James Harrell v. The Ryland Group, doing business as Ryland Homes, a foreign for-profit corporation

CourtDistrict Court of Appeal of Florida
DecidedAugust 13, 2019
Docket18-3728
StatusPublished

This text of James Harrell v. The Ryland Group, doing business as Ryland Homes, a foreign for-profit corporation (James Harrell v. The Ryland Group, doing business as Ryland Homes, a foreign for-profit corporation) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Harrell v. The Ryland Group, doing business as Ryland Homes, a foreign for-profit corporation, (Fla. Ct. App. 2019).

Opinion

FIRST DISTRICT COURT OF APPEAL STATE OF FLORIDA _____________________________

No. 1D18-3728 _____________________________

JAMES HARRELL,

Appellant,

v.

THE RYLAND GROUP, doing business as Ryland Homes, a foreign for-profit corporation,

Appellee. _____________________________

On appeal from the Circuit Court for Duval County. Karen K. Cole, Judge.

August 13, 2019

LEWIS, J.

Appellant, James Harrell, appeals the final summary judgment entered in favor of Appellee, The Ryland Group, Inc., d/b/a Ryland Homes, and raises two issues. Appellant argues that the trial court erred in ruling that the statute of repose of section 95.11(3)(c), Florida Statutes (2016), applies. In the alternative, he argues that Appellee failed to establish that the statute of repose had run. We affirm.

BACKGROUND

In June 2016, Appellant filed against Appellee an amended complaint for damages for injuries he allegedly sustained around June 6, 2012, when an attic ladder he was climbing at a residential home (“the home”) for purposes of repairing a leak collapsed underneath him. 1 Appellant alleged that Appellee constructed and sold the home prior to June 6, 2012, and was negligent “by failing to ensure that the attic ladder was installed in a secure manner with the appropriate hardware” and “by failing to verify that the ladder was secure before selling the home.” Appellee filed a motion to dismiss, arguing in part that Appellant’s claim was barred by the ten-year statute of repose of section 95.11(3)(c), Florida Statutes. The trial court found that the statute is applicable because an attic ladder is an improvement to real property, but denied the motion upon further finding that it was not clear from the face of the complaint whether the suit was filed before the expiration of the statute of repose.

Appellee then filed a motion for summary judgment, in which it alleged and argued as follows. In July 2003, Appellee entered into an agreement with the original owners, pursuant to which it was to construct and sell the home to them. On or around April 30, 2004, the construction of the home was completed and a certificate of occupancy was issued. By that date, final performance had occurred and final payment had become due for all the contracted-for services related to the construction of the home. On or around May 7, 2004, Appellee executed a warranty deed conveying title to the home to the original owners, who took actual possession of the home. As found by the trial court, the installation of the attic ladder was an improvement to real property; thus, section 95.11(3)(c) applies. The issuance of the certificate of occupancy, the conveyance of the home to the original owners, and the recording of the warranty deed confirm that “all construction activities on the Home were complete, and paid for, and that the Original Owners took actual possession of the Home on [May 7, 2004].” As such, any claims relating to the home

1 Appellant filed the original complaint in September 2015 against Chandler’s Trim, Inc., who he alleged negligently installed the attic ladder without “the proper hardware, including adequate- sized screws” and as to whom he subsequently dismissed the action with prejudice.

2 expired ten years later, on May 7, 2014, rendering Appellant’s claim time barred.

Appellee filed several exhibits in support of its motion. A rider to the agreement between Appellee and the original owners reflects a contract date of July 29, 2003, and an estimated closing date of March and that the contract included optional “[p]ull down attic stairs” for $249. A certificate of occupancy was issued on April 30, 2004, stating that the home “has been completed to the best of our knowledge in compliance with all Building Code and Zoning Regulations applicable therein.” A warranty deed reflects that Appellee conveyed the home to the original owners on May 7, 2004. Appellee also filed the affidavit of William Berryhill, the vice-president of the successor corporation by merger to Appellee, in which Berryhill attested in part as follows:

5. . . . The issuance of the Certificate of Occupancy indicates that construction of the Home was completed as of April 30, 2004. I know this based on Ryland’s standard building procedures and I can also attest to the fact that Ryland’s standard building procedures regarding completion of construction and application for the Certificate of Occupancy are common to other production home builders.

