Matter of University of Minnesota

566 N.W.2d 98, 1997 Minn. App. LEXIS 741, 1997 WL 370157
CourtCourt of Appeals of Minnesota
DecidedJuly 8, 1997
DocketC4-96-2526, C9-96-2411
StatusPublished
Cited by8 cases

This text of 566 N.W.2d 98 (Matter of University of Minnesota) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of University of Minnesota, 566 N.W.2d 98, 1997 Minn. App. LEXIS 741, 1997 WL 370157 (Mich. Ct. App. 1997).

Opinion

OPINION

HARTEN, Judge.

The Minnesota Pollution Control Agency (the MPCA) issued an air emissions permit to respondents University of Minnesota and Foster Wheeler Twin Cities, Inc. authorizing renovation of the University’s steam generation system. Relators contend that the MPCA decision to issue the permit is unsupported by substantial evidence, arbitrary and capricious, and based on an erroneous interpretation of the law. We affirm.

FACTS

The University of Minnesota (the University) and Foster Wheeler Twin Cities, Inc. (FTC) respectively own and operate three steam generating plants that provide for heating, air conditioning, and other University campus needs. Two of the steam plants, the Main Steam Service Facility (Main Plant), and the Southeast Service Facility (Southeast Plant), are located on the riverbank of the Mississippi River in Minneapolis, and the third plant, the St. Paul Steam Service Facility, is located adjacent to the state fairgrounds in St. Paul.

In 1988, responding to a growing concern about the continued use of its steam plant facilities, the University hired a consultant to evaluate its steam systems and long-term energy requirements. In 1989, after being advised that the University steam plants had a remaining useful life of about 10 years, the University regents began a three-year study. The University solicited proposals from more than 100 qualified vendors worldwide, reviewed detailed proposals submitted by eight vendors, and conducted intensive negotiations with three vendors. In April 1992, the Board of Regents entered into a design and construction contract with FTC.

In June 1992, the University submitted a steam plant renovation proposal to the Minnesota Environmental Quality Board (MEQB) for critical environmental review. The ensuing three-year review involved at least four public hearings and culminated in a detailed Environmental Impact Statement (EIS), which analyzed the environmental impact of the proposed steam plant project and numerous project alternatives.

In August 1994, the University submitted the original permit application to the MPCA. Federal Clean Air Act regulations require preconstruction permits for construction and

*102 modification of certain new emission sources. 40 C.F.R. § 52.21(i) (1996). Minn. R. 7007.3000 (1995) has delegated implementation and enforcement of the federal rules to the MPCA. Installation of new boilers and other changes proposed in the 1994 permit application are evaluated under these rules. 1

The University’s proposal provides that the coal-burning Main Plant will be shut down. The Southeast Plant, in operation since 1903, will be rehabilitated; its two existing coal boilers will be replaced with two new gas/oil boilers and a state-of-the-art circulating fluidized bed boiler (CFB) capable of burning a variety of fuels, including coal, gas, oil, and renewable fuels such as wood. In addition, a steam turbine will be installed in the Southeast Plant to provide 15 megawatts of electricity. Two coal boilers will be retired and a new gas/oil boiler will be installed at the St. Paul Plant.

In December 1995 and January 1996, the University regents issued a report to the University administration stating that “all project options represent environmental improvements, [but] each option has some shortcomings and presents different tradeoffs of different environmental interests and community values.”

During the 1996 legislative session, the MEQB issued its report to the legislature summarizing the EIS findings, as required by Minn.Stat. § 116G.15 (1996). The report included: (1) several alternative project proposals with the environmental advantages and disadvantages of each; (2) an indication that the EIS did not identify an environmentally superior alternative to the University’s proposal; (3) an indication that the proposed renovation is superior to the existing facilities; and (4) a warning that further delay in implementing the renovation would itself be a “significant environmental impact.”

After the EIS was completed, the MPCA informed the University that it proposed to resume working on the project permit. In order to begin processing the permit, the MPCA required that the University submit a supplemental permit application and commit to the following conditions:

1. The facilities would be required to burn a minimum of 70% natural gas on an annual basis for the life of the permit.
2. The facilities would be allowed a fuel-flexibility option, but petroleum coke would not be a fuel option.
3. The air emissions permit would not be issued until after the legislature adjourned in 1996.

In April 1996, the University and FTC supplemented the permit application. The application was amended to accommodate several recommended measures intended to improve riverfront esthetics, minimize emissions of fugitive coal dust, and eliminate coal traffic between the coal storage facility and the Southeast Plant. These measures involved enclosing and screening the coal storage facilities at the Main Plant, eliminating coal truck traffic near the river by installing an underground conveyor system for the Southeast Plant, and doubling (from 50% to 100%) the natural gas capability of the new CFB boiler.

On June 15, 1996, the MPCA issued a public notice of its commissioner’s preliminary decision to issue the permit and established a comment period of June 15 to July 15, 1996. MPCA staff prepared the draft permit. The commissioner gave public notice of the draft permit and made both it and an associated technical support document available for public review.

On August 27, 1996, the MPCA Board heard and considered a number of public comments. At that meeting, representatives of the City of Minneapolis Planning Department and NorAm Energy Management, Inc. claimed that the project would violate the Shoreland Development Act, Minn.Stat. § 103F.201-221 (1996), related state rules, and a City of Minneapolis ordinance governing shorelands. The MPCA Board extended until September 6, 1996, the period to accept *103 additional comments related to the shoreland issues. During this extension period, the University and relators submitted comments regarding the shoreland issue and Nor Am Energy Management cautioned that the project also would violate the Floodplain Management Law, Minn.Stat. §§ 103F.101-.155 (1996).

The commissioner directed MPCA staff to seek input regarding the shoreland and floodplain issues from the Minnesota Department of Natural Resources (MDNR), which administers both the shoreland and floodplain laws. The MDNR advised the MPCA that the proposed project would not violate statutes or rules governing shorelands or floodplains.

On October 22, 1996, the MPCA Board met and again considered the proposed permit. After considering all oral and written comments, it voted to issue the air emission permit. In its primary and supplemental findings of fact and conclusions of law, the Board stated its rationale for issuing the permit and rejecting each of the challenges.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Maltreatment & Disqualification of Kleven
736 N.W.2d 707 (Court of Appeals of Minnesota, 2007)
In Re American Iron and Supply Co.
604 N.W.2d 140 (Court of Appeals of Minnesota, 2000)
City of Minneapolis v. State
604 N.W.2d 140 (Court of Appeals of Minnesota, 2000)
In re the Northern State Power Co. for Approval of its 1998 Resource Plan
604 N.W.2d 386 (Court of Appeals of Minnesota, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
566 N.W.2d 98, 1997 Minn. App. LEXIS 741, 1997 WL 370157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-university-of-minnesota-minnctapp-1997.