In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.

CourtCourt of Appeals of Minnesota
DecidedMay 18, 2015
DocketA14-1006
StatusUnpublished

This text of In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract. (In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract., (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-1006

In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.

Filed May 18, 2015 Affirmed Hudson, Judge

Minnesota Public Utilities Commission File No. E-002/M-12-1278

David J. Zoll, Charles N. Nauen, Kristen G. Marttila, Lockridge Grindal Nauen, P.L.L.P., Minneapolis, Minnesota; and

Thomas Melone (pro hac vice), Ecos Energy LLC, Minneapolis, Minnesota (for relator Minnesota Go Solar, LLC)

Michael C. Krikava, Thomas Erik Bailey, Kodi Jean Church, Briggs and Morgan, PA, Minneapolis, Minnesota; and

Mara N. Koeller, Xcel Energy Inc., Minneapolis, Minnesota (for respondent Northern States Power Company, d/b/a Xcel Energy, Inc.)

Lori Swanson, Attorney General, Anjali V. Shankar, Assistant Attorney General, St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission)

Considered and decided by Reyes, Presiding Judge; Hudson, Judge; and

Stoneburner, Judge. ∗

∗ Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10. UNPUBLISHED OPINION

HUDSON, Judge

In this certiorari appeal, relator challenges respondent public utility commission’s

denial, based on the recommendations of respondent utility, of relator’s application for a

renewable-development-fund (RDF) grant. Relator argues that respondent commission

(1) failed to follow the statutory funding directives of giving preference to the most cost-

effective proposals and strongly considering the benefits to Minnesotans, (2) failed to

address record evidence supporting relator’s application, and (3) did not accord relator

due process. We affirm.

FACTS

In 1994, to promote renewable energy, the Minnesota legislature established the

RDF to administer and distribute funds collected from the ratepayers of respondent

Northern States Power Company, d/b/a Xcel Energy. See Minn. Stat. § 116C.779 (2014).

The legislation requires Xcel to deposit funds into the RDF based on the volume of spent

nuclear fuel maintained in Xcel’s nuclear-power plants. Id., subd. 1. Respondent

Minnesota Public Utilities Commission (MPUC) approves grants for RDF funding after

recommendations by Xcel, which consults with an advisory board on those

recommendations. See id.

In 2012, after a legislative audit report recommended changes to the RDF

program, the Minnesota legislature amended the program’s governing statute. See 2012

Minn. laws. ch. 196, § 1, at 276–77; Minn. Stat. § 116C.779. The amended statute

provides that “[a] request for proposal [RFP] for renewable energy generation projects

2 must, when feasible and reasonable, give preference to projects that are most cost-

effective for a particular energy source.” Minn. Stat. § 116C.779, subd. 1(h). It also

provides that, in selecting projects for proposed funding, Xcel “must strongly consider,

where reasonable, potential benefit to Minnesota citizens and the utility’s ratepayers.”

Id., subd. 1(f). Xcel must use an independent third-party expert, along with the advisory

board, to evaluate proposals submitted in response to an RFP. Id. The MPUC may

disapprove recommended projects, but it cannot modify those selections without Xcel’s

agreement. Id., subd. 1(e).

In 2013, in response to Xcel’s RFP for the fourth RDF funding cycle, relator Go

Solar, LLC, submitted a $7.4-million proposal for 20 one-megawatt solar projects at

separate locations on the electrical grid in southeast and southwest Minnesota. The

proposed project contemplated a long-term power purchase agreement (PPA) at Xcel’s

project-avoided cost, with a fixed production incentive from solar renewable-energy

credits over a 25-year term. It had stated goals of doubling Xcel’s solar generating

capacity and creating a template for a solar renewable-energy-credit program.