6. To be even more specific, issuance of the Certificate of Occupancy on April 30, 2004 indicates that as of that date final performance of all of the contracted- for services provided by the professional engineer, registered architect, or licensed contractor with respect to the Home were complete. In other words, on April 30, 2004 all of the contract(s) . . . were complete with respect to the Home.

....

8. Ryland’s procedures and protocols would not have permitted the conveyance of the Home as signified by the Warranty Deed without final completion of the contract(s) . . . with respect to the Home and final payment (i.e. closing) delivered to Ryland by the Original Owners. 3 9. The recording of the Warranty Deed on or about May 7, 2004 provides final confirmation that all construction activities on the Home were complete, and paid for, and that the Original Owners took actual possession of the Home on that date.

In his response, Appellant argued that section 95.11(3)(c) does not apply because “the act of fastening a pre-assembled attic ladder does not constitute design, planning or construction of an improvement to real property” and even if the statute were applicable, Appellee failed to establish that the alleged negligent act occurred more than ten years before this action was filed because it has not shown when the ladder was installed. At the motion hearing, Appellant’s counsel argued that although the summary judgment evidence indicates that the contract had been completed, it “ignores the fact that sometimes builders have to come back out and do things that they forgot to do as part of that contract. And so, without knowing when this attic ladder was installed, I don’t think [Appellee] can carry its burden of establishing when the construction was abandoned or completed.”

The trial court entered final summary judgment for Appellee. This appeal followed.

ANALYSIS

The party moving for summary judgment must establish the absence of any genuine issue of material fact and its entitlement to judgment as a matter of law. Bradley v. Fort Walton Beach Med. Ctr., Inc., 260 So. 3d 1178, 1180 (Fla. 1st DCA 2018). When the movant satisfies this initial burden, the burden shifts to the opposing party to demonstrate the existence of disputed issues of fact by presenting evidence of countervailing facts or justifiable inferences from the facts presented. Id. A mere assertion that an issue exists does not suffice; “general allegations and legal argument do not constitute evidence of disputed issues of material fact.” Id. The trial court must draw every possible inference in favor of the nonmoving party and may grant the motion only if the facts are so crystallized that nothing remains but questions of law. Convergent Techs., Inc. v. Stone, 257 So. 3d 161, 166 (Fla. 1st DCA 2018). An order granting summary judgment is reviewed de novo. Id. 4 Likewise, an issue of statutory interpretation is reviewed de novo. Whitney Bank v. Grant, 223 So. 3d 476, 479 (Fla.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trust Company Bank v. United States Gypsum Company
950 F.2d 1144 (Fifth Circuit, 1992)
Snyder v. Wernecke
813 So. 2d 213 (District Court of Appeal of Florida, 2002)
Plaza v. Fisher Development, Inc.
971 So. 2d 918 (District Court of Appeal of Florida, 2007)
Joseph Cherilus v. Federal Express
87 A.3d 269 (New Jersey Superior Court App Division, 2014)
Ryan & Jessica Dominguez v. Hayward Industries
201 So. 3d 100 (District Court of Appeal of Florida, 2015)
Searcy, Denney, Scarola, Barnhart & Shipley, etc. v. State of Florida
209 So. 3d 1181 (Supreme Court of Florida, 2017)
Gary G. Debaun v. State of Florida
213 So. 3d 747 (Supreme Court of Florida, 2017)
WHITNEY BANK, a Mississippi state v. Von Daniel Grant Jr., and Lisa D. Grant
223 So. 3d 476 (District Court of Appeal of Florida, 2017)
Simmons v. Rave Motion Pictures Pensacola, L.L.C.
197 So. 3d 644 (District Court of Appeal of Florida, 2016)
Diana v. Russo Development Corp.
799 A.2d 689 (New Jersey Superior Court App Division, 2002)
Bradley v. Fort Walton Beach Med. Ctr., Inc.
260 So. 3d 1178 (District Court of Appeal of Florida, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
James Harrell v. The Ryland Group, doing business as Ryland Homes, a foreign for-profit corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-harrell-v-the-ryland-group-doing-business-as-ryland-homes-a-fladistctapp-2019.