Electrical Power Systems, Inc. v. Argo International Corp.

864 F. Supp. 1080, 27 U.C.C. Rep. Serv. 2d (West) 94, 1994 U.S. Dist. LEXIS 19297, 1994 WL 547529
CourtDistrict Court, N.D. Oklahoma
DecidedSeptember 22, 1994
DocketNo. 94-C-158-BU
StatusPublished
Cited by1 cases

This text of 864 F. Supp. 1080 (Electrical Power Systems, Inc. v. Argo International Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electrical Power Systems, Inc. v. Argo International Corp., 864 F. Supp. 1080, 27 U.C.C. Rep. Serv. 2d (West) 94, 1994 U.S. Dist. LEXIS 19297, 1994 WL 547529 (N.D. Okla. 1994).

Opinion

ORDER

BURRAGE, District Judge.

On August 5, 1994, United States Magistrate Judge Jeffrey S. Wolfe issued a Report and Recommendation with respect to the plaintiffs Motion for Summary Judgment (Docket No. 4). In the Report and Recommendation, Magistrate Judge Wolfe recommended that summary judgment be granted and that the plaintiff be awarded the principal sum of $106,744.00. He also recommended that the plaintiff be awarded monthly interest of $1,601.16, reasonable storage costs since November 27, 1993, the costs of the lawsuit and a reasonable attorney’s fee as provided for in 12 O.S. § 936.

This matter now comes before the Court upon the defendant’s objection to the Report and Recommendation. The defendant objects to Magistrate Judge Wolfe’s recommendation that the plaintiff be granted pre-judgment interest at the rate of 18% per annum and in the amount of $1,601.16 per month. The defendant contends that there is no evidence in the record that the defendant and the plaintiff agreed that interest would accrue on unpaid balances at the rate of 18% per annum.

In response, the plaintiff has submitted a document entitled “Terms of Sale” which states that -all past due invoices will be subject to 18% interest per annum. The plaintiff states that it sent the document to the defendant when it acknowledged the defendant’s order for the two electrical switchgear assemblies which are the subject of this action.

The defendant, in reply, has submitted the affidavit of its president, John Calicehio. Mr. Calicehio states that he has reviewed the defendant’s file relating to this matter and that the invoice sent by the plaintiff does not contain the “Terms of Sale” document.

Having conducted a de novo review of this matter, the Court agrees with and ADOPTS Magistrate Judge Wolfe’s Report and Recommendation to the extent that it [1082]*1082recommends judgment be granted in favor of the plaintiff and that the plaintiff be awarded the unpaid contract price of $106,744.00, reasonable storage costs since November 3, 1993, the costs of the lawsuit and a reasonable attorney’s fee. The Court, however, disagrees with and REJECTS Magistrate Judge Wolfe’s Report and Recommendation to the extent it recommends that the plaintiff be awarded pre-judgment interest at 18% per annum. The Court finds that the plaintiff has failed to present sufficient evidence to establish that the document entitled “Terms of Payment” was actually sent to and received by the defendant. Thus, the Court finds that the plaintiff is only entitled to recover statutory pre-judgment interest, which is currently at 5.69% per annum.

Based upon the foregoing, the Court hereby GRANTS the plaintiffs Motion for Summary Judgment (Docket No. 4). The parties are DIRECTED to submit a proposed judgment for the Court’s approval within seven (7) days from the date of this Order. If the parties, after conferring in good faith, cannot agree as to the appropriate amount of storage costs, costs of lawsuit and attorney’s fee to be awarded to the plaintiff, the parties shall submit the proposed judgment leaving blanks for the storage costs, costs of suit and attorney’s fee. The plaintiff shall file a motion in regard to costs and attorney’s fees for the Court’s'determination.

REPORT AND RECOMMENDATION OF UNITED STATES MAGISTRATE JUDGE

[Filed Aug. 5, 1994]

WOLFE, United States Magistrate Judge.

Now before the Court is Plaintiffs Motion For Summary Judgment (docket # f)1 The motion comes after Plaintiff Electrical Power Systems, Inc. (“EPSI”) sued Defendant Argo International Corporation (“ARGO”) to collect a past due account of $106,744. Argo ordered two electrical switchgear assemblies from EPSI and then failed to pay for them. EPSI, in its Motion for Summary Judgment, argues that Argo must pay for the assemblies, citing 12A O.S. § 2-709(l)(b). For the reasons discussed below, the undersigned recommends summary judgment be granted.

1. Facts

The undisputed facts are as follows: Sonotraeh needed two electrical switchgear assemblies for use in one of its facilities in Algiers. In 1991, ARGO salesman Michael Burrell, in an effort to purchase the assemblies for Sonotrach,2 contacted EPSI Production Manager Sue Yates to see if EPSI could submit a quotation for building the assemblies. Westinghouse, apparently similarly interested in soliciting Sonotraeh’s business, also asked Yates for a quote. EPSI provided quotes to both companies.

On March 8, 1993, ARGO ordered two electrical switchgear assemblies from EPSI for $104,328 plus crating costs. Some seven months later, on October 27, 1993, EPSI completed the specially designed assemblies according to ARGO’s specifications. EPSI notified ARGO they were ready to be picked up and sent an invoice for $106,744 (cost plus crating charges). The invoice informed ARGO that payment was due November 27, 1993. No payment was ever made, nor were any subsequent agreements entered into between the parties changing the terms of payment.

Sometime between November of 1993 and January of 1994, Yates talked with a Westinghouse representative about the Sonotrach assemblies. Westinghouse asked whether EPSI would “resurrect” the quotation given to Westinghouse by EPSI two years earlier. The Westinghouse representative also told Yates that General Electric Corporation was interested in filling the Sonotrach contract.

Then, on February 8,1994, John P. Santa-Croce, ARGO’s Vice President of International Operations, talked with Yates on the telephone. Yates told SantaCroce that an[1083]*1083other company 'had inquired about the switchgear assemblies. SantaCroee told Yates “that if EPSI had another buyer, that EPSI should sell the equipment to that buyer.” Affidavit of John P. SantaCroee. A day later, SantaCroee told Bill Cody, Yates’ supervisor, the same thing. Yates made no further attempts to sell the assemblies to Westinghouse or General Electric.

After making written demand on ARGO and still receiving no payment, EPSI filed this suit on February 18, 1994. On March 11, 1994, EPSI filed the instant Motion For Summary Judgment. Subsequently, after the lawsuit and summary judgment motion was filed, EPSI President Vernon Lawson says that he did telephone representatives of Westinghouse and General Electric to determine if they would purchase the assemblies.3 Lawson says both companies told him they would not.

II. Legal Analysis

What is at dispute is (1) whether ARGO “accepted” the assemblies under Section 2-709(l)(a) of the Oklahoma Commercial Code and (2) whether EPSI, under Section 2-709(l)(b) of the Oklahoma Commercial Code, has made a reasonable effort to dispose of the assemblies or show that such an effort would be unavailing. Both questions will be analyzed by the summary judgment procedure outlined in Fed.R.Civ.P. 56.

Summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roger Edwards, LLC. v. Fiddes & Son, Ltd.
245 F. Supp. 2d 251 (D. Maine, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
864 F. Supp. 1080, 27 U.C.C. Rep. Serv. 2d (West) 94, 1994 U.S. Dist. LEXIS 19297, 1994 WL 547529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electrical-power-systems-inc-v-argo-international-corp-oknd-1994.