J.A. Moore Construction Co. v. Sussex Associates Ltd. Partnership

688 F. Supp. 982, 1988 U.S. Dist. LEXIS 5844
CourtDistrict Court, D. Delaware
DecidedJune 21, 1988
DocketCiv. A. 86-498-JRR, 86-499-JRR and 87-82-JRR
StatusPublished
Cited by18 cases

This text of 688 F. Supp. 982 (J.A. Moore Construction Co. v. Sussex Associates Ltd. Partnership) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.A. Moore Construction Co. v. Sussex Associates Ltd. Partnership, 688 F. Supp. 982, 1988 U.S. Dist. LEXIS 5844 (D. Del. 1988).

Opinion

OPINION

ROTH, District Judge.

Before the Court are motions by defendants in three cases which involve disputes arising from the construction of the Rehoboth Mall in Sussex County, Delaware. Plaintiff in all three cases is J.A. Moore Construction Company (“Moore”), which was general contractor for construction of the Mall. Moore has brought two actions, now consolidated, based on breach of contract, quantum meruit and fraud, 1 and one action pursuant to the Racketeer Influenced and Corrupt Organizations Act (“RICO”), 18 U.S.C. § 1961 et seq. Defendants in all three actions are Richard M. Singer (“Singer”), the project’s promoter; R.M. Singer & Associates, Inc. (“Associates”), the developer; Rehoboth Mall Limited Partnership (“Rehoboth LP”), leaseholder and operator of a major portion of the Mall; Sussex Associates Limited Partnership (“Sussex LP”), leaseholder and operator of that portion of the Mall occupied by the Peebles Department Store; Patrick J. B. Donnelly, John G. Wharton, and Andrew N. Lutyk, limited partners in Rehoboth LP and Sussex LP; Peter Nierenberg, limited partner in Sussex LP; and William R. Russell, general partner of Sussex LP and a limited partner in Sussex LP and Rehoboth LP. Defendant Singer is general partner of Rehoboth LP and president of Associates. Defendants have moved for summary judgment on the contract, quantum meruit and fraud claims and for dismissal of the RICO claims. Because matters outside the complaint are considered in the motion to dismiss the RICO claim, we will consider it also to be a motion for summary judgment. For the reasons set forth below, we will grant in part and deny in part defendants’ motions with respect to the contract and fraud claims. We will grant defendants’ motions on the quantum meruit and RICO claims.

I. FACTS.

A. Rehoboth Mall Project.

Most of the negotiations for the general contract to build Rehoboth Mall took place between Richard Singer and Randy Radish, Assistant Secretary of the J.A. Moore Company. Plaintiff claims that, unknown to Radish, defendants were confronted with *985 difficulties in setting up financing for the Mall. Defendants intended to finance the project with Internal Revenue Code § 103(b)(6)(D) industrial development bonds to be issued by Sussex County. Under the Tax Code, in order for the interest from such bonds to be free from federal income tax, capital expenditures on the project financed by the bonds could not exceed $10,-000,000. To meet this limitation, defendants divided the Mall into two projects with two limited partnerships. One partnership, Rehoboth LP, constructed the major part of the Mall and was financed by the industrial development bonds. The second partnership, Sussex LP, backed by conventional financing, constructed the Peebles Department Store, located in the Mall.

To finance the Rehoboth LP portion of the Mall, Sussex County issued a $7,770,-000 Economic Development Revenue Bond on December 28, 1984. The Bank of New York is the only holder of the bond and enjoys certain protections in the event that the bond looses its tax-favored status. Should the $10,000,000 capital expenditure limitation be exceeded and the interest on the bond no longer be excluded from gross income for federal income tax purposes, the interest which Rehoboth LP pays to the Bank of New York would increase as of that time from 75 percent of the Bank of New York’s Prime Rate up to the Bank of New York’s Prime Rate plus 1 percent, that being the same interest rate which Sussex LP currently pays to the Bank of New York on the money borrowed for the construction of the Peebles Department Store.

