Reagan Marine Construction, LLC v. Victor Costa

CourtSupreme Court of Rhode Island
DecidedJuly 7, 2026
Docket2024-0344-Appeal.
StatusPublished

This text of Reagan Marine Construction, LLC v. Victor Costa (Reagan Marine Construction, LLC v. Victor Costa) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reagan Marine Construction, LLC v. Victor Costa, (R.I. 2026).

Opinion

Supreme Court

No. 2024-344-Appeal. (PC 22-6418)

Reagan Marine Construction, LLC :

v. :

Victor Costa et al. :

NOTICE: This opinion is subject to formal revision before publication in the Rhode Island Reporter. Readers are requested to notify the Opinion Analyst, Supreme Court of Rhode Island, 250 Benefit Street, Providence, Rhode Island 02903, at Telephone (401) 222-3258 or Email opinionanalyst@courts.ri.gov, of any typographical or other formal errors in order that corrections may be made before the opinion is published. Supreme Court

Present: Suttell, C.J., Robinson, Lynch Prata, Long, and Indeglia (ret.), JJ.

OPINION

Justice Lynch Prata, for the Court. The defendants, Victor Costa and Costa

Companies, Inc., appeal from a default judgment in favor of the plaintiff, Reagan

Marine Construction, LLC, in the amount of $716,001.83, inclusive of costs,

prejudgment interest, and attorney’s fees. On appeal, the defendants argue that the

trial justice erred in entering a default judgment because, according to them, the

plaintiff’s service of motions for conditional order of default, default judgment, and

attorney’s fees were defective. This case came before the Supreme Court pursuant

to an order directing the parties to appear and show cause why the issues raised in

this appeal should not be summarily decided. After considering the parties’ written

and oral submissions and reviewing the record, we conclude that cause has not been

shown and that this case may be decided without further briefing or argument. For

the reasons set forth in this opinion, we affirm the judgment of the Superior Court.

-1- Facts and Travel

The plaintiff, Reagan Marine Construction, LLC (plaintiff or Reagan), was

the general contractor on a construction project (the project) for the expansion of the

Church Street Marina in Bristol, Rhode Island. On November 3, 2021, plaintiff

entered into a subcontract (the subcontract) to have electrical work performed on the

project. Victor Costa (Costa) signed the subcontract as “CEO” of Costa Companies,

Inc. (Costa Companies) (collectively defendants), and, on appeal, it is uncontested

that Costa had the authority to bind Costa Companies to the subcontract. Notably,

under the terms of the subcontract, the parties agreed that time was of the essence

and that Reagan would be provided with timely written notices of delays that could

postpone the project’s completion. The subcontract also included an

indemnification clause that outlined that Costa Companies “shall fully and

completely indemnify [Reagan] * * * from and against all claims, damages, losses

and expenses, including but not limited to attorney’s fees, arising out of, caused by,

or resulting from the performance of the [w]ork associated with this [c]ontract or

other conduct of [Costa Companies] * * *.” Reagan alleges that after execution of

the subcontract, Costa Companies delayed commencement of work on the project.

We are advised that during the summer of 2022—to comply with state

electrical and building code requirements—Reagan and Costa Companies

negotiated to expand the scope of work in the subcontract. Costa Companies

-2- conditioned acceptance of the expanded scope of work on Reagan’s payment of a

twenty percent deposit, which Reagan submits it paid. According to Reagan, Costa

accepted the expanded scope of work and provided Reagan with an estimated

completion schedule.

Reagan avers that in reliance on the terms of the subcontract, it formally

executed a change schedule order with the Town of Bristol on September 8, 2022.

