florida, a Florida Corporation, Appellant/Cross-Appellee,
v.
BLACK, CROW & EIDSNESS, INC., a Florida Corporation; and Continental Casualty Company, a Foreign Corporation, Appellees/Cross-Appellants.

No. 85-1215.

District Court of Appeal of Florida, Second District.

April 9, 1986.

*839 Raymond C. Conklin of Stolba, Englander, Conklin, Brainard, DiSano & Verona, P.A., St. Petersburg, for appellant/cross-appellee.

John R. Bush of Bush, Ross, Gardner, Warren & Rudy, Tampa, for appellees/cross-appellants.

GRIMES, Judge.

In this complex and tortuous litigation involving claims of professional malpractice against Black, Crow & Eidsness, Inc. (BC & E), Cousins Construction Co. No. III, Inc., of Florida (Cousins) appeals from a $40,000 summary final judgment entered in its favor.

In 1973 Cousins, a land developing company which was considering the purchase and development of certain real estate, contracted with BC & E to perform the engineering work. Following receipt of BC & E's engineering documents, Cousins purchased the land and commenced construction. Within a few months, Cousins encountered numerous problems with respect to the land that made further development impossible. Construction was stopped late in 1974. The following year, Cousins brought suit for damages contending that BC & E was guilty of negligence and breach of contract for failing to advise Cousins of drainage, soil, and fill dirt problems, failing to design an adequate percolation pond and failing to furnish an accurate estimate of the cost of development. Following the introduction of extensive evidence, the court determined Cousins to be negligent as a matter of law on its negligence claim and submitted the balance of the case to the jury. The jury found against Cousins on its contract claim but returned a verdict for Cousins against BC & E in negligence for $65,600.

Following the trial, the court entered an order, the effect of which was to set aside the jury verdict, to grant Cousins' motion for directed verdict on liability on the breach of contract claim, and to award Cousins a new trial on damages only. Judge Robert Beach gave as the basis for ordering a new trial on damages that he had erred in one of his jury instructions on damages and that the verdict was grossly inadequate and against the manifest *840 weight of the evidence. These orders were affirmed by a per curiam decision without opinion of this court reported in Black, Crow & Eidsness, Inc. v. Cousins Construction Co. No. III, 351 So.2d 412 (Fla. 2d DCA 1977), cert. denied, 368 So.2d 1362 (Fla. 1979).

After the case was returned to the trial court, Judge David Seth Walker, who had then been assigned to the litigation, granted Cousins' motion to limit issues at the retrial of the case. The order precluded BC & E from the presentation of any evidence with respect to liability and to contributory or comparative negligence. However, it indicated that BC & E would be entitled to show that Cousins had failed to mitigate its damages at or subsequent to the time when it knew or should have known of BC & E's negligence.

In the meantime, in 1978 Cousins and its loan guarantors entered into an agreement with Barnett Mortgage Trust (Barnett), the real estate investment trust that had loaned Cousins the money with which to acquire the land and commence the development. Under the agreement, Cousins waived the right to contest the foreclosure of Barnett's mortgage on the land, conveyed to Barnett certain personal property connected with the development and assigned to Barnett the right to two-thirds of Cousins' recovery of damages in its lawsuit against BC & E. Cousins and the guarantors further agreed to pay Barnett $24,000 and to fund an additional $20,000 for future costs in the conduct of the lawsuit. Barnett agreed to release Cousins and the guarantors from any personal liability under the note and mortgage on the property. Upon the motion of BC & E, the court entered a partial summary judgment in 1982 finding that because of such agreement, Cousins' measure of damages could not include any prior or present indebtedness to Barnett.[1]

Thereafter, Judge Frank White, who was then assigned to the case, entered an order on Cousins' motion in limine, directing that BC & E was precluded from the presentation of any evidence with regard to the issues of liability, contributory negligence, comparative negligence, reliance or proximate cause. Finally, at a pretrial conference *841 held in 1985, the court, over Cousins' objection, entered a summary final judgment in favor of Cousins for $40,000. Cousins appeals that judgment. BC & E cross-appeals, complaining of several interlocutory orders which preceded the entry of the final summary judgment.

The primary issue in this case concerns the effect of the agreement with Barnett upon Cousins' cause of action against BC & E. In entering the summary judgment, Judge White reasoned that because of the Barnett agreement, Cousins could not recover from BC & E any development expenditures that had been paid with funds borrowed from Barnett. Apparently, Judge White arrived at the figure of $40,000 because Cousins' certified public accountant had testified at the trial that Cousins had spent on the development only $40,000 more than the monies borrowed from Barnett. Cousins points out that even if the court's rationale was proper, its ruling overlooked liabilities of $347,698 not covered by the Barnett loan which had been incurred but not yet paid. More importantly, Cousins contends that the Barnett agreement should be totally disregarded and the fact of its existence deemed inadmissible on the issue of damages. BC & E relies upon the logic that since all but $40,000 of Cousins' expenditures came from the Barnett loan, and the Barnett loan has now been satisfied without personal liability, Cousins' recovery should be limited to $40,000.

There is very little law on this issue. However, the opinion in Robert E. Owen & Associates v. Gyongyosi, 433 So.2d 1023 (Fla. 4th DCA 1983), petition for review denied, 444 So.2d 417 (Fla. 1984), warrants consideration. In that case, Owen, an engineering firm, contracted with Southeastern to conduct periodic inspections on a sewer project being constructed on Southeastern's property. Despite Owen's certification that the sewer project was properly constructed, Owen had not properly checked the system and it had been constructed in a manner which would not pass governmental inspection. About the time the system was completed, Southeastern had contracted to sell the property to Mr. and Mrs. Gyongyosi. In settlement of the controversy over the sewer system which arose between Southeastern and the Gyongyosis, Southeastern obtained a release in exchange for conveying the property to the Gyongyosis, paying them $50,000 and assigning to the Gyongyosis its contract with Owen. The Gyongyosis then sued Owen for damages incurred in rectifying the defective sewer system. The court found that the Gyongyosis' damages were $146,222.62 and entered a judgment for that sum less a setoff of the $50,000 that Southeastern had paid to the Gyongyosis.

On appeal, the court held that there was competent evidence to support the finding that Owen was liable for the Gyongyosis' costs of repairing the sewer system. In a split decision on the cross-appeal, the court further held that the judgment should not have been subject to the $50,000 setoff of the money paid by Southeastern to the Gyongyosis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Miami Beach v. Carner
579 So. 2d 248 (District Court of Appeal of Florida, 1991)
Black, Crow & Eidsness, Inc. v. Cousins Construction Co., No. III, Inc. of Fla.
556 So. 2d 1146 (District Court of Appeal of Florida, 1989)
Roma Construction Co. v. Goodman
557 So. 2d 58 (District Court of Appeal of Florida, 1989)
E.H. v. K.S.
511 So. 2d 345 (District Court of Appeal of Florida, 1987)
In Re Adoption of Baby Girl C
511 So. 2d 345 (District Court of Appeal of Florida, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
488 So. 2d 838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cousins-const-v-black-crow-eidsness-inc-fladistctapp-1986.