Grace v. Nesbitt

109 Mo. 9
CourtSupreme Court of Missouri
DecidedOctober 15, 1891
StatusPublished
Cited by46 cases

This text of 109 Mo. 9 (Grace v. Nesbitt) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grace v. Nesbitt, 109 Mo. 9 (Mo. 1891).

Opinion

Macfarlane, J.

This is a suit for judgment against the contractor, and to enforce a mechanics’ lien against the property of the owners, for the value of lumber, lime and other material furnished the contractor by plaintiff and used in the construction of a business house on a lot in the city of ChillicotljLe. The siiit is against J. Y. Nesbitt as contractor and purchaser of the materials, and Smith, McVey & McG-ee as owners of the lot and building.

The petition contained two counts. The* first was for a special bill of lumber and lime, for which a charge [14]*14In bulk of $2,800 is made. The items of all the materials are given in detail, but no prices are fixed to the •several items. On this account plaintiff applied credits amounting to $2,795.65, which left an unpaid balance of only $4.35.

The second cause of action is based on a running •account for material, the value of each item being stated in the account, except in three instances. One for a number of doors, windows and sashes, the articles being itemized, but the values placed in the aggregate at $440. The second was for yellow pine bars, /casings and mouldings, giving the items of each, $255; and the third fpr another itemized account for doors and windows, $260. The second count in the petition fails to charge in terms that the materials so furnished by plaintiff were used in the construction of the building. It does charge that Nesbitt, the contractor, applied to the plaintiff for lumber and material with - which to construct the building, and agreed to pay the value of all such lumber and material as plaintiff might furnish and supply for the construction of suck building, and, pursuant to such agreement, he did, from time to time, furnish to said Nesbitt lumber and material to be used in the construction of said building of the value of $3,194.06.

Defendants Smith and others, owners of the property, answered over, without objection to the petition, by demurrer or otherwise. In one part of the answer they deny that the material was used in the construction of the building, and, in a special defense, they charge that the account - is fraudulent and wrongful, “in this, that the lime, lumber, laths and other materials therein mentioned, or a great part thereof, was not furnished and used in the construction of said building.; ? Upon a trial to the court, without a jury, a judgment was rendered for plaintiff against Nesbitt for balance [15]*15■claimed on the accounts, and a decree against the property enforcing the lien, and the owners appealed.

I. On the trial objection was made, by the defendant owners, to the introduction of any evidence under the petition for two reasons. The first was that it did not appear from the petition that the material specified in the account was used in the construction of the building. It is well-settled law in this state that no lien for the value of materials can be acquired, unless they go into the construction of the improvement, and that fact becomes a necessary averment of the petition. It is also a well-settled rule of practice that the omissions or other defects of the petition may be cured by the subsequent pleading of the adverse party. We think, in this case, that the aid given the petition, by the averments in the answer, fairly 'formed an issue, under the pleadings, as to whether, or not, the materials furnished by plaintiff were used in the construction •of-the building. That issue was tried, and complaint now comes too late. Defendants must be consistent .and abide the result of an issue they aided in making. Bigelow on Estoppel [5 Ed.] 717; Hughes v. Carson, 90 Mo. 399; Garth v. Caldwell, 72 Mo. 622.

II. The second objection urged as ground upon which the introduction of the testimony under the petition should have been denied was that “the petition counts separate and distinct contracts and alleges but one notice and lien.” The counts of the petition show that the material specified in the two counts was furnished by plaintiff, to the contractor, under distinct and independent contracts, or arrangements, so much so that it was necessary to declare on the accounts as independent causes of action, in different counts. Only -one lien account was filed, but it covered all the items ■of material included in the two counts. Only one .notice was given to the owners of the property that [16]*16plaintiff held a lien against it, but that notice included, a copy of the whole lien account as filed.

There is no provision of the statute requiring a separate account to be filed for each separate contract, under which material may have been furnished, though the material may be entirely different and the contracts independent. The statute requires the account filed to be “a just and true account of the demand due him or-them after all just credits have been given.” The statute evidently only contemplated filing one account, and no reason can be seen for adding anything to its requirements. We agree with the St. Louis court of appeals when it says: “It is permissible to "embrace in an account, filed as a lien, items for work on the same building under different contracts with the owner; but, in order to enforce the lien for the entire work, the evidence must show that the lien was filed within six months after the completion of the work under each contract.” Kern v. Pfaff, 44 Mo. App. 30.

