Intervale Steel v. Borg & Beck Div., Borg-Warner

578 F. Supp. 1081, 38 U.C.C. Rep. Serv. (West) 805, 1984 U.S. Dist. LEXIS 20620
CourtDistrict Court, E.D. Michigan
DecidedJanuary 9, 1984
DocketCiv. A. 81-71079
StatusPublished
Cited by9 cases

This text of 578 F. Supp. 1081 (Intervale Steel v. Borg & Beck Div., Borg-Warner) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Intervale Steel v. Borg & Beck Div., Borg-Warner, 578 F. Supp. 1081, 38 U.C.C. Rep. Serv. (West) 805, 1984 U.S. Dist. LEXIS 20620 (E.D. Mich. 1984).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

PHILIP PRATT, District Judge.

This case involves the application of the Uniform Commercial Code, adopted by Michigan, M.C.L.A. § 440.1101 et seq., to the sale of steel by plaintiff to the defendant. 1 The plaintiff, Intervale Steel Corporation (Intervale) is the successor to Barry Steel Corporation (Barry) and sold 22 coils of steel to the defendant Borg & Beck (Borg), a division of Borg-Warner Corporation. The latter has refused to remit the purchase price and this suit ensued.

I. FACTS

Barry had sold steel to Borg for over 15 years. During most if not all of that period, the defendant’s sales representative on the Borg account was Peter Adzema, a metallurgist who was also associated with Barry’s quality control department. Adze-ma visited the Borg plant frequently and was fully aware of Borg’s manufacturing processes and procedures. More particularly, Adzema testified he was familiar with Borg’s practice regarding the partial fabrication of the parts in question here and the storage of the partially completed parts until customers placed an order, after which the parts would be completed. He was also aware that Borg did not conduct microscopic examinations of ordered steel and did not cut sample pieces from ordered steel and run those samples completely through the fabrication process.

Borg is engaged in the manufacturing or fabrication of parts and components for the automotive industry. In August, 1980, it ordered 98,195 pounds of high carbon cold rolled steel for use in the fabrication of the “Belleville Spring”, a component of automobile clutch assemblies. The purchase order set forth the specifications for this steel, which were of critical importance due to the demanding requirements of the “Belleville Spring” and its function in clutch assemblies. The acceptance by plaintiff of the purchase order, of course, resulted in the plaintiff’s grant of express and implied warranties of merchantability and fitness for the purpose intended. 2

Barry obtained the steel originally from Jones and Laughlin Steel in coils. Barry then unrolled the coils, treated the steel, rerolled the coils and on August 26 and 28 of 1980 delivered 22 coils to defendant at the agreed upon price.

Borg, in accordance with its usual practice, checked the steel for dimensional accuracy and chemical content. In August or early September, 1980, Borg began its fabrication process by stamping out “blanks” from strips of the coils and deburring (smoothing) the pieces. It then stored these blanks prior to any further processing pending the receipt of orders from its automotive customers. In late September, Borg removed the pieces from storage and resumed its fabrication process which involved forming by presses, heat treatment, “wheelabrating” (similar to sandblasting), “stroking” (a stress-removal process) and “load-testing” (a quality control measure). During the course of these latter steps, however, it was observed that the springs were cracking and evidencing other failures. Notice was immediately given to Barry and Borg halted production and began extensive testing of the steel. Borg tested for several weeks and communicated to Barry regularly with regard to the testing. Eventually, it was determined that the steel was indeed defective and that the *1085 cause was associated with the fact that, contrary to the specifications of that type of steel, it had been annealed 3 once, rather than twice.

Barry admitted the steel was defective and not fit for its intended use and conceded the same at trial. Upon discovering that the entire order had been stamped, after providing for some samples for its own testing and demonstrative purposes, Barry authorized Borg to scrap the steel.

The evidence also established that Borg did not conduct metallurgical or microscopic examinations of Barry steel and that Barry was aware of this. It was further established that it is not an industry practice to do so. Moreover, it was also established that “samples” of coil steel are not run through the complete fabrication process due to the high cost of, for example, unrolling the coil, taking samples from representative parts of the coil and tying up the production line for testing purposes.

Intervale, as a successor to Barry, 4 then instituted this suit for $41,612.47, that figure representing the invoice price less credit for the scrap value realized by Borg. 5 It is the position of plaintiff that Borg accepted the steel, is not entitled to revoke that acceptance and is precluded from maintaining an action or asserting the defense of breach of warranty.

II. ACCEPTANCE AND REVOCATION

Borg argued that it did not “accept” the goods and should not be held obligated to pay the purchase price of the contract. See M.C.L.A. § 440.2607(1). Borg reasoned that it properly rejected the goods as required under Sections 2-601, 2-602 and 2-606. 6 According to defendant, although it blanked out all the steel, it could reject the steel because defendant acted reasonably and rejected the goods as soon as the breach of warranty could be discovered. Borg supports this position by citing several cases which have found effective rejections by buyers despite their changing or using the goods. It is true that Borg acted reasonably, nonetheless, under the circumstances Borg’s action can only be viewed to constitute acceptance of the steel.

First, under the Uniform Commercial Code, Borg’s rejection after the steel was entirely stamped out was not effective. 7 Borg did not attempt to reject the steel until after it had received shipment, blanked all the steel, and stored the partially completed parts for over a month. In total, Borg retained the steel for over three months before it notified plaintiff of the problems with the steel. The determination of whether goods have been accepted is governed by Section 2-606. That Section states:

(1) Acceptance of goods occurs when the buyer
(a) after a reasonable opportunity to inspect the goods signifies to the seller that the goods are conforming or that he will take or retain them in spite of their non-conformity; or
(b) fails to make an effective rejection (sub-section (1) of Section 2-602), but such acceptance does not occur until the buyer has had a reasonable opportunity to inspect them; or
(c) does any act inconsistent with the seller’s ownership; but if such act is *1086 wrongful as against the seller it is an acceptance only if ratified by him.
(2) Acceptance of a part of any commercial unit is acceptance of that entire unit.

M.C.L.A. § 440.2606. Subsection (l)(b) appears to most appropriately apply in the instant case 8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles Farley v. Country Coach Incorporated
403 F. App'x 973 (Sixth Circuit, 2010)
Farley v. COUNTRY COACH, INC.
550 F. Supp. 2d 689 (E.D. Michigan, 2008)
Deere & Company v. Johnson
271 F.3d 613 (Fifth Circuit, 2001)
Electrical Power Systems, Inc. v. Argo International Corp.
864 F. Supp. 1080 (N.D. Oklahoma, 1994)
Piezo Crystal Co. v. Uddeholm Corp.
870 F. Supp. 589 (M.D. Pennsylvania, 1994)
M.K. Associates v. Stowell Products, Inc.
697 F. Supp. 20 (D. Maine, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
578 F. Supp. 1081, 38 U.C.C. Rep. Serv. (West) 805, 1984 U.S. Dist. LEXIS 20620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/intervale-steel-v-borg-beck-div-borg-warner-mied-1984.