Jacobson & Co., Inc. v. Armstrong Cork Co.

433 F. Supp. 1210
CourtDistrict Court, S.D. New York
DecidedMay 9, 1977
Docket76 Civ. 2376
StatusPublished
Cited by3 cases

This text of 433 F. Supp. 1210 (Jacobson & Co., Inc. v. Armstrong Cork Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacobson & Co., Inc. v. Armstrong Cork Co., 433 F. Supp. 1210 (S.D.N.Y. 1977).

Opinion

OPINION, FINDINGS OF FACT AND CONCLUSIONS OF LAW

EDWARD WEINFELD, District Judge.

Jacobson & Company, Inc. (“Jacobson”) brought this action under the antitrust laws seeking damages and an injunction compelling the defendant, Armstrong Cork Company (“Armstrong”), to reinstate it as an authorized distributor of Armstrong products in the New York-New Jersey area. Armstrong is the nation’s leading producer of acoustical ceiling products, including ceiling tile and board. Jacobson is a large “interior” contractor, which specializes in the installation of “integrated ceiling systems.” Such systems are composed of acoustical ceiling board, suspension materials, light fixtures, air distribution components and, occasionally, background noise generators designed to mask floor noises that are reflected off a ceiling. Jacobson was first appointed an authorized Armstrong distributor in March 1968. Essentially, plaintiff’s claim is that Armstrong terminated it as a distributor on March 19, 1916 in furtherance of an effort to impose restrictions on the territories in which and customers to whom authorized distributors could resell Armstrong products. The termination is thus alleged to have violated section 1 of the Sherman Act, 1 which was held by the Supreme Court in United States v. Arnold, Schwinn & Co., 2 to render per se illegal any attempt by a manufacturer “to restrict and confine areas or persons with whom an article may be traded after the manufacturer has parted with dominion over it.” 3

On July 2, 1976, the Court issued a preliminary injunction requiring Armstrong during the pendency of this action to continue selling its products to Jacobson on the same terms and conditions, and with the same concomitant services, as such products are sold to Armstrong’s authorized distributors. 4 Although the Court at that juncture of the litigation questioned whether Jacobson had shown a probability of success on the merits, it nonetheless concluded that preliminary relief was justified, since Jacobson had raised “sufficiently serious questions going to the merits to make them a fair ground for litigation”, and had demonstrated “a balance of hardships tipping decidedly toward [it]”. 5 In the absence of a hearing, which neither side requested, the decision to grant the injunction was made on the basis of affidavits submitted to the Court. 6 The Court then observed that the reasons underlying Jacobson’s termination were in sharp dispute 7 and that the controverted issues deserved more deliberate inquiry than was possible at that time, when the parties had not had full discovery and *1212 when all the pertinent facts had not been fully developed. 8

As the case neared trial, on April 19, 1977, Jacobson moved to punish Armstrong for contempt of court for alleged violations of the preliminary injunction in connection with Jacobson’s bids on construction projects in Columbia, South Carolina, and New Haven, Connecticut. After oral argument and a review of the submissions of the parties, the Court directed that a contempt hearing be consolidated with the trial of plaintiff’s case, since it appeared that Jacobson would seek to introduce evidence relating to the alleged contempt both for the purpose of recovering damages under its complaint and to show Armstrong’s motive and intent in terminating Jacobson as a distributor.

At the start of trial, the Court ruled that Jacobson could not introduce evidence relating to the South Carolina and New Haven projects for the purpose, of recovering damages because the events complained of occurred subsequent to the institution of suit 9 and because no motion to supplement the complaint had been made. 10 Plaintiff’s counsel was then instructed that such evidence would be admitted solely for the purpose of showing Armstrong’s alleged motive and intent in terminating Jacobson. 11 Upon the trial before the jury, evidence concerning the South Carolina project was received for the limited purpose stated above. 12

Although plaintiff in the pretrial order asserted claims for damages only based on Armstrong’s alleged acts in connection with the projects in New Haven and South Carolina, no motion was made during trial to supplement the complaint to include those claims and, by plaintiff’s own admission, no competent evidence of damages on any of its claims was introduced. Accordingly, at the conclusion of plaintiff’s case, the Court granted Armstrong’s motion for a directed verdict on the claim for damages. Because only equitable issues remained in the case, the jury was dismissed and the Court resumed the trial as the trier of fact with respect to plaintiff’s claim for injunctive relief. 13 Upon the continued trial both parties were afforded an opportunity to submit additional evidence on the contempt claims.

The consolidated trial and hearing generated a transcript of testimony totalling over 1,000 pages and extended over six trial days. Sharply contested issues of fact de *1213 veloped with respect to plaintiff’s claim for injunctive relief and its contempt motion.

CLAIM FOR INJUNCTIVE RELIEF

Jacobson seeks to be reinstated as an authorized Armstrong distributor under section 16 of the Clayton Act, which authorizes a private party to sue for injunctive relief “against threatened loss or damage by a violation of the anti-trust laws”. 14 The gravamen of plaintiff’s claim is that Armstrong has violated section 1 of the Sherman Act because its termination of Jacobson was an act in furtherance of an agreement, combination or conspiracy to impose restrictions on the territories within which Jacobson could resell Armstrong products and on the types of customers to which such products could be resold. 15 Specifically, Jacobson asserts that Armstrong attempted to restrain it both from selling Armstrong products in the Philadelphia, Pennsylvania area, where Armstrong had a longstanding relationship with a major approved distributor, and from bidding against local Armstrong contractors or distributors to secure contracts for installation of ceiling systems in government office buildings to be constructed in Atlanta, Georgia and Columbia, South Carolina. In addition, Jacobson contends that Armstrong was opposed to the operation of a “Supply Center” by Jacobson in the Philadelphia area, which wholesaled Armstrong products directly to independent contractors, institutional buyers and other customers who installed such products themselves.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reborn Enterprises, Inc. v. Fine Child, Inc.
590 F. Supp. 1423 (S.D. New York, 1984)
Kolling v. Dow Jones & Co.
137 Cal. App. 3d 709 (California Court of Appeal, 1982)
Morse v. Swank, Inc.
459 F. Supp. 660 (S.D. New York, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
433 F. Supp. 1210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacobson-co-inc-v-armstrong-cork-co-nysd-1977.