International Management Consultants v. Sea-z

Superior Court of Pennsylvania·Decided August 4, 2017·No. International Management Consultants v. Sea-z No. 704 EDA 2016·Unpublished

Opinion

J-A13011-17

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

INTERNATIONAL MANAGEMENT IN THE SUPERIOR COURT OF CONSULTANTS, INC. PENNSYLVANIA

Appellee

v.

SEA-Z, INC.

Appellant No. 704 EDA 2016

Appeal from the Order February 8, 2016 In the Court of Common Pleas of Montgomery County Civil Division at No(s): 2011-24556

BEFORE: LAZARUS, J., OTT, J., and FITZGERALD, J.*

MEMORANDUM BY LAZARUS, J.: Filed August 4, 2017

Sea-Z, Inc. (“Sea-Z”) appeals from the order granting Appellee’s,

International Management Consultants, Inc. (“IMC”), post-trial motion to

mold a jury verdict to include interest, attorneys’ fees and expenses under

the Contractor and Subcontractor Payment Act (“CASPA”).1 After careful

review, we affirm in part, reverse in part and remand.

On April 6, 2010, IMC entered into an agreement (“contract”) with

Sea-Z to provide materials and labor to complete renovations and additions

to Sea-Z’s King of Prussia, Pennsylvania, warehouse facility and office

____________________________________________

* Former Justice specially assigned to the Superior Court. 1 73 P.S. §§ 501-516. J-A13011-17

building. The contract price was a lump sum of $1,509,824.00. Under the

contract, Sea-Z agreed to pay IMC in-progress payments based on written

“application of payment” as the work progressed. Sea-Z was entitled to

deduct 10% of the amount approved for payment to be held as “retainage”

until final payment was due.

The contract required IMC to achieve “substantial completion” 2 within

208 calendar days from the date work commenced. Here, work commenced

in June 2010 after IMC received the permit. Substantial completion was

delayed. IMC and Sea-Z each disagree as to which party is responsible for

the contract delay. IMC contends that substantial completion occurred on or

around March 17, 2011; Sea-Z contends that IMC abandoned the project

prior to achieving substantial completion.

On August 26, 2011, IMC filed a complaint against Sea-Z for breach of

contract, CASPA violations, and unjust enrichment, seeking to recover the

contract balance due on the project. IMC calculated the balance owed under

2 Substantial completion is defined under the contract as:

[T]he stage in the work when the work or designated portions thereof is sufficiently complete in accordance with the contract documents so that the owner can occupy or utilize the work for its intended purpose.

A201 General Conditions, §9.8.1.

-2- J-A13011-17

the contract at $118,923.70,3 which represented the total of two unpaid

invoices it submitted to Sea-Z in February and April 2011.4 On October 6,

2011, Sea-Z filed an answer, new matter and counterclaim for breach of

contract, contractual liquidated damages,5 and attorneys’ fees, interest, and

penalties, alleging that it had a contractual right to withhold payment as a

result of IMC’s “failure to perform and/or complete the work” in accordance

with the parties’ contract.6 See Sea-Z Answer, New Matter & Counterclaim,

10/6/11, at 14. In its answer, Sea-Z averred that the parties’ original

contract sum was increased to $1,571,756.00 “based []on mutually agreed

upon change orders to the Contract,” and that Sea-Z “has paid IMC

3 IMC later stated in its answer to Sea-Z’s counterclaim that the balance owed under the parties’ contract was $123,897.70, based on the fact that the contract sum was later increased from $1,509,824.00 to $1,575,631.00 by mutually agreed change orders. 4 According to IMC, it submitted invoices to Sea-Z on February 25, 2011, in the amount of $75,797.13, and on April 25, 2011, in the amount of $43,126.57. IMC Complaint, 8/26/11, at ¶¶ 8-10. 5 Sea-Z sought liquidated damages pursuant to the parties contract, for IMC’s failure to achieve substantial compliance in a timely manner, citing the parties’ contract to substantiate its entitlement to over $50,000, plus post- judgment interest. In coming to its calculation of liquidated damages, Sea-Z computed the damages at $500.00/day for days 1-30 after substantial completion date (SCD); $1,000.00/day for days 31-60 after SCD; $1,500.00/day for days 61-90 after SCD; and $2,000.00/day for 91 days after SCD. 6 Specifically, the counterclaim alleged that the incomplete work consisted of 54 items. Moreover, Sea-Z also claimed that IMC’s work did not conform to the contract with regard to 11 items.

-3- J-A13011-17

$1,451,751.00, leaving a contract balance of $120,005.00.” Id. at ¶¶ 10-

11. Moreover, Sea-Z averred that the cost to complete IMC’s unfinished

work and to correct non-conforming work will exceed the unpaid contract

balance. Id. at ¶ 16.

From November 2-5, 2015, a trial was held before the Honorable

Carolyn Tornetta Carluccio. After deliberating, the jury returned the

following verdict:

 Sea-Z breached its contract with IMC;

 Sea-Z did not have a good faith basis under CASPA to withhold payment from IMC; and

 IMC breached its contract with Sea-Z (on Sea-Z’s counterclaim).

