Barry & Sewall Industrial Supply Co., Appellant/cross-Appellee v. Metal-Prep of Houston, Inc., Appellee/cross-Appellant

912 F.2d 252
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 23, 1990
Docket89-5453, 89-5472
StatusPublished
Cited by15 cases

This text of 912 F.2d 252 (Barry & Sewall Industrial Supply Co., Appellant/cross-Appellee v. Metal-Prep of Houston, Inc., Appellee/cross-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barry & Sewall Industrial Supply Co., Appellant/cross-Appellee v. Metal-Prep of Houston, Inc., Appellee/cross-Appellant, 912 F.2d 252 (8th Cir. 1990).

Opinion

BEAM, Circuit Judge.

Barry & Sewall Industrial Supply Co. appeals the district court’s judgment which awarded Metal-Prep of Houston, Inc. $433,000 1 in damages. Metal-Prep cross-appeals several rulings of the district court. The court found that Barry & Sewall breached an express warranty under a contract for a metal treating oven which it sold to Metal-Prep. We affirm the finding that Barry & Sewall breached its express warranty of line speeds, but reverse the award of damages for increased energy costs and lost profits. We affirm on the issues raised in the cross-appeal.

I. BACKGROUND

In 1972, Larry Kohlmeyer founded Metal-Prep, a Texas corporation which treated and painted steel coils used in the metal building industry. See Trial Transcript, Oct. 1987, at 15. The coils were comprised of strips of steel which were approximately 2000 feet long, twenty-four to forty-two inches wide, and twelve to sixteen gauges thick. Metal-Prep designed a 250-foot processing line at which it unwound the coil and ran it through a wheelabrator, painted the coil in a roll-coater, heat-cured the paint in a gas oven, cooled the painted steel in a quench tank, slit the steel into desired widths, and recoiled the steel as the finished product. Brief for Appellant at 3. The strip of hot steel was difficult to control because of various imperfections such as uneven edges, thickness variations, ir *254 regularities in tension, “oil canning,” and “camber.” These imperfections caused the coil to “wander” laterally, to jump, buck, or stand on edge as it was run through the processing line. Trial Transcript, July 1985, at 658-63. Frequently, the coil line had to be stopped to prevent damage to the oven, which stoppage resulted in the burning of the paint. Therefore, when Metal-Prep decided to build a new production facility, it negotiated with Barry & Sewall for the purchase of an infrared oven which it believed would eliminate the problems associated with the gas oven.

Barry & Sewall operated a systems division which assembled and sold high density infrared ovens. These ovens were custom-designed to heat and cure paint and laminates on coated metal, wood, and other industrial products. Brief for Appellant at 2. Barry & Sewall, however, had never designed infrared ovens for heavy-gauge coil-coating operations and it hoped to create a new market with such ovens. See Trial Transcript, July 1985, at 448-50, 601-03. After extensive discussions and plans by the two parties, Barry & Sewall offered Metal-Prep quotation no. 1276 on June 20, 1979. Barry & Sewall proposed to design and manufacture a complete high density infrared heating and control system for $112,176. On July 26, 1979, Metal-Prep accepted quotation no. 1276 subject to the following additions:

1. Guides incorporated into the oven to protect the infrared heating elements and facilitate positioning.
2. A written acknowledgment of verbal assurances that there will be no burned spots on the strip caused by heat remaining on when the line is stopped.
3. A written acknowledgment of verbal assurances that the coatings used in your demonstrations will be cured at 125 fpm [feet-per-minute] on 16 gauge and 100 fpm on 14 gauge X 48" wide.

Metal-Prep purchase order, Brief for Appellant at 250.

On August 3, 1979, Barry & Sewall acknowledged the additions which Metal-Prep incorporated:

1. Guide rollers will be incorporated into the oven to help protect the lamps and keep the coil from standing on edge.
2. There will be no burned spots on the strip due to heat remaining on when the line is stopped.
3. Most of our testing was done with 14 gauge steel and based on this testing, the 14 gauge will run 90 to 100 FPM. Based on Larry’s information on the old oven, this means the 16 gauge should run approximately 115 to 120 FPM. One item I would like to call your attention to is the reference to 48" wide material. It is Larry’^ [sic] opinion that he will be able to run 48" wide material at a slower line speed and do a satisfactory job. Although a 48" wide strip will physically fit through the oven, the oven is not designed to cure paint on a 48" wide strip.

Barry & Sewall response letter, id. at 251.

In June of 1980, Barry & Sewall shipped its infrared oven to Metal-Prep’s facility where it was installed and operated. From the beginning, the oven was slower than anticipated in its production line speeds. Also, the coil broke an inordinate number of infrared bulbs as it was run through the oven. Metal-Prep reported the complications, and Barry & Sewall responded by inspecting the oven and writing a letter dated July 1, 1980, in which it promised to make various changes to improve line speeds and remedy the other problems. On July 29, 1980, Metal-Prep sent a letter to Barry & Sewall complaining about the delays in remedying the infrared oven problems. Following numerous discussions between the parties, on August 27, 1980, Barry & Sewall agreed to redesign and build a new infrared oven for Metal-Prep at no charge.

In October of 1980, George Krahn, the Barry & Sewall sales engineer most actively involved in the Metal-Prep transaction, left Barry & Sewall. Barry & Sewall never *255 delivered a new infrared oven. Rather, it insisted that the existing oven conformed to the contract terms. On March 3, 1981, Barry & Sewall sued Metal-Prep in the Hennepin County Minnesota District Court, seeking recovery of the balance due on the contract for the manufacture and delivery of the infrared oven. Metal-Prep purchased the oven through a lease financing arrangement and paid Barry & Sewall $97,-084.60 before shipment. The remaining balance of $16,826.40 was due within thirty days of the start-up of the oven. Metal-Prep did not pay the $16,826.40 balance, nor did it pay for the parts and materials worth $27,446.64 which it allegedly requested from Barry & Sewall.

On March 20, 1981, Metal-Prep removed the case to the United States District Court for the District of Minnesota, and the case was assigned to Judge Diana E. Murphy. Metal-Prep filed a motion to dismiss for lack of personal jurisdiction or, in the alternative, to transfer the case to the Southern District of Texas. The district court denied these motions, and on August 12, 1981, Metal-Prep sent a registered letter to Barry & Sewall which stated that “we consider the entire system [infrared oven] to be non-conforming [sic] to the original contract and Metal Prep [sic] hereby revokes its acceptance, and demands full return of the purchase price plus payment of incidental and consequental [sic] damages.” Ap-pellee’s App. at 88. On August 14, 1981, Metal-Prep filed its answer in which it denied that it owed Barry & Sewall the balance for the oven or the cost of the materials. Metal-Prep also counterclaimed, alleging that Barry & Sewall breached express and implied warranties under the contract, which breaches resulted in consequential and incidental damages to Metal-Prep in the amount of $767,-083.42.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barry-sewall-industrial-supply-co-appellantcross-appellee-v-ca8-1990.