National Press Brick Co. v. W. H. Lester Construction Co.

160 S.W. 1027, 177 Mo. App. 573, 1913 Mo. App. LEXIS 63
Missouri Court of Appeals·Decided November 4, 1913·Published·Cited by 5 cases

Opinion

ALLEN, J.

This is an action to enforce a mechanic’s lien. The only question involved in the appeal pertains to a lumping charge in the lien account filed. The debit side of the lien account is as follows: March 8, 1910—To 2,000 Common- Brick

(8%x2%x4) ..........................$ 15.00

April 6, 1910-—To 3,000 Common Brick (8y4x21/4xá) .......................... 22.50

May 31, 1910—-To 10,000 Common Brick (8%x2%x4) .......................... 75.00

June 1-29, 1910—To 137,000 Common Brick (8i4x2%x4) .......................... 1027.50

June 23-Sept. 9, 1910—To 16,491 Enamel Brick, Special Sizes, as itemized on Statement (A) ............................ 2243.43

July 5-16, 1910—To 81,000 Common Brick (8%x2%x4) .......................... 607.50

July 13, 1910—To 8,000 Enamel Stretcher Brick ..................'............. 800.00

$4790.93

Then follow various credit items totaling $2531.48, leaving a balance of $2259.45, for which amount the lien is sought to be enforced. The lumping charge in question is that for the 16,491 enamel brick, totaling $2243.43. Attached to the account is “Statement A,” which, without specifying dates or prices, gives in detail the number of different kinds and sizes of enamel brick furnished. There was judgment below sustaining the lien, from which the owners of the property have appealed.

Appellant takes the position that the lumping charge in question is not authorized under the mechanic’s lien statute, in view of the evidence relating to the purchase by the contractor, W. H. Lester Construction Company, of these enamel brick from the brick company, respondent herein.

[577] The evidence reveals that the contractor furnished the plaintiff with a list of various enamel brick, of different shapes and of special sizes, and that the plaintiff quoted the contractor certain prices for the various classes of brick contained in this list ; and quoted a price of $7.50 per thousand on the common brick. The plaintiff did not manufacture the enamel brick, but purchased the same from a manufacturer, and informed the contractor that its quotations were based on shipments of carload lots, and that if less than carload lots were required, the prices would be subject to additional charges for packing in barrels and freight or express above the regular carload rate. Plaintiff made these quotations in writing, and the contractor signed a written acceptance of the same, which paper constituted the contract between the parties at that time.

On behalf of plaintiff, its secretary and sales-manager, Charles W. Irwin, testified that after plaintiff had commenced to make deliveries under the above contract, and as the work progressed, a number of changes were made in the original list that had been furnished plaintiff, and that the contractor ordered a great many enamel brick of special shapes and sizes which were not contemplated by the original contract, and that in many instances it was necessary that these orders be filled very quickly; that the matter became so complicated on account of these extra orders and the special brick required, and the fact that the original prices were on a carload basis, whereas the brick furnished under the special orders had to be packed in barrels and shipped by local freight, that the witness interviewed Mr. Lester, representing the Contractor Company, telling him that prices could not be at once quoted on these special orders; and that it was thereupon agreed between the plaintiff and the contractor to treat this entire lot of enamel brick, i. e.,

[578] special sizes itemized on “Statement A,” in disregard of the original contract of the original prices; that the plaintiff would make a reasonable price for this entire lot; and that plaintiff and the contractor would afterwards go over the matter and agree upon what these brick were worth. It appears that the last delivery was made on September 9, and this witness testified that, on September 15, he had a further conference with Mr. Lester, the contractor’s representative, at which time they agreed that the total price of $2243.43 would be reasonable for the entire special lot of brick.

In cross-examination this witness testified that the enamel brick in question were sold “on open account,” on the understanding that the price would be reasonable “on the winding upon of the contract;” that he said to Mr. Lester, “now we will get all these special sizes here, Mr. Lester, and we will then have the bills from the company, showing what they cost, and we will put these specials all in one lot and agree upon a price;” that it was agreed to disregard the contract prices, and that the plaintiff would make one entire price, which price would be reasonable, and that the parties would undertake to agree as to what would be a reasonable price for the total.

The cause was referred by the lower court to "W. K. Koeraer, Esq., of the St. Louis Bar, to try all of the issues, and we quote that portion of the referee’s report in which the latter deals with the lumping charge for the item here under consideration, as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

National Press Brick Co. v. W. H. Lester Construction Co., 160 S.W. 1027, 177 Mo. App. 573, 1913 Mo. App. LEXIS 63 (Mo. Ct. App. 1913).

160 S.W. 1027 (National Press Brick Co. v. W. H. Lester Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McMillan v. Ball & Gunning Milling Co.
204 S.W. 257 (Supreme Court of Missouri, 1918)
Springfield Planing Mill, Lumber & Construction Co. v. Krebs
193 S.W. 621 (Missouri Court of Appeals, 1917)
McMillan & Parker v. Ball & Gunning Milling Co.
177 S.W. 315 (Missouri Court of Appeals, 1915)