Thereafter, Reagan represented that, Costa Companies neither complied with the

estimated completion schedule for the expanded scope of work nor did defendants

provide Reagan with written notices of delays. As a result, Reagan represented that,

the Town of Bristol threatened to terminate the general contract if Reagan did not

provide a remedy within thirty days. In turn, Reagan advises that it informed

defendants of its intent to terminate the subcontract unless Costa Companies

complied with a modified schedule. Reagan alleges that Costa Companies failed to

timely comply, so it terminated the subcontract and hired a replacement electrical

subcontractor. Consequently, Reagan filed a complaint in Providence County

Superior Court alleging counts of breach of contract, negligent misrepresentation,

and fraud against Costa Companies; a count of fraud against Costa; and a count of

conversion against defendants. Reagan sought damages, and attorney’s fees

-3- pursuant to G.L. 1956 § 9-1-45. In response, defendants filed an answer, denied

certain allegations in Reagan’s complaint, and asserted six affirmative defenses.1

Reagan served defendants with a request for production of documents. An

order directing defendants to comply with the production was entered on March 10,

2023. Thereafter, Reagan moved to compel production of answers to certain

interrogatories and additional documents, to which defendants timely objected. At

the hearing on the motion, counsel appeared on behalf of defendants and asserted

that, with respect to defendants’ production issue, “a collection of e-mails * * * had

subsequently been rectified and produced to the [p]laintiff * * *.” Counsel conceded

that “[t]here [were] other issues with respect to the interrogatories[,]” and he stated

that he could not “go into any further detail regarding those specific requests” due

to his pending motion to withdraw. On July 3, 2023, the trial justice entered separate

orders granting defense counsel’s motion to withdraw and granting Reagan’s motion

to compel. The trial justice, however, stayed discovery for twenty days, effectively

affording defendants the opportunity to retain new counsel. Subsequently, on

October 18, 2023, the trial justice entered an order, giving Costa an additional thirty

days to comply with the July 3, 2023 order and granting Costa Companies thirty

1 The affirmative defenses pled by defendants were: (1) failure to state a claim upon which relief may be granted; (2) failure to state a cause of action upon which relief may be granted; (3) improper subject matter jurisdiction; (4) frustration of purpose; (5) the doctrine of laches; and (6) the parties failed to reach an agreement on terms.

-4- days to procure new counsel. According to Reagan, defendants did not comply with

the court’s order to produce discovery and did not retain new counsel.

Consequently, Reagan moved for a conditional order of default against

defendants and requested an award of attorney’s fees. In its motion, Reagan asserted

that defendants “[willfully violated] multiple [c]ourt [o]rders compelling the

production of sufficient discovery responses and requiring the corporate [d]efendant,

Costa Companies, Inc., to retain counsel * * *.” A hearing on the motion was held,

at which defendants did not appear. The trial justice informed Reagan’s counsel that

the court received a letter from a medical provider that morning indicating that, due

to a medical condition, Costa was unable to return to work until March 25, 2024.

The trial justice continued with the proceeding, reasoning that defendants did not

file an objection to the motion. The trial justice granted Reagan’s motion and entered

a conditional order of default on March 28, 2024. The order afforded defendants

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Charles Pona
66 A.3d 454 (Supreme Court of Rhode Island, 2013)
Victoria Rodriguez v. John Virgilio
58 A.3d 914 (Supreme Court of Rhode Island, 2012)
Providence Gas Company v. Biltmore Hotel Operating Co.
376 A.2d 334 (Supreme Court of Rhode Island, 1977)
Jacksonbay Builders, Inc. v. Azarmi
869 A.2d 580 (Supreme Court of Rhode Island, 2005)
Reyes v. Providence Place Group, L.L.C.
853 A.2d 1242 (Supreme Court of Rhode Island, 2004)
Clark v. Dubuc
486 A.2d 603 (Supreme Court of Rhode Island, 1985)
Sean Marchionte v. Francisco Jaramillo
182 A.3d 1146 (Supreme Court of Rhode Island, 2018)
Daryl Heneault v. Kenneth Lantini
213 A.3d 410 (Supreme Court of Rhode Island, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Reagan Marine Construction, LLC v. Victor Costa, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reagan-marine-construction-llc-v-victor-costa-ri-2026.