Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc.

CourtDistrict Court, D. Hawaii
DecidedJune 28, 2019
Docket1:16-cv-00205
StatusUnknown

This text of Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc. (Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc., (D. Haw. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF HAWAI‘I

UNITED STATES for the use and CIVIL NO. 16-00205 DKW-WRP benefit of KINGSTON ENVIRONMENTAL SERVICES, INC., a Missouri corporation, ORDER GRANTING PLAINTIFF’S MOTION TO LIFT STAY Plaintiff,

vs.

DAVID BOLAND, INC., WESTERN SURETY COMPANY, GRANITE PRECASTING & CONCRETE, INC., and HAWAII GEOPHYSICAL SERVICES, LLC,

Defendants,

and

UNITED STATES for the use and Benefit of DAVID BOLAND, INC.

Counterclaim Plaintiff,

KINGSTON ENVIRONMENTAL SERVICES, INC. and BERKELY REGIONAL INSURANCE COMPANY,

Counterclaim Defendants. INTRODUCTION Plaintiff Kingston Environmental Services, Inc. (“Kingston”) moves to lift

the stay of its action against Defendants Western Surety Company and David Boland, Inc. (“Boland” and together with Western Surety, the “Defendants”). Kingston is Boland's subcontractor on a military construction project on Oahu.

Pursuant to this Court’s August 2017 Order granting Defendants’ Motion to Stay, over the course of the past two years, Kingston has pursued contractually- mandated administrative remedies for its breach of contract claims, obtaining contracting officer final decisions (COFDs) regarding the extent of the

government’s liability for those claims. Finding that Kingston has satisfied its contractual obligation to exhaust administrative remedies prior to proceeding with its civil action against Boland, the Court GRANTS Plaintiff’s Amended Motion to

Lift Stay (Dkt. No. 169). BACKGROUND I. The Project and Subcontract Boland is the prime contractor (Contract No. W9128A-12-C-0009 or “Prime

Contract”) on an infrastructure construction project for the United States Army Corps of Engineers (“USACE”) at Wheeler Army Airfield, Oahu, Hawaii (the “Project”). Defendant Western Surety issued performance and payment bonds on

2 behalf of Boland for the Project. Complaint, Dkt. No. 1, ¶¶ 10–11. Boland subcontracted with Kingston to provide labor, materials, equipment, and services

(“Subcontract”).1 Kingston contends that Boland mismanaged the Project, which had an original completion date of approximately May 2015. Boland acknowledges that

the Project was behind schedule, and that its management of the Project may have been “below average” due to its “strained relationship” with the government but asserts that the majority of the issues forming the basis for Kingston’s claims against Boland are issues for which the USACE is or may be responsible.

Kingston Ex. A, 7/19/17 Hildebrandt Dep. at 83–85; Dkt. No. 134-1. Kingston filed this action on April 29, 2016 seeking payment from Western Surety of its bonds under the Miller Act, 40 U.S.C. § 3133 et seq., (Count I) and

alleging that Boland breached the Subcontract (Count II). Complaint ¶¶ 38–50. II. The Stay At the time it initiated this action, Kingston had not submitted requests to Boland to sponsor or submit to the government all claims for which the USACE

might be responsible for Kingston’s losses. See Order Granting in Part

1Kingston’s 2012 Subcontract is attached as Exhibit A to the Declaration of Craig Hildebrandt, Dkt. No. 116-1, and as Exhibit B to Boland’s Concise Statement of Facts, Dkt. No. 116-2.

3 Defendants’ Motion for Partial Summary Judgment and Staying Case (2017 Order), Dkt. No. 145, August 30, 2017. The parties disputed whether Kingston

could pursue the claims asserted here prior to exhausting the remedial procedure specified in the Subcontract, as Kingston had done previously with other claims. Id.

On June 16, 2017, Defendants filed a Motion for Summary Judgment, which argued that Kingston failed to comply with the contractually-mandated remedial procedure in Subcontract Paragraph 13A, which is a condition precedent to the present civil action. See Dkt. No. 115. Defendants moved to stay this action and

enforce the administrative remedies outlined in Subcontract Paragraph 13A, which provides that any claims by Kingston against Boland for which the USACE “may be responsible” must be pursued first by Boland on behalf of Kingston through the

remedial procedures set forth in the Prime Contract between Boland and the USACE. Paragraph 23 of the Subcontract, entitled “Waivers and Stays,” provides that Kingston agrees to stay any action pending the completion of the Prime Contract’s remedial procedure as required by Paragraph 13. Finding that

Kingston was contractually obligated to exhaust claims for which the USACE might bear responsibility, this Court stayed proceedings.