Jury Verdict, 11/6/15, at 1-2. The jury awarded IMC $124,280.95 in

damages and Sea-Z $58,000.00 in damages.

On November 13, 2015, IMC filed post-trial motions to mold the

verdict to include statutory interest, penalties, and attorneys’ fees and

expenses under sections 505(d), 509(d) and 512(a) of CASPA, respectively.

On November 20, 2015, Sea-Z filed a cross-motion for post-trial relief

seeking vacation of the jury’s finding that it lacked good faith in response to

interrogatory #2 of the verdict slip, claiming that the response was against

the weight of the evidence.

On February 8, 2016, the trial court granted IMC’s post-trial motions

and molded the verdict to $404,036.89, which now included $65,204.88 in

statutory interest, $65,204.88 in penalties, and $149,346.18 in attorneys’

-4- J-A13011-17

fees and expenses under CASPA. On February 11, 2016, the court entered

judgment on the verdict in the amount of $404,036.89 in favor of IMC and in

the amount of $58,000 for Sea-Z. On February 19, 2016, Sea-Z filed a

timely notice of appeal from the trial court’s February 8, 2016 order. Sea-Z

raises the following issues on appeal:

(1) Whether the trial court erred as a matter of law or abused its discretion in denying Sea-Z’s cross-motion to set aside the jury’s finding that Sea-Z “did not have a good faith basis under [CASPA] to withhold payment from IMC . . .”, including the following subsidiary questions:

a. Did the trial court err in sustaining the jury’s finding that Sea[-]Z lacked a good faith basis in withholding payment from IMC where such finding is inconsistent with the jury’s award of $58,000 to Sea-Z for breach of [c]ontract[?]

b. Did the trial court err in sustaining the jury’s finding that Sea-Z did not have a good faith basis to withhold final payment where there was un[]contradicted evidence of IMC’s failure to satisfy express conditions precedent to final payment under the parties[’] [c]ontract?

(2) Did the trial court err in molding the [j]ury [v]erdict when it assessed interest in favor of IMC under CASPA in the absence of any basis in the [j]ury [v]erdict to determine the amount of the contract balance due and owing (within the meaning of CASPA § 505(d)) or the amount held as retainage and subject to the special provisions of CASPA § 509(d)?

Free access — add to your briefcase to read the full text and ask questions with AI

International Management Consultants v. Sea-z, (Pa. Ct. App. 2017).

International Management Consultants v. Sea-z (International Management Consultants v. Sea-z) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tyus v. Resta
476 A.2d 427 (Supreme Court of Pennsylvania, 1984)
Zimmerman v. Harrisburg Fudd I, L.P.
984 A.2d 497 (Superior Court of Pennsylvania, 2009)
De Fulvio v. Holst
362 A.2d 1098 (Superior Court of Pennsylvania, 1976)
Rozanc v. Urbany
664 A.2d 619 (Superior Court of Pennsylvania, 1995)
House of Pasta, Inc. v. Mayo
449 A.2d 697 (Supreme Court of Pennsylvania, 1982)
Pittsburgh Construction Co. v. Griffith
834 A.2d 572 (Superior Court of Pennsylvania, 2003)
Criswell v. King
834 A.2d 505 (Supreme Court of Pennsylvania, 2003)
Profit Wize Marketing v. Wiest
812 A.2d 1270 (Superior Court of Pennsylvania, 2002)
Berkeley Inn, Inc. v. Centennial Insurance
422 A.2d 1078 (Superior Court of Pennsylvania, 1980)
Zelenak v. Mikula
911 A.2d 542 (Superior Court of Pennsylvania, 2006)
Metropolitan Edison Co. v. Old Home Manor, Inc.
482 A.2d 1062 (Supreme Court of Pennsylvania, 1984)
Ruthrauff, Inc. v. Ravin, Inc.
914 A.2d 880 (Superior Court of Pennsylvania, 2006)
Zavatchen v. RHF Holdings, Inc.
907 A.2d 607 (Superior Court of Pennsylvania, 2006)
Mirizio v. Joseph
4 A.3d 1073 (Superior Court of Pennsylvania, 2010)
LBL SKYSYSTEMS (USA), INC. v. APG-America, Inc.
514 F. Supp. 2d 704 (E.D. Pennsylvania, 2007)
Waller Corp. v. Warren Plaza, Inc., Pet
108 A.3d 29 (Supreme Court of Pennsylvania, 2015)
Lomas, R. v. Kravitz, J.
130 A.3d 107 (Superior Court of Pennsylvania, 2015)
Fazio v. Guardian Life Insurance Co. of America
62 A.3d 396 (Superior Court of Pennsylvania, 2012)
Waller Corp. v. Warren Plaza, Inc.
95 A.3d 313 (Superior Court of Pennsylvania, 2014)