Jacksonbay Builders, Inc. v. Azarmi

869 A.2d 580, 2005 R.I. LEXIS 55, 2005 WL 670737
CourtSupreme Court of Rhode Island
DecidedMarch 24, 2005
Docket2004-255-Appeal
StatusPublished
Cited by31 cases

This text of 869 A.2d 580 (Jacksonbay Builders, Inc. v. Azarmi) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacksonbay Builders, Inc. v. Azarmi, 869 A.2d 580, 2005 R.I. LEXIS 55, 2005 WL 670737 (R.I. 2005).

Opinion

OPINION

PER CURIAM.

The failure of pro se litigants to reject an arbitrator’s award within twenty days is the genesis of this appeal. Arguing that he never was informed that he had only twenty days to challenge the award, the defendant, Farhad Azarmi, 1 appeals from a Superior Court judgment in favor of the plaintiff, Jacksonbay Builders, Inc., for $14,163, plus interest and costs.

This case came before the Supreme Court for oral argument pursuant to an order directing the parties to show cause why the issues raised on appeal should not summarily be decided. After hearing the arguments of the litigants and examining the record and the memoranda filed by the parties, we are of the opinion that cause has not been shown, and we affirm the judgment entered in the Superior Court.

Facts and Procedural History

In 1996, Farhad and Lida Azarmi contracted with plaintiff to build a house in North Kingstown. 2 In late June 1997, the Azarmi family moved into this new house. The defendant alleges that at that time there remained numerous problems with the house that plaintiff agreed to correct. The defendant further says that he gave plaintiff a check for $25,000, which he considered payment in full under the contract. On November 25, 1997, however, plaintiff filed a petition to enforce a mechanic’s hen against the Azarmis’ property. The plaintiff alleged that defendants owed $24,993 for labor and materials that plaintiff furnished in constructing the house. Unfortunately, efforts to resolve the dispute through negotiations proved unsuccessful. According to defendant, however, in 1998 Jacksonbay Builders “removed [the] mechanic [sic] hen” upon the payment by defendants of $25,000 into an escrow ae- *582 count accessible only by joint signatures of both parties’ attorneys.

There was no activity on the petition until October 2002, when plaintiff filed a motion to assign the case to the continuous trial calendar. The Azarmis filed a pro se objection and then, through counsel, a motion to dismiss, alleging lack of personal service. The motion to dismiss was heard and denied by a Superior Court justice on December 16,' 2002. Thereafter, the Azar-mis, pro se, filed a second motion to dismiss on the grounds that the mechanic’s lien no longer existed. That motion also was denied.

At a control calendar call on October 2, 2003, the case was “converted to [a] contract case” and referred to court-annexed arbitration. The arbitrator originally selected by the parties asked to be replaced because of a conflict of interest, and James Marusak, Esq., was appointed as the arbitrator. Before the arbitration hearing, the Azarmis filed a counterclaim, and plaintiff filed an amended complaint and an answer to the counterclaim.

An arbitration hearing was held on June 14, 2004, 3 and on June 21, 2004 the arbitrator issued an award. He awarded plaintiff $20,363 on its amended complaint, and awarded the Azarmis $6,200 on their counterclaim. The total award to plaintiff after the set off was $14,163, excluding interest and costs. A copy of the award was mailed to both parties on June 21, 2004, and docketed in the Superior Court file on June 22, 2004.

On July 29, 2004, on a previously scheduled control hearing date, Mr. and Mrs. Azarmi filed an “Objection to arbitration decision” and a motion to assign the matter to the continuous trial calendar. The trial justice explained to them that Rule 5(a) of the Superior Court Rules Governing Arbitration of Civil Actions (Superior Court Arbitration Rules) provides that a dissatisfied party may file a written rejection of the award within twenty days after the award is filed. In addition, he said that Rule 6(b) of the Superior Court Arbitration Rules provides that if no party files a written rejection within twenty days, the court “shall enter judgment” on the award. In overruling the Azarmis’ objection, he ruled that the arbitration award had “ripened into a judgment,” and “the court has little alternative but to confirm the arbitration award.”

