Harakas Construction, Inc. v. Metropolitan Government Of Nashville and Davidson County

561 S.W.3d 910
CourtCourt of Appeals of Tennessee
DecidedJanuary 29, 2018
DocketM2016-01540-COA-R3-CV
StatusPublished
Cited by2 cases

This text of 561 S.W.3d 910 (Harakas Construction, Inc. v. Metropolitan Government Of Nashville and Davidson County) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harakas Construction, Inc. v. Metropolitan Government Of Nashville and Davidson County, 561 S.W.3d 910 (Tenn. Ct. App. 2018).

Opinion

01/29/2018 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 23, 2017 Session

HARAKAS CONSTRUCTION, INC. v. METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY, ET AL.

Appeal from the Chancery Court for Davidson County No. 13-576-IV Russell T. Perkins, Chancellor

No. M2016-01540-COA-R3-CV

Harakas Construction, Inc. appeals the judgment of the Chancery Court for Davidson County (“the Trial Court”) granting summary judgment to Metropolitan Government of Nashville and Davidson County (“Metro”) and Dale and Associates, Inc. (“Dale”). We find and hold that the Trial Court correctly granted summary judgment to Metro based upon sovereign immunity and that the Trial Court correctly granted summary judgment to Dale because Dale had negated essential elements of Harakas’s claim.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed Case Remanded

D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which FRANK G. CLEMENT, JR., P.J., M.S., and JOHN W. MCCLARTY, J., joined.

J. Brad Scarbrough and Chris Holleman, Brentwood, Tennessee, for the appellant, Harakas Construction, Inc.

Jon Cooper and J. Brooks Fox, Nashville, Tennessee, for the appellee, Metropolitan Government of Nashville and Davidson County.

David N. Garst, J. Wallace Irvin, and Brian S. Faughnan, Nashville, Tennessee, for the appellee, Dale and Associates, Inc. OPINION

Background

In 2007, BK Partners, LLC (“BK Partners”) owned undeveloped real property located in Davidson County, Tennessee (“the Property”) upon which it planned to construct a high-rise condominium. In order for the Property to be developed, the existing public sewer service had to be upgraded. The sewer system that services the Property also services an area known as the Holiday Travel Park area. In August of 2007, BK Partners submitted an application to upgrade the public sanitary sewer to Metro Water, the department of Metro which manages the water and sewer services in Davidson County, Tennessee. The application was approved.

BK Partners and Metro entered in to a Participation Agreement wherein Metro agreed to fund $200,000 toward the cost of the sewer improvement. Pursuant to Metro’s policies, BK Partners was responsible for paying capacity fees based upon the anticipated impact that the new development would have on the existing sewer system. The capacity fees for the development of the Property were approximately $275,000. Subject to the passage of an authorizing ordinance, Metro agreed to waive $200,000 of the capacity fees since BK Partners was funding a portion of the sewer improvement costs, and BK Partners was to pay the balance. Metro also waived the requirement for BK Partners to post a payment and performance bond as security for the project.

In December of 2007, a Metro ordinance was approved which authorized Metro to pay an amount not to exceed $200,000 toward the sewer improvements being made by BK Partners. The ordinance, Ordinance No. BL2007-67, provided, in pertinent part:

An ordinance authorizing the Metropolitan Government to participate with BK Partners to provide public sewer service in Davidson County to Pennington Towers Outfall-Holiday Travel Park Sewage Pumping Station Removal, Project No. 07-SL-113.

WHEREAS, Pursuant to the document attached as Exhibit A and incorporated into this ordinance by reference, BK Partners proposes to provide public sewer service in Davidson County to a development known as Pennington Towers Outfall-Holiday Travel Park Sewage Pumping Station Removal, Project No. 07-SL-113, Map 62.1, Parcels 17 & 22; and

WHEREAS, the Metropolitan Government, Department of Water and Sewerage Services, has built the Mill Creek Trunk Sewer Project No. 98-

2 SG-13 anticipating participation from developers at $2,000.00 per connection towards the cost of the Project; and

WHEREAS, this Project is deemed to benefit both parties and the general community, and the Metropolitan Government agrees to pay an amount not to exceed $200,000.00 towards construction of the Project.

The Participation Agreement For Sewer Services incorporated into Ordinance No. BL2007-67 by reference provided, in pertinent part:

The project consists of removal of the existing pump station and replacement with approximately 5,100 linear feet of gravity sewer to the existing gravity sewer line Project No. 07-SL-0113, complete with all necessary easements and appurtenances.

***

METRO agrees to participate in the construction costs for a portion of this project in the lessor amount of $200,000 or 50% of the actual construction cost as determined by the contractor’s affidavit . . . . Actual payment may be in the form of capacity fee credits or cash. All cash payments will be made upon completion of the work and deeding to METRO.

BK will be responsible for all other costs associated with this project.

BK Partners hired Dale to prepare plans for the sewer improvements, which consisted of installing approximately 5,000 linear feet of sewer pipe on adjacent land and removing an existing pump station (“the Project”). The Project was delayed for a time due to economic factors.

In January of 2012, BK Partners entered into a contract (“the Service Agreement”) with Harakas Construction, Inc. (“Harakas”) for work on the Project. Metro was not a party to the Service Agreement and had no input into the hiring of Harakas or the terms of the Service Agreement. The Service Agreement called for Harakas to install sewer pipe and remove the pump station. Work on the Project began in March of 2012. During construction, Harakas encountered unforeseen soil conditions, and Harakas and BK Partners agreed to two change orders, which increased the amount of the Service Agreement. Metro was involved in discussions regarding the unforeseen conditions and the change orders.

3 Harakas performed the extra work and mostly completed the Project on June 21, 2012, with the exception of reconstruction of a fence. On that date, Harakas tied the new sewer system into the existing sewer system, and Metro began using the new sewer system. Around this same time period it was discovered that the new sewer system was not the proper elevation because it was too high to connect sewer outfall from adjacent property owned by Kampgrounds of America (“KOA”). Due to the elevation, the sewer system required a pump station to connect KOA’s outfall and could not be a gravity fed system as originally designed. Because of the issue with the KOA line, Metro refused to fund any more of the Project. Metro, however, continued to use the sewer system.

BK Partners defaulted on its obligation to pay Harakas both the original balance pursuant to the Service Agreement and the change order balance. Allegedly, BK Partners owed Harakas over $235,000. BK Partners also defaulted on repayment of its loan to Wilson Bank & Trust, and the Property was sold at foreclosure in 2013. Wilson Bank & Trust purchased the Property at the foreclosure sale. The Property later was dedicated to parks and conveyed to Metro.

Harakas sued Metro, BK Partners, and Wilson Bank & Trust1. Harakas later was granted leave to amend its complaint to add claims for negligence and negligent misrepresentation against Dale. In September of 2014, Dale filed a Suggestion of Bankruptcy alleging that BK Partners had filed a petition for bankruptcy. Dale also filed a motion for stay pending the outcome of the bankruptcy. An order was entered staying the instant case pending the outcome of the bankruptcy. In January of 2015, Harakas filed a notice of filing an order from the bankruptcy court granting relief from the automatic stay. In July of 2016, Harakas filed a Notice of Voluntary Nonsuit taking a nonsuit against BK Partners in the instant case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
561 S.W.3d 910, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harakas-construction-inc-v-metropolitan-government-of-nashville-and-tennctapp-2018.