Irwin & Leighton v. United States

115 Ct. Cl. 18, 1949 U.S. Ct. Cl. LEXIS 3, 1949 WL 4919
CourtUnited States Court of Claims
DecidedDecember 5, 1949
DocketNo. 48561
StatusPublished
Cited by6 cases

This text of 115 Ct. Cl. 18 (Irwin & Leighton v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irwin & Leighton v. United States, 115 Ct. Cl. 18, 1949 U.S. Ct. Cl. LEXIS 3, 1949 WL 4919 (cc 1949).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

Plaintiffs sue to recover $2,342.13 for extra labor costs incurred in the performance of a lump-sum construction contract entered into with defendant on June 28, 1944, for the construction of hangars, warehouse and terminal facilities at the New Castle Army Air Base, New Castle County, Delaware. The increased costs resulted from payment by plaintiffs of a higher wage rate to laborers working on the project than the rate specified in the contract specifications.

In conformity with the act of August 30, 1935,1 known as the Davis-Bacon Act, the invitation for bids provided that the contractor would be required to pay all mechanics and laborers employed on the site of the work the rates of wages stated in the specifications, referring particularly to Article 17 of the contract. It was further stated that wage rates for the locality of the work had been determined by the United States Department of Labor on August 26,1942, and subsequently 'modified November 1, 1943, January 10, 1944, and February 14,1944. Paragraph 1-16 of the specifications provided in part as follows:

[33]*33(a) The wages to be paid laborers and mechanics on this project, as determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the pertinent locality, are as follows:
Classification Bate per hour
Laborers, building_$0. 75
Laborers, concrete_ . 75
Laborers, unskilled- . 75

Article 17 of the contract, referred to in the invitation, provided that the contractor must pay all labor employed directly upon the site of the work wages “not less or more than those stated in the specifications (subject to Executive Order Number 9250 and the General Orders and Regulations issued thereunder) regardless of any contractual relationship which may be alleged to exist between the contractor * * * and such laborers and mechanics;”.

The invitation for bids also provided in pertinent part as follows:

20. Investigation oe Conditions. — Bidders are expected to visit the locality of the work, and to make their own estimates of the equipment and other facilities needed and to evaluate difficulties attending the execution of the proposed contract, including local conditions, availability of labor, transportation facilities, uncertainties of weather, and other contingencies. * * * Failure to acquaint himself with all available information concerning these conditions will not relieve the successful bidder of assuming all responsibilities for estimating the difficulties and cost of successfully performing the complete work.

Plaintiffs investigated the conditions at the site of the work but did not inquire into the labor situation. Relying entirely upon the wage provisions in the contract and specifications, plaintiffs estimated their bid, making no allowance for a possible increase in wage rates. Plaintiffs were low bidders and their contract with defendant was executed on June 28,1944, to be completed in 90 days.

Early in July when plaintiffs were prepared to commence work under the contract, they applied to Local No. 199, Hod [34]*34Carriers’, Building and Common Laborers’ Union, A. F. of L., for laborers. At that time shipyards in the New Castle area were paying a starting wage rate of 78 cents per hour to unskilled labor. These jobs carried the classification of “helper” and the rate of pay increased to $1.00 per hour as the worker’s skill increased. There was apparently sufficient work available in the shipyards and munitions factories in the area to provide work for considerable numbers of the building construction workers who were members of Local 199. As a result of this situation, the local union was unable to supply plaintiffs with laborers to work at the 75-cent-per-hour rate specified in their contract. Plaintiffs’ subsequent application to the Area Office of the War Manpower Commission met with no better success. During the first three weeks of, the contract when plaintiffs should have been working from 20 to 35 laborers on the job, they had been able to employ only 5 laborers and two pushers (straw bosses) and these men were recruited from Army enlisted personnel who worked on their days off with the consent of their commanding officer.

At the end of the third week plaintiffs reported their difficulties to the contracting officer. Plaintiffs appear to have been familiar with wage stabilization laws and regulations and suggested an application to the Wage Adjustment Board for permission to pay a rate to laborers sufficiently higher than the contract rate to enable them to meet competition in the local labor market. The contracting officer approved of this course of action and assigned a civilian employee to assist plaintiffs in preparing their application to the Board. The contracting officer asked plaintiffs if they proposed to request reimbursement from the Government in the event the wage increase was allowed. Plaintiffs replied that they would reserve their right to do so, apparently depending on the amount involved.

As supporting data for their wage adjustment application plaintiffs secured a letter from the Area Director of the War Manpower Commission and one from the local laborers’ union. The letter from the War Manpower Commission was in response to a letter from plaintiffs inquiring as to the differences in pay scale for common labor in the vicinity,- [35]*35and advised plaintiffs that local industrial plants and shipyards in the area were paying “helpers” rates ranging from 78 cents to $1.00 per hour. The letter from the union, which executed the application for wage adjustment jointly with plaintiffs, read in part as follows:

This is to notify you that it is impossible to furnish men for the rate of 750 per hour. Owing to high cost of living the men cannot make or meet their current expenses.
The contract for 75$ per hour expired August of 1943. That was set by the Government September 17, 1942. I am not making a demand for more money but men of today will not work for any less than 85‡ per hour. Many Bosses are paying the above mentioned rate and more. The Bosses have the work, likewise they have to get it off their hands, so consequently they pay 850 per hour or more on various occasions. This is the reason why I am notifying Bosses and etc., who employ men from this Local No. 199.
I have been advised by Bosses to send notices for a protection of some kind or for a protection to them so as to avoid difficulties on governmental work. So, I trust that this is a protective notice for the benefit of the Bosses and other concerns who hire or employ laborers of Wilmington and Vicinities.

The joint application for approval of wage rate adjustment was executed by the union and plaintiffs on July 20, 1944. It stated, among other things, that between 40 and 50 laborers were involved; that the laborers’ rate in the area on January 1, 1941, had been 70 cents per hour; that the “present wage rate” was 75 cents and that the “proposed wage rate” was 85 cents per hour. The statement of facts in justification of the proposed adjustment read in part as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
F. H. McGraw & Co. v. United States
130 F. Supp. 394 (Court of Claims, 1955)
FH McGraw and Company v. United States
130 F. Supp. 394 (Court of Claims, 1955)
Binghamton Construction Co. v. United States
107 F. Supp. 712 (Court of Claims, 1952)
Kirchhof v. United States
102 F. Supp. 770 (Court of Claims, 1952)
Merrill-Stevens Dry Dock & Repair Co. v. United States
96 F. Supp. 464 (Court of Claims, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
115 Ct. Cl. 18, 1949 U.S. Ct. Cl. LEXIS 3, 1949 WL 4919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irwin-leighton-v-united-states-cc-1949.