In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.

Court of Appeals of Minnesota·Decided May 18, 2015·No. A14-1006·Unpublished

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA

IN COURT OF APPEALS

A14-1006

In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.

Filed May 18, 2015

Affirmed

Hudson, Judge

Minnesota Public Utilities Commission File No. E-002/M-12-1278

David J. Zoll, Charles N. Nauen, Kristen G. Marttila, Lockridge Grindal Nauen, P.L.L.P., Minneapolis, Minnesota; and

Thomas Melone (pro hac vice), Ecos Energy LLC, Minneapolis, Minnesota (for relator Minnesota Go Solar, LLC)

Michael C. Krikava, Thomas Erik Bailey, Kodi Jean Church, Briggs and Morgan, PA, Minneapolis, Minnesota; and

Mara N. Koeller, Xcel Energy Inc., Minneapolis, Minnesota (for respondent Northern States Power Company, d/b/a Xcel Energy, Inc.)

Lori Swanson, Attorney General, Anjali V. Shankar, Assistant Attorney General, St. Paul, Minnesota (for respondent Minnesota Public Utilities Commission)

Considered and decided by Reyes, Presiding Judge; Hudson, Judge; and Stoneburner, Judge. ∗

Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10.

UNPUBLISHED OPINION

HUDSON, Judge In this certiorari appeal, relator challenges respondent public utility commission’s denial, based on the recommendations of respondent utility, of relator’s application for a renewable-development-fund (RDF) grant. Relator argues that respondent commission (1) failed to follow the statutory funding directives of giving preference to the most cost- effective proposals and strongly considering the benefits to Minnesotans, (2) failed to address record evidence supporting relator’s application, and (3) did not accord relator due process. We affirm.

FACTS

In 1994, to promote renewable energy, the Minnesota legislature established the RDF to administer and distribute funds collected from the ratepayers of respondent Northern States Power Company, d/b/a Xcel Energy. See Minn. Stat. § 116C.779 (2014). The legislation requires Xcel to deposit funds into the RDF based on the volume of spent nuclear fuel maintained in Xcel’s nuclear-power plants. Id., subd. 1. Respondent Minnesota Public Utilities Commission (MPUC) approves grants for RDF funding after recommendations by Xcel, which consults with an advisory board on those recommendations. See id.

In 2012, after a legislative audit report recommended changes to the RDF program, the Minnesota legislature amended the program’s governing statute. See 2012 Minn. laws. ch. 196, § 1, at 276–77; Minn. Stat. § 116C.779. The amended statute provides that “[a] request for proposal [RFP] for renewable energy generation projects

must, when feasible and reasonable, give preference to projects that are most cost- effective for a particular energy source.” Minn. Stat. § 116C.779, subd. 1(h). It also provides that, in selecting projects for proposed funding, Xcel “must strongly consider, where reasonable, potential benefit to Minnesota citizens and the utility’s ratepayers.” Id., subd. 1(f). Xcel must use an independent third-party expert, along with the advisory board, to evaluate proposals submitted in response to an RFP. Id. The MPUC may disapprove recommended projects, but it cannot modify those selections without Xcel’s agreement. Id., subd. 1(e).

In 2013, in response to Xcel’s RFP for the fourth RDF funding cycle, relator Go Solar, LLC, submitted a $7.4-million proposal for 20 one-megawatt solar projects at separate locations on the electrical grid in southeast and southwest Minnesota. The proposed project contemplated a long-term power purchase agreement (PPA) at Xcel’s project-avoided cost, with a fixed production incentive from solar renewable-energy credits over a 25-year term. It had stated goals of doubling Xcel’s solar generating capacity and creating a template for a solar renewable-energy-credit program.

