Ittner v. Hughes

34 S.W. 1110, 133 Mo. 679, 1896 Mo. LEXIS 163
CourtSupreme Court of Missouri
DecidedMarch 31, 1896
StatusPublished
Cited by39 cases

This text of 34 S.W. 1110 (Ittner v. Hughes) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ittner v. Hughes, 34 S.W. 1110, 133 Mo. 679, 1896 Mo. LEXIS 163 (Mo. 1896).

Opinion

Barclay, J.

This action was begun, May 3, 1893, to enforce a mechanics’ lien against certain land in the city of St. Louis, and to obtain judgment against the chief contractor for the work for which the lien is claimed. At the trial á verdict for defendant, the landowner, was returned on the issue of the lien.

Plaintiff moved for a new trial, which the learned trial judge granted. The defendant, in whose favor the verdict had been given, appealed, in the usual way.

» The plaintiff sues as assignee of an account in favor of the Delaney brothers who were subcontractors [684]*684for work upon a large building owned by tbe Blackmer & Post Pipe company, one of defendants. The principal contractor was Mr. Hughes (the other defendant) with whom Delaney brothers dealt in reference to their work, according to the petition. That pleading presents an account and allegations to show an indebtedness of Hughes'for various items of work and labor. The account is as follows:

“All materials furnished and work done between the 20th day of August, 1892, and the 1st day of March, 1893, the last work having been done on March 1st, 1893.
54 perch rubble stoae work at $4......................... $ 216.00
8 yards dimension stone at $8 ............................ 64.00
12 yards concrete at $8.................................... 96.00
Excavation for piers and boiler house walls ................. 24.00
Removing, raising and lowering 18 window and door frames, extra.............................................. 200.00
1,089,362 brick laid on wall at $11.73 per M................ 12,800.00
$ 13,400.00
Credit by cash....................................... 9,385.89
Balance due......................................... $ 4,014.11
“All of which work was done and materials furnished between August 20th, 1892, and March 1st, 1893, the last thereof having.been done March 1st, 1893, when said account accrued. That all of said work and materials went into the construction of said building.”

The petition then avers the taking of necessary steps for a lien, including a notice, April 22, 1893, to the Pipe company of intention to file the lien. The lien account was filed, May 3, 1893; and the assignment by Delaney brothers to plaintiff is alleged as of that date, “after having filed said lien.” Judgment for $4,014.11 with interest was demanded.

The petition is not challenged except at certain [685]*685points. As to them, the foregoing outline will be found sufficient.

The amended answer denied the petition generally, and also set up the fact that Delaney brothers had absolutely assigned their account to plaintiff long before the filing of their lien; and that they were consequently not entitled to a lien when the same was filed.

Defendant Hughes made no answer.

The reply denied the new' matter alleged by the Pipe company.

When the case came to trial (a jury having been called) plaintiff read in evidence the notice of lien without objection. When the lien was offered, objections were made which the court overruled. The substance of the objections is that the credits are lumped in a single item; that the items of work are not sufficiently stated; that the date of the last work is not clearly given; and that no application of the credits appears to have been made to any'particular part of the general account stated in the petition.

The lien statement of account was identical with that of the petition above quoted; but it had an appropriate caption showing Hughes as contractor, the Pipe company as owner and Delaney brothers as subcontractors, claimants.

In the early stages of the trial, plaintiff withdrew the claim for a lien for the stone work, excavation and extras, and asked solely for a lien for the brick work. He took this course after the testimony had developed the facts that the original written contract between the Delaney brothers and Hughes did not include clearly these items, though the work and materials represented by them had been in fact done and furnished by the Delaney brothers, but not as subcontractors. Those items of work and material were furnished (so plaintiff considered) under a distinct contract with the Pipe [686]*686company; but there was testimony to show that they were reasonably worth the prices claimed, and that the materials and labor went into the building and improvement of the company; there was some testimony that Hughes directed it and the representative of the company sanctioned it, but plaintiff appears to have thought it safer to withdraw the claim, presumably because the work was outside the contract of the company with Hughes.

