Bernard Schoninger Shopping Centers, Ltd. v. J.P.S. Elastomerics, Corp.

102 F.3d 1173, 1997 U.S. App. LEXIS 87, 1997 WL 541
CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 6, 1997
Docket95-4636
StatusPublished
Cited by15 cases

This text of 102 F.3d 1173 (Bernard Schoninger Shopping Centers, Ltd. v. J.P.S. Elastomerics, Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bernard Schoninger Shopping Centers, Ltd. v. J.P.S. Elastomerics, Corp., 102 F.3d 1173, 1997 U.S. App. LEXIS 87, 1997 WL 541 (11th Cir. 1997).

Opinion

TJOFLAT, Circuit Judge:

The controversy in this diversity suit stems from a leaky roof. The owner of the porous building seeks money damages against the installer of the roof under several legal theories. The district court held the owner’s claims barred on the ground that the applicable statute of limitations had run. The district court entered summary judgment for the installer, and the owner appeals. We affirm.

I.

Bernard Schoninger Shopping Centers, Ltd., the appellant, is a limited partnership organized under the laws of Florida. 1 Schoninger owns and manages ten shopping centers, one of which includes a Kmart located in Bradenton, Florida. In July 1984, Schoninger decided to refurbish the roof of the Kmart building, a roof with an area greater than 100,000 square feet. Sehoninger sought bids for the project and chose J.P. Stevens & Company, Inc., the predecessor of the appellee, J.P.S. Elastomerics, Inc. 2 JPS is a Delaware corporation which manufactures and sells roofing products, including a synthetic material called “Hipalon Hi-Tuff Membrane” (the “membrane”). When unrolled, attached, and sealed to an existing roof, the membrane resembles a large plastic sheet that repels water from the roof. In this case, the membrane covers the original Kmart roof, which was not removed. The original roof consists of a one-half-inch, gyp-sumboard deck with tar and gravel on top and fiberglass insulation underneath.

The employees of JPS themselves do not install the membrane. Instead, JPS maintains standard agreements with various subcontractors, or “applicators,” to install the membrane. From a list of these authorized applicators, Schoninger chose General Roofing Industries, Inc. (“GRI”) to attach the membrane to the Kmart roof. GRI then contracted with Schoninger to do the work. 3 GRI used an installation manual supplied by JPS to purchase the supplies required to complete the project. These supplies included an unspecified amount of JPS’ membrane, a large quantity of one-half-inch-thick wood fiberboard to be placed under the membrane, *1176 and several thousand “toggle bolts” to secure the membrane and fiberboard to the Kmart roof. 4

In early September 1984, GRI notified JPS that GRI had completed its work on the Kmart roof. On September 7, 1984, an employee of JPS, Paul Dillenbeck, met with an employee of GRI, Dan Caldwell, and an employee of Olympic Manufacturing Group, Inc., 5 Stan Choiniere, to inspect the completed work. In a report dated the same day, Choiniere described defects in the installation of the toggle bolts. Schoninger did not receive a copy of Choiniere’s report, but JPS and GRI apparently did.

Dillenbeck also filed an inspection report, dated September 8, 1984 (“Dillenbeck’s first report”), which characterized GRI’s work as entirely good. Despite corporate policy to the contrary, JPS sent a copy of Dillenbeck’s first report to Schoninger. In a separate report dated September 10, 1984 (“Dillenbeck’s second report”), however, Dillenbeck listed five defects in the work done on the Kmart roof. Attached to Dillenbeek’s second report was a “punch list” of flaws that required the attention of GRI; the punch list bears the signature of GRI’s Dan Caldwell. Schoninger never received Dillenbeek’s second report. Although the Choiniere report and Dillenbeek’s second report catalogued several deficiencies in the Kmart roof, Dillenbeck’s superiors at JPS nevertheless issued to Schoninger a ten-year, written warranty for the roof, effective September 18, 1984. 6

On September 29, 1984, the tenant of the Kmart building reported leaks in the newly completed roof. Schoninger contacted GRI, which performed repairs. The leaks persisted, however, and the warranty department of JPS became involved in coordinating the repair efforts. The roof continued to leak. On August 5, 1988, JPS terminated GRI as the subcontractor responsible for repairing the Kmart roof. JPS reassigned the task to National Skyway Roofing, Inc. Shortly thereafter, however, JPS terminated National Skyway and reassigned the work to Atlantic Roofing, Inc., which continued to attempt to repair the Kmart roof. The roof never stopped leaking. In September 1991, JPS informed Schoninger that, due to water damage, at least one portion of the original roof would require replacement.

Schoninger filed this complaint on March 18, 1993, in the Circuit Court of Dade County, Florida. The complaint alleged seven claims, including the following: fraud, negligent misrepresentation, breach of express warranty, breach of implied warranty of fitness for particular purpose, breach of implied warranty of merchantability, and negligence in the design, manufacture, and installation of the roofing system. 7 On April 20, 1993, JPS removed the case to the United States District Court for the Southern District of Florida pursuant to 28 U.S.C. § 1441 (1994). 8

After more than eighteen months of discovery, JPS moved for summary judgment, contending that Schoninger’s claims were barred by Fla. Stat. ch. 95.11(3)(c) (1995). 9 *1177 On April 13, 1995, the district court granted: the motion, holding that Schoninger’s claims were time-barred. This appeal followed.

II.

Our review of a district court’s grant of summary judgment is de novo. Duke v. Massey, 87 F.3d 1226, 1230 (11th Cir.1996). We view in the light most favorable to the plaintiff the evidence bearing on the issue of when its cause of action arose. We give the plaintiff the benefit of all reasonable inferences on this point. Florida law determines when the applicable statute of limitations began to run in this case, but federal law determines whether the evidence supporting this starting date suffices to entitle the defendant to summary judgment. See Hutcherson v. Progressive Corp., 984 F.2d 1152, 1155 (11th Cir.1993).

III.

A.

Schoninger argues that the district court erred in applying the four-year statute of limitations contained in Fla. Stat. ch. 95.11(3)(c) to each of Schoninger’s claims. This provision applies to “[a]n action founded on the design, planning, or construction of an improvement to real property?’ Fla. Stat. ch. 95.11(3)(c) (1995). Schoninger contends that the installation of the membrane on the Kmart roof was not an “improvement to real property.” We reject this argument.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Companion Property & Casualty Group v. Built Tops Building Services, Inc.
218 So. 3d 989 (District Court of Appeal of Florida, 2017)
Simmons v. Rave Motion Pictures Pensacola, L.L.C.
197 So. 3d 644 (District Court of Appeal of Florida, 2016)
Ryan & Jessica Dominguez v. Hayward Industries
201 So. 3d 100 (District Court of Appeal of Florida, 2015)
Donald E. Carlson v. FedEx Ground Package Systems, Inc.
787 F.3d 1313 (Eleventh Circuit, 2015)
Lesti v. Wells Fargo Bank, N.A.
960 F. Supp. 2d 1311 (M.D. Florida, 2013)
Ferrell v. River City Roofing, Inc.
912 So. 2d 448 (Mississippi Supreme Court, 2005)
Garrish v. International Union
417 F.3d 590 (Sixth Circuit, 2005)
Garrish v. UNITED AUTO., AEROSPACE, AND AGRIC.
284 F. Supp. 2d 782 (E.D. Michigan, 2003)
Brandt v. Steel Hector & Davis
213 B.R. 406 (S.D. Florida, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
102 F.3d 1173, 1997 U.S. App. LEXIS 87, 1997 WL 541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bernard-schoninger-shopping-centers-ltd-v-jps-elastomerics-corp-ca11-1997.