4 Since August 2017, Kingston has pursued its claims administratively, submitting the following seven claims to the contracting officer:

1. CP-141.7 Cost Overrun Claim 2. CP-141.1 UXO Claim 3. CP-141.2 FPVC Claim 4. CP-141.3 Box Culvert Utility Relocation Claim 5. CP-141.4 Utility Pole Pads Claim 6. CP-141.5 Box Culvert Select Backfill Claim 7. CP-141.6 Airdrome Construction Entrance Claim

Amended Motion to Lift Stay (Motion), Dkt. No. 169, at 3. In February 2019, the contracting officer found that the USACE was responsible for Claim #2, the “UXO” claim (CP141.1), in the amount of $1,900.2 Id., 4. The six remaining claims were rejected, including Claim #1, the $6,882,738 “Cost Overrun” claim that makes up the bulk of Kingston’s claims against Boland. Id. Kingston agreed with three of the COFDs rejecting USACE liability, Claim #1, Claim #3, and Claim #7, and elected to only appeal the other three COFDs, Claim #4, Claim #5, and Claim #6, to the Armed Services Board of Contract Appeals (ASBCA). Id. The ASBCA has not yet reached a decision on the three appealed COFDs. See

2Plaintiffs state that the COFDs are attached as Exhibit A (Motion at 4) but no such attachment was filed. As a result, the Court is unable to determine on what day the COFDs were issued or the precise content of the COFDs.

5 Defendants’ Opposition to Plaintiff’s Amended Motion to Stay (Opp.), Dkt. No. 176.

On April 24, 2019, Plaintiff filed an Amended Motion to Lift Stay (Motion).3 Dkt. No. 169. On May 16, 2019, Defendants filed an Opposition (Dkt. No. 176), and Plaintiff timely replied (Dkt. No. 177). Pursuant to Local

Rule 7.2(d), the Court finds this matter suitable for disposition without a hearing. LEGAL FRAMEWORK “[T]he power to stay proceedings is incidental to the power inherent in every court to control disposition of the cases on its docket with economy of time and

effort for itself, for counsel, and for litigants.” Landis v. N. Am. Co., 299 U.S. 248, 254 (1936). “The exertion of this power calls for the exercise of sound discretion.” CMAX, Inc. v. Hall, 300 F.2d 265, 268 (9th Cir. 1962); see Clinton v.

Jones, 520 U.S. 681, 706 (1997) (“The District Court has broad discretion to stay proceedings as an incident to its power to control its own docket.”); Lockyer v. Mirant Corp., 398 F.3d 1098, 1109 (9th Cir. 2005) (“A district court has discretionary power to stay proceedings in its own court[.]”). When a stay is

requested because of pending proceedings that bear on the case, the court may

3Kingston erroneously filed an unsigned version of this Motion on April 24, 2019. (Dkt. No. 168). That motion is superseded by this one and the previous motion is DENIED as moot.

6 grant a stay in the interests of the efficiency of its own docket and fairness to the parties. See Leyva v. Certified Grocers of Cal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Clinton v. Jones
520 U.S. 681 (Supreme Court, 1997)
Lockyer v. Mirant Corp.
398 F.3d 1098 (Ninth Circuit, 2005)
Sarang Corp. v. United States
76 Fed. Cl. 560 (Federal Claims, 2007)
Sitco General Trading & Contracting Co. v. United States
87 Fed. Cl. 506 (Federal Claims, 2009)
Olsberg Excavating Co. v. United States
31 Cont. Cas. Fed. 71,445 (Court of Claims, 1983)
Rider v. United States
32 Cont. Cas. Fed. 73,473 (Court of Claims, 1985)
Cmax, Inc. v. Hall
300 F.2d 265 (Ninth Circuit, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-environmental-services-inc-united-states-for-the-use-and-hid-2019.