Royal Indemnity Co. v. American District Steam Co.

88 S.W.2d 1091
CourtCourt of Appeals of Texas
DecidedNovember 20, 1935
DocketNo. 8113.
StatusPublished
Cited by10 cases

This text of 88 S.W.2d 1091 (Royal Indemnity Co. v. American District Steam Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Royal Indemnity Co. v. American District Steam Co., 88 S.W.2d 1091 (Tex. Ct. App. 1935).

Opinion

McCLENDON, Chief Justice.

This is a materialman’s Hen suit brought under R.C.S. art. 5160, as amended in 1929 (Acts 41 Leg. p. 481, c. 226, § 1 [Vernon’s Ann.Civ.St. art. 5160]). The suit was by the steam company (appellee), a subcontractor, against Osburn, the contractor (who has not appealed), and his bondsman, the indemnity company (appellant), for material furnished Osburn for use in completing a contract with the University of Texas to furnish the labor and material required to install a steam heating distribution system on the campus of that institution.

The appeal presents three questions:

1.Whether the claim filed with the county clerk satisfied the statute as to itemization by giving only the- agreed lump-sum price for the entire list of articles furnished; the claim being otherwise in full compliance with the statute as to itemization.

2. Whether the indexing by the county clerk was sufficient.

3. If not, whether indexing is essential to fix the lien.

The facts are undisputed. In so far as pertinent to the first question they are:

The steam company’s bid contained an itemized list of articles with a stated price for each article, aggregating $3,600.62, but offering to accept a lump sum of $3,450 if the entire list was purchased. This offer was accepted, and the material furnished thereunder. The claim filed with the county clerk contained a full itemization of each article, which is conceded to be sufficient, except that a designated price for each article was not given, but only the lump-sum price of $3,450.

The exact point thus raised is one of first impression in this state. So far as our research has disclosed, among states requiring itemization of lump-sum claims under statutes similar to our own, only four have passed upon it: Missouri (Grace v. Nesbitt, 109 Mo. 9, 18 S.W. 1118, 1120); Montana (Bardwell v. Anderson, 13 Mont. 87, 32 P. 285, 287); Pennsylvania (Willson v. Canevin, 226 Pa. 362, 75 A. 666, 667); West Virginia (Hough v. Watson, 91 W.Va. 161, 112 S.E. 303, 306). Uniformly the holding in these jurisdictions is that where the contract is for a lump sum the statute regarding itemization is satisfied by listing separately the items and stating the lump sum agreed upon without assigning a price or value to the separate items.

Appellant relies in the main upon the following cases: Union Indemnity Co. v. Rockwell (Tex.Com.App.) 57 S.W.(2d) 90, 91; Hardin v. McCarthy (Tex.Civ.App.) 55 S.W.(2d) 1099; Ormsby Chevrolet Co. v. White (Tex.Civ.App.) 60 S.W.(2d) 517, 519. In none of these cases was the question of itemization of price, as distinguished from articles, involved. In the Rockwell Case the claim stated that the claimant “did furnish all labor and material and did install the plumbing” under a turnkey job contract. There was. nothing to show what articles 'were furnished or what labor performed. In the Hardin Case the claim listed four cars of cement at a designated price for each car, but did not give the quantity of cement in each car, or in gross. In the Ormsby Case two Chevrolet automobiles and *1093 one Chevrolet truck were listed, but the price neither separately nor in gross was given. The amount claimed was stated as the balance due after deducting all credits without indicating the amount of the credits. “Without this data,” the opinion reads, “there is no way to calculate the cost of the three motor vehicles, and this data was absolutely essential to the sufficiency of the affidavit.”

Some of the language employed in the Rockwell opinion, if considered in the abstract, might be broad enough to embrace appellant’s contentions. This language, however, must be construed in the light of the record then before the court, in order to ascertain the court’s decision. Reference in the opinion to the conflict in authority in 40 C.J. p. 242, § 293bb, is urged in support of appellant’s contention. This conflict, however, is upon the necessity for any character of itemization where there is a lump-sum bid. The necessity for itemizing the price in lump-sum bids where the articles are itemized is treated in 40 C.J. p. 245, § 296ee. No conflict is noted upop this point, the authorities holding as above stated.

The lien being a creature of the statute, strict compliance with its provisions is required. Rockwell Case, supra. This simply means that the things required by the statute must be done in a manner that will accomplish the objectives of the statute in prescribing their doing. Specifically: “The sufficiency of the itemization must be determined, in view of the objects and purposes of the statute. The evident purpose of the statute here involved is to provide the owner of the property with such particulars as will enable him to ascertain whether or not the account is correct, and show the facts necessary to the establishment of. a lien, not only for the benefit of the owner, but of third parties as well, who may be or might become interested or affected thereby.” Ball v. Davis, 118 Tex. 534, 18 S.W.(2d) 1063, 1064.

The purpose of itemization is thus stated in the West Virginia case, above: “The evident purpose of requiring an itemized account to be served by a sub-contractor on the owner is that the latter may be able to check up the account with reference to the material and labor furnished, and to determine therefrom whether they actually 'went into the building or other structure contracted for. The price of each item is not important, if the aggregate of the whole is shown, and where, as in this case, the price was not by the piece or day, but for the aggregate of particular lots of material, it would hardly be possible to segregate and apply the sum total in that way to each item of material.”

This from the Pennsylvania case, above: “The statement gives the owners a detailed account of the various items of materials furnished, the total of the price to be paid, and the kind of materials furnished. This is all the information he heeds to enable him to deal intelligently with the contractor and protect himself. He can readily ascertain, if he desires to know, whether or not the contract price was exorbitant and beyond the fair value of the materials agreed to be furnished. If he desires, he can have a price put upon each item of the material furnished by a person competent to value it, and in that way determine whether the sum total is exorbitant. While the price agreed to be paid was a lump sum, the various items of the materials furnished are specifically set forth in the statement. This differentiates it from the case where the items and character of the material are not given and the price is a lump sum. In such case the statement would not be sufficient because it would not enable the owner to ascertain the fair value of the materials furnished for which only is he liable.”

And this from the Montana case, above: “The items of materials alleged to have been furnished are so particularly set forth in said account that any person informed as to the reasonable value of such wares can readily ascertain whether the * aggregate price set down is just and reasonable. Therefore we cannot sustain the ruling of the court excluding said lien account on the ground that it is not sufficiently itemized.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwestern Bell Telephone Co. v. Reeves
578 S.W.2d 795 (Court of Appeals of Texas, 1979)
Wiseman Hardware Co. v. R. L. King Construction Co.
387 S.W.2d 79 (Court of Appeals of Texas, 1965)
Maryland Casualty Co. v. Barron-Britton, Inc.
336 S.W.2d 622 (Texas Supreme Court, 1960)
Maryland Casualty Co. v. Barron-Britton, Inc.
327 S.W.2d 769 (Court of Appeals of Texas, 1959)
Lebo v. Dochen
310 S.W.2d 715 (Court of Appeals of Texas, 1958)
Turner Roofing & Supply Co. v. United Pacific Insurance Co.
289 S.W.2d 407 (Court of Appeals of Texas, 1956)
Allis-Chalmers Mfg. Co. v. Curtis Electrical Co.
259 S.W.2d 918 (Court of Appeals of Texas, 1953)
Bancroft v. Welch
250 S.W.2d 285 (Court of Appeals of Texas, 1952)
Grapette Co. v. Bowden
165 F.2d 487 (Fifth Circuit, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
88 S.W.2d 1091, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-indemnity-co-v-american-district-steam-co-texapp-1935.