Israel v. Campbell

330 P.2d 83, 163 Cal. App. 2d 806, 1958 Cal. App. LEXIS 1568
CourtCalifornia Court of Appeal
DecidedSeptember 30, 1958
DocketCiv. 17771
StatusPublished
Cited by9 cases

This text of 330 P.2d 83 (Israel v. Campbell) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Israel v. Campbell, 330 P.2d 83, 163 Cal. App. 2d 806, 1958 Cal. App. LEXIS 1568 (Cal. Ct. App. 1958).

Opinion

BRAY, J.

Each of the parties sued the other in separate actions for breach of contract. The actions were consolidated for trial. Appellants appeal from a judgment of $13,123.14 in favor of respondent in the action brought by respondent and holding that appellants take nothing in the action brought by them.

Questions Involved

1. Was the court’s finding as to the contract erroneous?

2. Did the court err in striking parol evidence of the meaning of the contract?

3. Was Edwards in default?

4. Damages: (a) Was Edwards’ breach the proximate cause? (b) Uncertainty and alleged improper allowance.

5. Alleged error in permitting witness to refresh his recollection.

6. Did the award exceed the prayer of the complaint?

Record

Appellants are copartners doing business under the name of Edwards Lumber and Manufacturing Company. They will be referred to as Edwards. Respondent does business under the name of Campbell Construction and Equipment Company, and will be referred to as Campbell. Edwards sued Campbell for $22,778.45 for lumber sold by the former to the latter pursuant to a contract and for $4,578.80 damages from *811 loss of profits. Campbell sued Edwards for failure to deliver lumber under said contract for $11,087.53 damages. During the trial this amount was increased to $30,079.96 by amendment to the complaint.

Evidence

In June, 1953, Campbell had a contract with the United States Government to build 21,127 wooden pallets. 1 Negotiations between the parties resulted in a purchase order signed by Campbell being sent to Edwards. It stated: “Furnish and deliver, FOB Jobsite . . . 252,000 pcs-2"x6"x6' DF S4S . . . All lumber to be certified #2 and better and to. be precision cut to length. [ 2 ] . . . Delivery to start on June 29, 1953 and to continue at the rate of 45,000 MBF per working day until completed.” On July 1, 1953, Edwards wrote Campbell a letter stating: ‘ ‘ Confirming our telephone conversation, we acknowledge receipt of the above order and accept same in all particulars except delivery is to commence at once and be completed within 90 days. We will endeavor to remain as close to your schedule as possible but cannot guarantee 45,000' per each working day. Hoping this will be satisfactory, we are ...” This letter was delivered by Israel Sr. who stated that he could not guarantee delivery of 45,000 board feet per day but felt that he could deliver the entire amount in the stipulated time. Mincey, Campbell’s general superintendent, told him to do the best he possibly could. Mincey informed Israel of the job requirements schedule and the operation. The job was set up to produce 500 pallets a day. Under the purchase order Edwards could deliver green lumber. Campbell was going to “stick” the lumber to dry it. “Stick” means stacking the lumber with lathing in between so that the air can circulate around each piece separately. It was estimated that it would take three weeks to 30 days for drying and it was expected that Campbell would start to build pallets on August 1, 1953. The lumber ordered from Edwards would be all the lumber necessary for the pallets and it was not contemplated that any other would be bought. 3

*812 From July 1 to August 1 Edwards delivered five loads totalling 81,958 board feet. Campbell was constantly complaining about the lack of delivery and about August 3 handed Edwards a written protest stating that the deliveries were deficient in amount and grade and were not precision cut; that the situation was “intolerable” and that unless Edwards started to comply with the purchase order in 48 hours Campbell would buy lumber when and where possible and would charge Edwards with any excess costs. M'incey complained to Israel about once a week and Israel would reply that the lumber was coming. In August Edwards delivered 12 loads totalling 224,851 board feet and one load in September of 15,030 board feet. There were a number of rejects, being pieces too short or warped or otherwise unusable. The rejects were either taken away by Edwards or sent back. They amounted to about 16,000-19,000 board feet. August 19 a letter was sent Edwards to the effect that the 48-hour period of grace mentioned in the previous letter had expired and that Campbell was proceeding to purchase material where and as possible. Any excess cost would be charged to Edwards’ account. However, Campbell would accept such deliveries as Edwards could make.

It was stipulated that the amount of lumber delivered by Edwards for which Edwards received credit was of the gross amount of $22,778.45 less credits for rejects and back charges, or a net balance of $19,812.49.

1. The Contract.

The court found that the purchase order and the letter of July 1 constituted the entire contract between the parties and that there were no ambiguities in it. Edwards contends that the order was merely an offer and that the letter was a qualified acceptance which in turn became a new proposal which was never accepted, so that there was no contract. See section 1585, Civil Code, requiring an acceptance to be absolute and unqualified and stating that a qualified acceptance is a new proposal. See also Four Oil Co. v. United Oil Producers, 145 Cal. 623 [79 P. 366, 68 L.R.A. 226]; May Hosiery Mills v. G. C. Hall & Son, 77 Cal.App. 291 [246 P. 332]. However, here there was an acceptance of the counter-offer. It was not exactly expressed in words, but the actions of both parties show that they considered a contract as expressed in the two writings was entered into, modified to the extent that delivery of said lumber was to *813 be made over the 90-day period with delivery as near to 45,000 board feet per working day as possible. Edwards’ complaint alleges that the parties entered into a written agreement in which Edwards agreed to sell and Campbell to buy certain lumber “delivery to be made within 90 days.” The quantity and price are set forth the same as in the purchase order.

However, the finding that the entire contract between the parties consisted of the purchase order and the letter of July 1, 1953, is incorrect. It should have stated that these two writings and an oral acceptance agreeing to the modification above mentioned constituted the entire agreement between the parties. In another finding the court, in effect, so found. It stated that “it was the clear understanding of said parties that said contract provided that delivery of said lumber should be made over the ninety day period mentioned in said contract, with delivery as near to 45,000 ft. per working day as possible.” This court has power to, and hereby does correct the findings as hereinabove set forth.

2. Pabol Evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirk v. Dimitri CA4/1
California Court of Appeal, 2013
Onyx Pharmaceuticals, Inc. v. Bayer Corp.
863 F. Supp. 2d 894 (N.D. California, 2011)
Bank of California v. Connolly
36 Cal. App. 3d 350 (California Court of Appeal, 1973)
Page v. Bakersfield Uniform & Towel Supply Co.
239 Cal. App. 2d 762 (California Court of Appeal, 1966)
J. C. Peacock, Inc. v. Hasko
196 Cal. App. 2d 353 (California Court of Appeal, 1961)
Buchanan v. Hammond
340 P.2d 556 (Washington Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
330 P.2d 83, 163 Cal. App. 2d 806, 1958 Cal. App. LEXIS 1568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/israel-v-campbell-calctapp-1958.