On that exhibit of facts, plaintiff, at all events, saw proper to abandon his claim for lien as to all items except the brick work, which was shown to have been done as alleged. There was proof further that the price charged therefor was reasonable.

It also appeared from plaintiff’s testimony that the brick work was completed in March, 1893; and that the company refused payment of the demand on the ground that the principal contractor, Hughes, had already been fully paid for the whole work according to his contract.

Plaintiff at the trial also withdrew his claim for a money judgment against Hughes, as to all the items except the brick work, notwithstanding Hughes was in default and had made no answer.

The verdict for plaintiff was for $3,414.11 against Hughes, and in favor of the Pipe company on the lien.

Much testimony was introduced which need not be recited in view of the nature of the issue presented by the present appeal from the order granting plaintiff a new trial.

It is enough now to say that “the sole contested issue of fact was raised by the affirmative defense set up in the appellant’s amended answer, viz: Whether the claim of Delaney brothers- against the principal contractor, Hughes, had been assigned to plaintiff before the filing of the mechanics’ lien, and whether at [687]*687the time the lien was filed, Ittner, the plaintiff, or Delaney Brothers, was the owner of the demand. It was ■conceded that the demand had been transferred to Ittner long before the lien was filed, but, on behalf of the plaintiff, it was contended that such transfer was a mere pledge, and by the appellant, that it was an absolute transfer. There was testimony to support both contentions.”

The quotation is from appellant’s statement in this court. It will be taken to sufficiently indicate the dispute now submitted for decision.

The learned trial judge assigned, as the reason for granting the new trial, error in the instructions given.

It does not appear necessary to copy the instructions at large.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Quality Dairy Company
400 S.W.2d 78 (Supreme Court of Missouri, 1966)
Herrman v. Daffin
302 S.W.2d 313 (Missouri Court of Appeals, 1957)
Larson v. City of Seattle
171 P.2d 212 (Washington Supreme Court, 1946)
Mueller v. Schien
176 S.W.2d 449 (Supreme Court of Missouri, 1943)
Williams Lumber & Manufacturing Co. v. Ginsburg
146 S.W.2d 604 (Supreme Court of Missouri, 1941)
Conroy Ex Rel. Conroy v. St. Joseph Railway, Light, Heat & Power Co.
134 S.W.2d 93 (Supreme Court of Missouri, 1939)
Thompson v. St. Joseph Railway, Light, Heat & Power Co.
131 S.W.2d 574 (Supreme Court of Missouri, 1939)
Arnold v. Alton Railroad Co.
124 S.W.2d 1092 (Supreme Court of Missouri, 1939)
Woodling v. Westport Hotel Operating Co.
63 S.W.2d 207 (Missouri Court of Appeals, 1933)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
Mooney v. Monark Gasoline & Oil Co.
298 S.W. 69 (Supreme Court of Missouri, 1927)
State ex rel. Southern National Bank v. Ellison
181 S.W. 998 (Supreme Court of Missouri, 1915)
Landreth Machinery Co. v. Roney
171 S.W. 681 (Missouri Court of Appeals, 1915)
Kelly v. City of Higginsville
171 S.W. 966 (Missouri Court of Appeals, 1914)
Banner Lumber Co. v. Robson
168 S.W. 244 (Missouri Court of Appeals, 1914)
Rochester v. Seattle, Renton & Southern Railway Co.
135 P. 209 (Washington Supreme Court, 1913)
Barr v. Hays
155 S.W. 1095 (Missouri Court of Appeals, 1913)
Graefe v. St. Louis Transit Co.
123 S.W. 835 (Supreme Court of Missouri, 1909)
Powers & Boyd Cornice & Roofing Co. v. Muir
123 S.W. 490 (Missouri Court of Appeals, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
34 S.W. 1110, 133 Mo. 679, 1896 Mo. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ittner-v-hughes-mo-1896.