Singer asked Radish to sign written contracts and allegedly assured him that the construction contracts were required solely for the purpose of obtaining the bond financing before the end of 1984. On November 26, 1984, both partnerships executed stipulated sum contracts with plaintiff to construct the project. 2 Randy Radish signed for plaintiff. The contracts were reexecuted in substantially the same form by Ronald Moore, president of the J.A. Moore Company, on April 1, 1985, at the request of his bonding company. Plaintiff claims that defendants knew the contracts provided inadequate compensation. In fact, some of plaintiff’s cost estimates exceeded the stipulated sums in the contracts and parts of the project, such as the waste water treatment plant and the entrances from the highway, had not yet been designed. Singer allegedly promised Radish that defendants would pay the difference between the contract stated price for on-site costs, off-site costs and contingencies and the actual trade subcontractors’ prices, plus any direct costs for work performed by Moore’s own forces. Moreover, contracts contained provisions for Change Orders to cover additional costs. However, any such changes had to be approved in writing by Rehoboth LP or Sussex LP.

During the course of construction, plaintiff obtained interim payments pursuant to the terms and procedures specified in the contracts. Plaintiff claims that in so doing, it was not vouching for the validity of the contracts but rather was merely following Singer’s instructions to preserve the appearance for financing purposes that the contracts were being followed. Defendants cultivated such an appearance, contends plaintiff, to insure defendants’ tax-favored financing of the Rehoboth LP portion of the Mall.

Following the execution of the contracts, construction of the Mall was held up until May, 1985, due to zoning problems. Some preliminary work, however, was completed by Moore during the interval, including excavation and ground fill. On May 28, 1985, Moore made an application to Rehoboth LP for payment for work performed to that date. Included in the application was Change Order No. 1, adding the amount of *986 $8,442.00 for removing and replacing unsuitable fill material.

Plaintiff contends that Singer at this point instructed Radish that under no condition was Moore to submit any more Change Orders. Singer purportedly gave this command because he was afraid further Change Orders would push the capital expenditures over the $10,000,000 limit. Plaintiff asserts that its employees were directed by Singer to ignore the contract provisions requiring written approval of any changes. Also, plaintiff claims that it was instructed to bill key tenants of the Mall directly for any additional costs and was promised that the parties would “settle up” any further amounts owing to Moore at the end of the job. Apparently, underestimates, changes in design and completion of additional parts of the overall plan then resulted in plaintiff paying costs beyond the contract figures.

As the project neared completion in the spring of 1986, Moore submitted to the partnerships a large number of requests for payment for changes. On May 9, 1986, defendant Wharton wrote to Ronald Moore, stating that no payment would be made for contract extras unless the written change order procedure had been followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kanno v. Marwit Capital Partners II
California Court of Appeal, 2017
Kanno v. Marwit Capital Partners II, L.P.
227 Cal. Rptr. 3d 334 (California Court of Appeals, 5th District, 2017)
Realty Finance Holdings, LLC v. KS Shiraz Manager, LLC
18 N.E.3d 350 (Massachusetts Appeals Court, 2014)
J.C. Trading Ltd. v. Wal-Mart Stores, Inc.
947 F. Supp. 2d 449 (D. Delaware, 2013)
Guidance Endodontics, LLC v. Dentsply International, Inc.
708 F. Supp. 2d 1209 (D. New Mexico, 2010)
Rosenthal v. Sonnenschein Nath & Rosenthal, LLP
985 A.2d 443 (District of Columbia Court of Appeals, 2009)
Aventis Environmental Science USA LP v. Scotts Co.
383 F. Supp. 2d 488 (S.D. New York, 2005)
Great Lakes Chemical Corp. v. Pharmacia Corp.
788 A.2d 544 (Court of Chancery of Delaware, 2001)
Vision Graphics, Inc. v. E.I. Du Pont De Nemours & Co.
41 F. Supp. 2d 93 (D. Massachusetts, 1999)
Eisele v. Rice
948 P.2d 1360 (Wyoming Supreme Court, 1997)
Middletown Concrete Products, Inc. v. Black Clawson Co.
802 F. Supp. 1135 (D. Delaware, 1992)
Southmark Prime Plus, L.P. v. Falzone
776 F. Supp. 888 (D. Delaware, 1991)
Schiffer v. Sherwood
936 F.2d 579 (Ninth Circuit, 1991)
Fiorentino v. Converse
705 F. Supp. 253 (E.D. Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
688 F. Supp. 982, 1988 U.S. Dist. LEXIS 5844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ja-moore-construction-co-v-sussex-associates-ltd-partnership-ded-1988.