In re the Northern State Power Co. for Approval of its 1998 Resource Plan

604 N.W.2d 386, 2000 Minn. App. LEXIS 100, 2000 WL 31803
CourtCourt of Appeals of Minnesota
DecidedJanuary 18, 2000
DocketNo. C0-99-917
StatusPublished
Cited by4 cases

This text of 604 N.W.2d 386 (In re the Northern State Power Co. for Approval of its 1998 Resource Plan) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re the Northern State Power Co. for Approval of its 1998 Resource Plan, 604 N.W.2d 386, 2000 Minn. App. LEXIS 100, 2000 WL 31803 (Mich. Ct. App. 2000).

Opinion

OPINION

G. BARRY ANDERSON, Judge.

On appeal from an administrative proceeding, relator challenges approval given to respondent Northern States Power permitting modification of nuclear waste storage at the Prairie Island nuclear generating plant. Because the modification does not require legislative approval, and the administrative procedure employed did not violate state law, we affirm.

FACTS

The history of this case can be traced to the failure of Congress and the federal government to fulfill a compact to construct and, in 1998, to begin receiving high-level nuclear waste generated by this country’s nuclear power plants. In April 1991, sensing this impending failure, respondent Northern States Power (NSP) petitioned in an Application for a Certificate of Need to respondent Minnesota Pubhc Utilities Commission (commission) [388]*388for approval of temporary storage of nuclear waste in dry metal casks at the Prairie Island nuclear generating plant. Such storage was necessary because NSP’s in-plant temporary storage facility, a large cooling pool, would have reached maximum capacity in 1995. In August 1992, the commission approved NSP’s request, although modifying the requested number of casks from NSP’s requested 48 to 17. A condition to the approval was that NSP establish cooling pool storage space for a full core off-load,1 which entailed the ability to store the 121 fuel assemblies from each of Prairie Island’s two reactors — for a total of 242 assemblies.

As part of its limited certificate of need order approving NSP’s plan to store waste in the 17 casks, the commission determined that state legislative approval of dry cask storage was unnecessary. This court disagreed, concluding that Minnesota’s Radioactive Waste Management Act prohibited the dry cask storage absent legislative approval. In re Application for Certificate of Need for Indep. Spent Fuel Storage Installation (ISFSI), 501 N.W.2d 638, 648 (Minn.App.1993), review denied (Minn. July 15,1993).

In response to ISFSI, the legislature passed legislation approving of the 17 dry casks. See Minn.Stat. §§ 116C.77, 771 (1994). The legislature also authorized a “third reracking” of the storage pool. Minn.Stat. § 116C.778 (1994). Prior to requesting approval for the dry cask storage, NSP had reracked the storage pool on at least two occasions, in 1977 and 1981, which entailed restructuring the storage racks in the storage pools to permit greater capacity. Further, the legislature did not foreclose commission consideration of additional dry cask storage in connection with the decommissioning of a nuclear power plant. Minn.Stat. § 1160.771(e) (1994).

The present controversy began in January 1998, when NSP filed its application for resource plan approval 1998-2012 (resource plan) with the commission. The resource plan, required by statute, details a utility’s options to meet the service needs of its customers. See Minn.Stat. § 216B.2422 (1998).

As part of its resource plan, NSP requested approval to create 195 temporary storage spaces in the cooling pool. In the event of a full core off-load into that area, NSP explained that the temporary storage racks would be moved to a portion of the storage pool. NSP proposed a dual use of that portion of the storage pool, now used as the dry cask lay down area to facilitate insertion of fuel rods into dry casks, so that the temporary storage racks could be accommodated there if a full core off-load was necessary. The Nuclear Regulatory Commission has approved this dual plan for temporary storage.

A party, not on appeal, challenged the resource plan. The commission responded by holding statewide hearings in December 1998. All hearings were moderated by an administrative law judge and attended by members of the commission. Several citizens groups submitted written comments, which were entered into the public record. In January 1999, all intervening parties presented oral argument.

On February 17, 1999, the commission approved NSP’s resource plan, with modifications to separate portions of the resource plan, which are not on appeal. The commission approved NSP’s storage pool proposal, concluding the resource plan neither violated statutory mandate nor the 1992 limited certificate of need. On March 8, 1999, relator petitioned the commission to reconsider its decision. Relator argued that NSP’s plan violated the statutory intent of limiting the total amount of nuclear waste stored at Prairie Island. The com[389]*389mission rejected relator’s reconsideration request.

Relator filed its writ of certiorari with this court for a review of the commission’s decision to allow NSP to modify its storage procedures. This court has granted leave to Communities United for Responsible Energy (C.U.R.E.) to file a brief as amicus curiae. By previous order, this court rejected NSP’s claim that certiorari does not lie in this case because the commission’s decision was not “quasi-judicial.”

ISSUES

I. Did the Minnesota Public Utilities Commission err in granting Northern States Power’s plan to revise its temporary storage plan?

II. Did the Minnesota Public Utilities Commission employ incorrect procedure to grant Northern States Power’s plan to revise its temporary storage plan?

ANALYSIS

An administrative agency’s decision will be sustained on appeal “unless it ‘reflects an error of law, the determinations are arbitrary and capricious, or the findings are unsupported by the evidence.’” Glazier v. Independent School Dist. No. 876, 558 N.W.2d 763, 766 (Minn.App.1997) (quoting County of Scott v. Public Employment Relations Bd., 461 N.W.2d 503, 504 (Minn.App.1990), review denied (Minn. Dec. 20, 1990)).

The scope of judicial review of administrative decisions is provided in Minnesota’s Administrative Procedure Act:

[T]he court may affirm the decision of the agency or remand the case for further proceedings; or it may reverse or modify the decision if the substantial rights of the petitioners may have been prejudiced because the administrative finding, inferences, conclusion, or decisions are:
(a)In violation of constitutional provisions; or
(b) In excess of the statutory authority or jurisdiction of the agency; or
(c) Made upon unlawful procedure; or
(d) Affected by other error of law; or
(e) Unsupported by substantial evidence in view of the entire record as submitted; or
(f) Arbitrary or capricious.

Minn.Stat. § 14.69 (1998).

I.

We first examine relator’s challenge to the commission’s approval of NSP’s temporary storage proposal. Although rejected at the administrative level, on appeal relator argues that NSP’s proposal results in an increase of the nuclear waste storage capacity at Prairie Island, in violation of state legislation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Minnesota Power
807 N.W.2d 484 (Court of Appeals of Minnesota, 2011)
Max Schwartzman & Sons v. Minnesota Pollution Control Agency
670 N.W.2d 746 (Court of Appeals of Minnesota, 2003)
HealthPartners, Inc. v. Bernstein
655 N.W.2d 357 (Court of Appeals of Minnesota, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
604 N.W.2d 386, 2000 Minn. App. LEXIS 100, 2000 WL 31803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-the-northern-state-power-co-for-approval-of-its-1998-resource-plan-minnctapp-2000.