In the fourth funding cycle, Xcel received 46 proposals for energy-production

projects, including Go Solar’s project, and 18 proposals for research-and-development

(R&D) projects. The independent expert first reviewed and rated the proposals. The

independent expert gave Go Solar’s proposal the highest total overall score, ranking it

highest in terms of total jobs created and highest among energy-production projects for

potential benefit to Minnesota and ratepayers, which was weighted 10% for energy-

production projects and 40% for R&D projects. Go Solar asserts that it should have also

3 been ranked first in cost-effectiveness because it provided the best value per RDF grant

dollar and was priced at avoided costs, which was lower than other solar-energy

proposals, which were priced at net-metering, or retail, prices. But the independent

expert used a different metric, total resource cost (TRC), and ranked Go Solar’s project in

the midrange of energy-production proposals for cost effectiveness.

The advisory board then reviewed a list of proposals, considering the independent

expert’s evaluation as well as qualitative factors, including diversity in location, project

types, and technology. Advisory board members noted that the independent expert rated

Go Solar’s proposal high in every area; that it was a large project; that its “[p]rice was

good”; and that its 25-year PPA was longer than typical 15-20 year PPAs. But advisory

group members also expressed concerns that the proposed four-month timeline to

negotiate PPAs was too short; that Go Solar was capable, but wished to negotiate one

PPA for the entire project; that its site locations were open, which added uncertainty; that

it was a “[g]ood, but very expensive project” and not suitable for RDF funding; and that

the solar renewable-energy-credit proposal was “interesting, but . . . need[ed] more

perspective.” The advisory group did not recommend Go Solar’s proposal to Xcel for

funding.

Xcel submitted an initial project selection report and two later supplemental

reports to the MPUC, noting its agreement with the advisory group’s concerns. Go Solar

filed a petition to intervene and requested a contested-case hearing, arguing that

significant issues not addressed in the selection process could be resolved only through a

contested-case hearing. The Minnesota Department of Commerce and other stakeholders

4 also filed comments. After an audit corrected technical scoring errors, which did not

affect Go Solar’s proposal, Xcel filed reply comments with a selection-report summary

and supplements for the MPUC review. Those comments observed that Go Solar had

received the highest technical score of EP proposals, but also that

[the project w]as disfavored by the advisory group as it would require too large of a portion of the funds anticipated to be awarded to EP projects (over a third of available funds). The energy price per kWh was high relative to other proposals and the locations for constructing the facilities were still open, which adds uncertainty. From prior experience, RDF proposals that do not have specific sites identified or a very clear plan to identify sites have significant project delays. Further, the overall timeline proposed for the project was not long enough based on the Company’s prior experiences negotiating power purchase agreements for projects of the scale proposed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reserve Mining Co. v. Herbst
256 N.W.2d 808 (Supreme Court of Minnesota, 1977)
Independent Sch. Dist. No. 581, Edgerton v. Mattheis
147 N.W.2d 374 (Supreme Court of Minnesota, 1966)
Brayton v. Pawlenty
781 N.W.2d 357 (Supreme Court of Minnesota, 2010)
In the Matter of Petition of N. St. Power
676 N.W.2d 326 (Court of Appeals of Minnesota, 2004)
In Re the Implementation of Utility Energy Conservation Improvement Programs
368 N.W.2d 308 (Court of Appeals of Minnesota, 1985)
In re the Northern State Power Co. for Approval of its 1998 Resource Plan
604 N.W.2d 386 (Court of Appeals of Minnesota, 2000)
State v. Caldwell
803 N.W.2d 373 (Supreme Court of Minnesota, 2011)
City of Moorhead v. Red River Valley Cooperative Power Ass'n
811 N.W.2d 151 (Court of Appeals of Minnesota, 2012)
Billion v. Commissioner of Revenue
827 N.W.2d 773 (Supreme Court of Minnesota, 2013)
In re S.G.
828 N.W.2d 118 (Supreme Court of Minnesota, 2013)
City of Moorhead v. Red River Valley Cooperative Power Ass'n
830 N.W.2d 32 (Supreme Court of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract., Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-xcels-request-to-issue-renewable-development-fund-cycle-4-minnctapp-2015.