In the fourth funding cycle, Xcel received 46 proposals for energy-production projects, including Go Solar’s project, and 18 proposals for research-and-development (R&D) projects. The independent expert first reviewed and rated the proposals. The independent expert gave Go Solar’s proposal the highest total overall score, ranking it highest in terms of total jobs created and highest among energy-production projects for potential benefit to Minnesota and ratepayers, which was weighted 10% for energy- production projects and 40% for R&D projects. Go Solar asserts that it should have also

been ranked first in cost-effectiveness because it provided the best value per RDF grant dollar and was priced at avoided costs, which was lower than other solar-energy proposals, which were priced at net-metering, or retail, prices. But the independent expert used a different metric, total resource cost (TRC), and ranked Go Solar’s project in the midrange of energy-production proposals for cost effectiveness.

The advisory board then reviewed a list of proposals, considering the independent expert’s evaluation as well as qualitative factors, including diversity in location, project types, and technology. Advisory board members noted that the independent expert rated Go Solar’s proposal high in every area; that it was a large project; that its “[p]rice was good”; and that its 25-year PPA was longer than typical 15-20 year PPAs. But advisory group members also expressed concerns that the proposed four-month timeline to negotiate PPAs was too short; that Go Solar was capable, but wished to negotiate one PPA for the entire project; that its site locations were open, which added uncertainty; that it was a “[g]ood, but very expensive project” and not suitable for RDF funding; and that the solar renewable-energy-credit proposal was “interesting, but . . . need[ed] more perspective.” The advisory group did not recommend Go Solar’s proposal to Xcel for funding.

Xcel submitted an initial project selection report and two later supplemental reports to the MPUC, noting its agreement with the advisory group’s concerns. Go Solar filed a petition to intervene and requested a contested-case hearing, arguing that significant issues not addressed in the selection process could be resolved only through a contested-case hearing. The Minnesota Department of Commerce and other stakeholders

also filed comments. After an audit corrected technical scoring errors, which did not affect Go Solar’s proposal, Xcel filed reply comments with a selection-report summary and supplements for the MPUC review. Those comments observed that Go Solar had received the highest technical score of EP proposals, but also that

[the project w]as disfavored by the advisory group as it would require too large of a portion of the funds anticipated to be awarded to EP projects (over a third of available funds). The energy price per kWh was high relative to other proposals and the locations for constructing the facilities were still open, which adds uncertainty. From prior experience, RDF proposals that do not have specific sites identified or a very clear plan to identify sites have significant project delays.

Further, the overall timeline proposed for the project was not long enough based on the Company’s prior experiences negotiating power purchase agreements for projects of the scale proposed.

Xcel recommended funding for 13 EP projects, in amounts ranging from $310,310 to $5,000,000. It recommended reserve funding for nine EP projects and no funding for 24 EP projects, including Go Solar’s project.

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract., (Mich. Ct. App. 2015).

In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract. (In the Matter of Xcel's Request to Issue Renewable Development Fund Cycle 4 Requests for Proposals and Petition for Approval of a Standard Grant Contract.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Reserve Mining Co. v. Herbst
256 N.W.2d 808 (Supreme Court of Minnesota, 1977)
Independent Sch. Dist. No. 581, Edgerton v. Mattheis
147 N.W.2d 374 (Supreme Court of Minnesota, 1966)
Brayton v. Pawlenty
781 N.W.2d 357 (Supreme Court of Minnesota, 2010)
In the Matter of Petition of N. St. Power
676 N.W.2d 326 (Court of Appeals of Minnesota, 2004)
In Re the Implementation of Utility Energy Conservation Improvement Programs
368 N.W.2d 308 (Court of Appeals of Minnesota, 1985)
In re the Northern State Power Co. for Approval of its 1998 Resource Plan
604 N.W.2d 386 (Court of Appeals of Minnesota, 2000)
State v. Caldwell
803 N.W.2d 373 (Supreme Court of Minnesota, 2011)
City of Moorhead v. Red River Valley Cooperative Power Ass'n
811 N.W.2d 151 (Court of Appeals of Minnesota, 2012)
Billion v. Commissioner of Revenue
827 N.W.2d 773 (Supreme Court of Minnesota, 2013)
In re S.G.
828 N.W.2d 118 (Supreme Court of Minnesota, 2013)
City of Moorhead v. Red River Valley Cooperative Power Ass'n
830 N.W.2d 32 (Supreme Court of Minnesota, 2013)