The same may be said of the sufficiency in form and substance of the notice served on McYey. The requirement of the statute is satisfied if the notice informs the owner that the lienor “holds a claim against such building or improvement setting forth the amount and from whom the same is due.” The proceeding is statutory, and that only is required to be done which the statute directs shall be done. R. S. 1879, sec. 3190 Laswell v. Church, 46 Mo. 279.

III. The claim constituting the first count in the petition, as it was filed, consisted of an account, itemizing the material furnished and giving the dates of delivery, without fixing any value to the respective items, but at the close stating an aggregate value of $2,800 for the whole. The items of credits were also given, leaving a balance of only $4.35 due on that account. The petition states in reference to this account that [17]*17Nesbitt, the contractor, applied to plaintiff to furnish toward the construction of said building all the lumber, lime, laths and other [materials named and specified in Exhibit “A,” hereto attached and made apart thereof; and thereupon the plaintiff agreed to furnish said material for the sum of $2,800.

Objection was made to proof of this account, on the ground that it was not such “ a just and true account of the demand” as was required by the statute. The same objection was made to three bills claimed under the second count in which the dates and items of materials were also given, but only an aggregate value. The question raised on this objection is whether the statute imperatively demands that, in the account filed, a value shall be placed upon each item of work done before a lien for such item can be secured. While the statute is remedial, and should be construed with reasonable'liberality, the right to a lien on the property of one to secure the debt of another is purely statutory, and to secure the right a substantial compliance with all the requirements of the statute, according to its reasonable intent, is essential.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Summit Lumber Co. v. Higginbotham
586 S.W.2d 799 (Missouri Court of Appeals, 1979)
Bernard v. Merrick
549 S.W.2d 561 (Missouri Court of Appeals, 1977)
Malott Electric Co. v. Bryan Enterprises, Inc.
549 S.W.2d 558 (Missouri Court of Appeals, 1977)
Continental Electric Co. v. Ebco, Inc.
365 S.W.2d 746 (Missouri Court of Appeals, 1963)
Wadsworth Homes, Inc. v. Woodridge Corporation
358 S.W.2d 288 (Missouri Court of Appeals, 1962)
Mawson-Peterson Lumber Co. v. Sprinkle
140 P.2d 588 (Wyoming Supreme Court, 1943)
H. B. Deal & Co. v. Hamilton-Brown Shoe Co.
160 S.W.2d 719 (Supreme Court of Missouri, 1942)
Royal Indemnity Co. v. American District Steam Co.
88 S.W.2d 1091 (Court of Appeals of Texas, 1935)
Blose v. Havre Oil & Gas Co.
31 P.2d 738 (Montana Supreme Court, 1934)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
Fischer v. Meiroff
213 N.W. 283 (Wisconsin Supreme Court, 1927)
State Ex Rel. St Francois County Building & Loan Ass'n v. Reynolds
232 S.W. 1035 (Supreme Court of Missouri, 1921)
McCarthy Lumber & Construction Co. v. Kinder
225 S.W. 1024 (Missouri Court of Appeals, 1920)
Springfield Planing Mill, Lumber & Construction Co. v. Krebs
193 S.W. 621 (Missouri Court of Appeals, 1917)
Jefferson Plumbers & Mill Supply Co. v. Peebles
71 So. 413 (Supreme Court of Alabama, 1916)
State ex rel. O'Malley v. Reynolds
182 S.W. 743 (Supreme Court of Missouri, 1916)
Banner Lumber Co. v. Lund
165 S.W. 389 (Missouri Court of Appeals, 1914)
National Press Brick Co. v. W. H. Lester Construction Co.
160 S.W. 1027 (Missouri Court of Appeals, 1913)
Baker v. Smallwood
143 S.W. 518 (Missouri Court of Appeals, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
109 Mo. 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grace-v-nesbitt-mo-1891.