City of Detroit v. Michigan Paving Co.

36 Mich. 335, 1877 Mich. LEXIS 144
CourtMichigan Supreme Court
DecidedApril 24, 1877
StatusPublished
Cited by17 cases

This text of 36 Mich. 335 (City of Detroit v. Michigan Paving Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Detroit v. Michigan Paving Co., 36 Mich. 335, 1877 Mich. LEXIS 144 (Mich. 1877).

Opinion

Campbell, J:

The provisions in the charter of Detroit forbidding the execution of public works, except under contract with the lowest bidder, were intended to prevent any action whatever, whereby contractors could make private arrangements with the council for payment for work done or to be done in such cases. If the letting of a contract is only required as a preliminary form, and if, as soon as it is broken, the council and the contractors may make any arrangement they choose in regard to payment for work done, it is evident that there will be yery little safety against such mischief as was meant to be guarded against. No suit can be brought until the council has been given an opportunity to settle without suit, and if there is power to settle at all, the power is plenary. The question is not whether frauds are likely or not. The legislature has seen fit to provide against arrangements not open to competition, by requiring all contracts to be let* impartially, and it is for bidders to determine the risks themselves.

There is no difficulty in bringing actions for quantum meruit against corporations any more than against individuals, so far as they are not guarded by charter against them. Where the city has had money or property belonging to others, it may doubtless be compelled to answer; but the law has not left this corporation to enter into contracts generally, or without restrictions never imposed on private parties. Individuals are held liable outside the terms of a contract which has been broken, for work done for their benefit, because a contract is implied, and because they are capable of entering upon implied contracts as far as they choose without resorting to express and formal agreements.

But this city has no such power in regard to' public im[340]*340provements. Its contracts must not only be express, but conformed to certain conditions and let under certain supervision. Work done in paving a street, or the like, without any contract, would not in any case be a charge against the city under the law. And work partially done under a broken contract, which cannot as a written contract be enforced by suit, stands as. if there were no contract, so far as any action is concerned. Unless the contract itself provides some remedy in such a case, the case seems to be without remedy.

The city has no power to prevent such difficulties, and is not responsible for them. If contractors tear up a street and fail to pave it properly, or to complete their work, as they have agreed, they have not put the city in the wrong for not paying them. The corporation would be guilty of misconduct in making express contracts for bad work, or for work intended to be left unfinished. It is impossible to tell what contracts they might have obtained if bids were received on such offers. If liable at all when the work is left undone, the liability arises at once, aud without reference to any future contract they may be enabled to make for the completion according to the original plan. There is no possible standard for determining the amount,' unless by disregarding the chartered conditions.

The doctrine of implied assumpsit in favor of a defaulting contractor is comparatively modern; and while it is generally equitable, it is in some cases very unjust, as a person is sometimes compelled to put up with such work as he would not have been willing to accept on any terms, because it has some pecuniary value, and cannot well be undone or removed from his land. It is a very easy matter for any contractor to make such terms as will entitle him to installments of compensation as his work progresses, and to make special terms for all accidents and innocent failures. It is a very difficult thing for a public corporation to watch over its contractors and their doings, as a private party would; and for this reason it needs special [341]*341safeguards. The charter is intended to provide these, and it has done so.

The city could not be expected or required to detach from the freehold the worlc not paid for, even if it could be identified, which would be impossible, inasmuch as it was an undistinguishable proportion of an entire job. The material not incorporated in the pavement, stands on a different footing. It did not belong to the city, and its proceeds, therefore, were not properly receivable or retainable. For these there is a liability arising out of a wrong, and not out of contract; and the form of the remedy in assumpsit, waiving the tort, does not prevent the maintenance of the action based on the facts.

The judgment should be reversed, with costs, and a new trial awarded.

Marston and Graves, JJ., concurred.

Cooley, Ch. J:

This action is brought to recover the value of labor done and materials made use of in the grading and paving of a portion of St. Antoine street in the city of Detroit. The work was begun by the defendant in error under a contract with the city, bearing date June. 23, 1874, by the terms of which the work was to be completed on or before the 15th day of September, 1874. The clause in the contract regarding compensation is as follows: “And it is further mutually agreed that the common council will cause a special assessment to be levied upon all lands or lots fronting or abutting upon said St. Antoine street, lying between Adams avenue and Division street, in consideration of the materials to be furnished and the labor to be performed, by said parties of the second part; and it is further agreed by the said party of ' the first part that party of the first part will pay over to said parties of the second part the avails of all special assessments levied and collected on lands liable by law, which shall be paid [342]*342into the treasury of said city for or on account of such special assessments: Provided, That the party of the first part shall have the option to pay to said parties of the second part any portion, not1 to exceed three-quarters of the contract price of said work and materials, in street paving bonds, in accordance with the charter and ordinances, in lieu of such assessments or moneys to be collected therefrom. But the said city of Detroit, party of the first part, shall not be liable for any part or portion of said special assessments until the same shall have been actually paid into the treasury of the said city.”

The bill of exceptions recites that evidence was introduced “showing that the plaintiff proceeded to perform said contract and finished a portion thereof, which was accepted and paid for; that the plaintiff also did certain grading, set curbstones and furnished a quantity of sand, all of which was of the value to the defendant of sixteen hundred thirty-eight and sixty-five one-hundredths dollars, said amount not exceeding the contract prices; that it was impossible for the plaintiff to fully perform said contract by the fifteenth of September, 1874, the time limited therefor, and the same was not performed on that day; that thereupon the board of public works of said defendant, with the direction of the common council, given on the evening of that day, declared said contract forfeited by the plaintiff, the party of the second part thereto.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. A. Kreis & Co. v. City of Knoxville
145 Tenn. 297 (Tennessee Supreme Court, 1921)
Snouffer v. City of Tipton
161 Iowa 223 (Supreme Court of Iowa, 1913)
Miller v. Jackson Township
99 N.E. 102 (Indiana Supreme Court, 1912)
McCurdy v. County of Shiawassee
118 N.W. 625 (Michigan Supreme Court, 1908)
City of Auburn v. State ex rel. First National Bank
83 N.E. 997 (Indiana Supreme Court, 1908)
Cass County v. Gibson
107 F. 363 (Sixth Circuit, 1901)
Coit v. City of Grand Rapids
73 N.W. 811 (Michigan Supreme Court, 1898)
Affeld v. City of Detroit
71 N.W. 151 (Michigan Supreme Court, 1897)
Campau v. City of Detroit
64 N.W. 336 (Michigan Supreme Court, 1895)
A., T. S. F. Rld. Co. v. Johnson
1895 OK 58 (Supreme Court of Oklahoma, 1895)
Atchison, Topeka & Santa Fe Railroad v. Johnson
3 Okla. 41 (Supreme Court of Oklahoma, 1895)
Eberstein v. Willets
24 N.E. 967 (Illinois Supreme Court, 1890)
Mackey v. Township of Columbus
38 N.W. 899 (Michigan Supreme Court, 1888)
Niles Water Works v. Mayor of Niles
26 N.W. 525 (Michigan Supreme Court, 1886)
City of Detroit v. Robinson
38 Mich. 108 (Michigan Supreme Court, 1878)

Cite This Page — Counsel Stack

Bluebook (online)
36 Mich. 335, 1877 Mich. LEXIS 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-detroit-v-michigan-paving-co-mich-1877.