The judgment on the arbitrator’s award was entered on July 30, 2004, and execution was issued on August 6, 2004 for $14,163, plus $11,347.47 in interest and $210 in costs, for a total of $25,720.47. The defendant has timely appealed.

Discussion

In his written submission captioned “brief,” defendant reviews the history of his relationship with plaintiff and describes certain problems and defects that allegedly occurred in the construction of the house. In addition, he points out that the letter that he and his wife received from the arbitration office did not explain that they had only twenty days in which to challenge the arbitration award. He contends that they are “victim[s] in this case [who] can’t [afford] to hire [a] lawyer and are not familiar with the law.” His statement further suggests that this is a “very complicated” case that would justify a deviation from the court rules. He also asserts that he placed $25,000 in escrow in 1998 per agreement of the parties, and argues that, if any interest is to be awarded to plaintiff, *583 it should only be the interest accumulated on that sum while it was held in escrow.

The plaintiff responds that defendant is bound by the rules. It asserts that after the twenty-day period in which to reject the award had elapsed, the Azarmis lost the right to challenge the award. Further, plaintiff contends, they failed to show any excusable neglect that might have warranted an enlargement of time for them to reject the arbitrator’s award.

Our task on review is to illuminate the meaning and effect of the applicable court rules. We do so on a de novo basis. “The interpretation of court rules is a question of law,” which we review de novo. Gucfa v. King, 865 A.2d 328, 331 (R.I.2005) (citing Cabral v. Arruda, 556 A.2d 47, 49 (R.I.1989) and Granoff Realty II Limited Partnership v. Rossi, 833 A.2d 354, 361 (R.I.2003)).

Rules Governing Arbitration of Civil Actions

At issue in this case are two of the Superior Court Arbitration Rules. Rule 5(a) provides:

“Trial as of Right. Any party not in default for a reason which may result in judgment by default who is dissatisfied with an arbitrator’s award may have a trial as of right upon filing a written rejection of the award on an approved form within 20 days after the arbitrator’s award has been filed, or within 20 days after an adverse determination of a Rule 3(j) motion to rehear.”

Moreover, Rule 6(b) provides:

“Judgment Entered on Award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Karen A. Oliveira v. Ashley L. Levesque
Supreme Court of Rhode Island, 2023
Arturo P. Batac v. Wells Fargo Home Mortgage
Supreme Court of Rhode Island, 2023
Rahim Caldwell v. Jason Anthony
Supreme Court of Rhode Island, 2022
Gerald Richard v. Steven Robinson
209 A.3d 1198 (Supreme Court of Rhode Island, 2019)
Judith P. BOWMAN v. Julian P. FORGUE
184 A.3d 1130 (Supreme Court of Rhode Island, 2018)
Sean Marchionte v. Francisco Jaramillo
182 A.3d 1146 (Supreme Court of Rhode Island, 2018)
Hakeem Pelumi v. City of Woonsocket
180 A.3d 840 (Supreme Court of Rhode Island, 2018)
Joyce Duffy v. Estate of Bartolomie Scire
111 A.3d 358 (Supreme Court of Rhode Island, 2015)
Timothy Raiche d/b/a T. Raiche Builders v. Timothy W. Scott
101 A.3d 1244 (Supreme Court of Rhode Island, 2014)
Karen McAninch v. State of Rhode Island Department of Labor and Training
64 A.3d 84 (Supreme Court of Rhode Island, 2013)
Rivera v. Rose
14 A.3d 939 (Supreme Court of Rhode Island, 2011)
Boranian v. Richer
983 A.2d 834 (Supreme Court of Rhode Island, 2009)
Works v. Sber Royal Mills, LLC
Superior Court of Rhode Island, 2009

Cite This Page — Counsel Stack

Bluebook (online)
869 A.2d 580, 2005 R.I. LEXIS 55, 2005 WL 670737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacksonbay-builders-inc-v-azarmi-ri-2005.