J. A. Kreis & Co. v. City of Knoxville

145 Tenn. 297
CourtTennessee Supreme Court
DecidedSeptember 15, 1921
StatusPublished
Cited by13 cases

This text of 145 Tenn. 297 (J. A. Kreis & Co. v. City of Knoxville) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Kreis & Co. v. City of Knoxville, 145 Tenn. 297 (Tenn. 1921).

Opinion

Mr. Justice Hall

delivered the opinion of the Court.

On April 12, 1917, the city of Knoxville (a municipal corporation) contracted in writing with the complainants to construct or build for it a pump pit in which to install a pump and engine for use in connection with the city’s waterworks system according to certain plans and specifications which had been prepared by its engineer prior to letting the contract, for a specified sum.

[299]*299Complainants entered npon a performance of the contract, and after they had proceeded for some time with the work it was found that the pit, as originally planned, would not he sufficient to accommodate the pump and engine which the city had purchased and desired to install. It, therefore, became necessary to enlarge the pit and complainants, by the verbal authority and direction of the city’s commissioner of waterworks, and with assurance from said commissioner of waterworks that they would be paid for the additional and extra work necessary to enlarge the pit to the dimensions required, did additional or extra work in the construction of said pit of the value of $6,377.94, to collect which the present bill was filed by complainants.

The city demurred to the bill upon a number of grounds. Its demurrer was overruled, after which it answered, setting up a number of grounds of defense. One of the grounds of defense was that the contract for this additional or extra work was not made in writing, and that complainants, therefore, could not recover for the same. It is unnecessary to set out the other defenses made by the city in its answer.

The cause was heard by the chancellor upon the pleadings, exhibits thereto, and certain proof taken by the complainants. The defendant offered no proof whatsoever.

The chancellor rendered a decree against the city and in favor of the complainants for $5,761.51, which sum he found the city had obligated itself to pay under a compromise agreement entered into by it with the complainants on September 9, 1919. From this decree the city has appealed to this court, and has assigned the action of the chancellor for error.

[300]*300There is no dispute as to the facts. The undisputed proof shows that complainants did this additional work on the pump pit with the verbal assurance of the city’s commissioner of waterworks that the same would he paid for by the city, and that this additional work cost complainants $0,377.94 more than the city had paid them; that on September 9, 1919, after the present bill had been filed, the commissioners of the city of Knoxville, in regular meeting, ordered a compromise of complainants’ claim against the city on account of said additional work, agreeing to pay complainants the sum of $5,761.51. The following entry appears on the minutes of the city commission;

“J. W. Culton appeared before the commission in regard to the compromising of the suit of J. A. Kreis & Company, now pending in the chancery court, for amounts due on completing the pumping station. On motion of Commissioner Crumbliss, Commissioner Hill voting No, the suit was ordered compromised for $5,761.51, Kreis paying all court courts.”

Before this compromise agreement was executed, the board of commissioners, Avho entered into said agreement, went out of office and were succeeded by the present board of commissioners of the city of Knoxville, who, by resolution, undertook to rescind the action of the old board of commissioners in compromising the claim of complainants, and, payment of said claim in accordance with said compromise agreement being refused by the present commissioners, the present bill was filed, as befoi'e stated.

The original contract for the building of said pump pit contains the following provisions:

“Contractor agrees that the commissioners of water-Avorks shall have the right, when in their opinion it be[301]*301comes necessary in the prosecution of the work, to make alterations or modifications in this contract, whereby the character as well as the quantities may be changed; but such alterations or modifications shall only be made by order of the commissioners of waterworks, and such order shall not go into effect until the price or prices to be paid for the work or materials under such altered or modified contract has been agreed upon in writing and signed by the contractor and the commissioners of waterworks; and said contractor shall not be allowed to recover anything for work or materials caused by any alterations or modifications in this contract, unless an order is made and agreement signed as aforesaid; nor shall said contractor in any case be allowed to recover more for such work and materials than said agreed price or prices; provided, that this condition shall not apply to any item for which a price has been written in the proposal.”

Section 46 of the charter of the city of Knoxville (chapter 207, Acts of 1907) provides as follows:

“Be it further enacted, that when, in the opinion of the board of public works, it shall become necessary in the prosecution of any work to make alterations or modifications in the specification or plans of a contract, such alterations or modifications shall be of no effect until the price to be paid for same shall have been agreed upon in writing and signed by the contractor and approved by the board. The total cost of the work, with the addition of the price so agreed upon, shall not exceed the original estimate.”

Section 47 provides as follows: “Be it further enacted, that no contractor shall be allowed anything for extra work caused by an alteration or modification, unless an [302]*302order is made or an agreement signed as provided in the preceding section, nor shall he in any case he allowed more for such alteration than the price fixed by such agreement.”

It will he noted that the first section above quoted provides that contracts for extra or additional work, resulting from alerationg or modifications in the plans or specifications of a contract, shall not go into effect until the price to be paid for same shall have been agreed upon in writing and signed by the contractor and approved by the board.

The second section above quoted expressly provides that no contractor shall be allowed anything for extra work caused by an alteration or modification of the plans or specifications, unless an order is made and the agreement signed as provided in the preceding section.

It cannot be controverted, therefore, that the contract upon which complainants seek to recover for the extra or additional work done on the pump pit specified in the original contract was expressly prohibited by these provisions of the city’s charter. In other words, the contract for this extra work, being in direct violation of the express provisions of the city’s charter, was void under the holding of this court in Watterson v. City of Nashville, 106 Tenn., 410, 61 S. W., 782.

In that case Mr. Watterson had made a written contract with the board of public works of the city of Nashville to do the carpentry work on its new city hall, and while engaged in the work he was ordered to make certain changes not intended in the original plan, which involved the use of more costly material, said excess cost being $2,-500. Upon receiving this order he gave written notice [303]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Earl M. Shahan v. Franklin County
Court of Appeals of Tennessee, 2003
Town of Morrison v. Warren County, Tennessee
Court of Appeals of Tennessee, 2001
City of Lebanon v. Baird
756 S.W.2d 236 (Tennessee Supreme Court, 1988)
State Ex Rel. Henderson County v. Stewart
326 S.W.2d 688 (Court of Appeals of Tennessee, 1959)
Hamilton National Bank v. Richardson
304 S.W.2d 504 (Court of Appeals of Tennessee, 1957)
Hudson City Contracting Co. v. Jersey City Incinerator Authority
111 A.2d 385 (Supreme Court of New Jersey, 1955)
Carter County v. Williams, No. 1
190 S.W.2d 311 (Court of Appeals of Tennessee, 1945)
Johnson City v. Carnegie Realty Co.
64 S.W.2d 507 (Tennessee Supreme Court, 1933)
Trotter v. Peterson
60 S.W.2d 149 (Tennessee Supreme Court, 1933)
Boshears v. Foster
290 S.W. 387 (Tennessee Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
145 Tenn. 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-kreis-co-v-city-of-knoxville-tenn-1921.