In re Programmatic Changes to the Standard-Offer Program

2014 VT 29, 95 A.3d 999, 196 Vt. 175, 2014 WL 1328175, 2014 Vt. LEXIS 29
CourtSupreme Court of Vermont
DecidedMarch 28, 2014
DocketNo. 13-308
StatusPublished
Cited by9 cases

This text of 2014 VT 29 (In re Programmatic Changes to the Standard-Offer Program) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Programmatic Changes to the Standard-Offer Program, 2014 VT 29, 95 A.3d 999, 196 Vt. 175, 2014 WL 1328175, 2014 Vt. LEXIS 29 (Vt. 2014).

Opinion

Crawford, J.

¶ 1. Applicant Ecos Energy, LLC appeals from the Public Service Board’s decision that its proposed solar power project does not qualify for a standard-offer power purchase contract under Vermont’s Sustainably Priced Energy Enterprise Development (SPEED) program because it exceeds the statutory limit on generation capacity. We reverse.

¶ 2. The Legislature established the SPEED program in 2005 to promote development of renewable energy in Vermont. 30 V.S.A. §§ 8001, 8005, 8005a. The statute promotes this goal in two ways: by requiring electric utilities to purchase a certain amount of [177]*177power from renewable energy sources, and by creating a standard-offer program. Under the standard-offer program, the Board authorizes certain long-term power-purchase contracts with electrical-providers in Vermont for renewable energy projects that have a nameplate capacity of 2.2 megawatts (MW) or less and meet certain other criteria. Id. § 8005a(b). Once a plant owner executes a standard-offer contract, the Board guarantees a set price for that plant’s energy for the duration of the contract regardless of whether the market price changes. Id. § 8005a(f)(4). The standard-offer program is administered by the SPEED facilitator, VEPP, Inc., which operates under a contract with the Board. Id. § 8005a(a).

¶ 3. In 2009, after soliciting public comment, the Board issued an order in which it prescribed various procedures and requirements for the standard-offer program. During the comment process, VEPP asked the Board to clarify how a plant was defined, stating that “the tenor of some questions it had received from developers indicated that at least some developers were anticipating construction of multiple plants at a single location that, collectively, exceed the 2.2 MW cap.” One of the participants in the implementation process, Central Vermont Public Service, commented that separate projects would need to enter into separate interconnection agreements with the utility, enter into separate standard contracts, and obtain separate certificates of public good. Another participant, Renewable Energy Vermont, commented that the statute was clear that “separate plants that share common infrastructure and interconnection should be considered as one plant.”

¶ 4. In response to these comments, the Board ordered that “[t]o the extent that any generation components share common infrastructure, we direct [VEPP] to consider these components as a single plant.” It ordered VEPP to identify and inform the Board of applications that would be on the same parcel of land or contiguous parcels of land and would collectively exceed the 2.2 MTW cap, and stated that “[t]o the extent required, the Board will make case-by-case determinations as to whether [such] projects constitute a single plant for purposes of § 8002(12).”1 The Board did not state what criteria would be used to determine whether [178]*178multiple projects constituted a single plant, either in the 2009 order or in any other order or rule.

¶ 5. In April 2013, VEPP issued a request for proposals (RFP) for projects that would be eligible for a power-purchase agreement under § 8005a. The RFP indicated that standard-offer contracts would be offered to proposals in order of price, starting with the lowest-priced projects, until the annual capacity cap was reached. In response, applicant proposed three 2.0 MW solar projects — the Bennington Solar project, the Apple Hill Solar project, and the Sudbury Solar project. Of the thirty-four proposals submitted, applicant’s three projects were the lowest-priced projects.

¶ 6. VEPP filed a report with the Board detailing the RFP results. VEPP noted that the Bennington project and the Apple Hill project would be located on the same parcel of property and the generation components of the project were “physically contiguous.” It requested that the Board make a determination as to whether or not the two projects constituted a single plant. If so, the combined capacity of the plant (4.0 MW) would exceed the standard-offer program limit of 2.2 MW.

¶ 7. The Board issued an order on May 16, 2013 in which it ruled that the Bennington and Apple Hill projects consisted of a single 4.0 MW plant “[b]ecause both proposals are located on the same parcel of land and have similar interconnection points.” The Board accepted the Bennington project and disqualified the Apple Hill project, which had a higher price. The Board authorized VEPP to enter into standard-offer contracts with applicant for the Bennington and Sudbury projects.

¶ 8. Applicant subsequently petitioned the Board to reconsider and modify its order. Applicant argued that the Bennington and Apple Hill projects were “independent technical facilities” because as proposed they would connect with the electric grid through separate three-phase lines, be separated by a fence, have separate access roads, use separate inverters, transformers and other equipment, and have different financing parties. The Board issued an order on June 28, 2013 stating that “[w]hile the projects may be operationally independent, they are still being advanced by the same developer, located on the same parcel of land, and adjoining each other. Based on our review of the site plans ... it is reasonable to infer that they are a single plant.” The Board stated that applicant’s interpretation of independence would permit “any [179]*179size facility [to] be constructed so long as it could be partitioned into ‘technically independent’ 2.2 MW pieces by including redundant equipment and separating each piece by a mere fence.” The Board reasoned that this type of clustered development would frustrate the legislative goal of distributing small-to-moderate facilities across the state’s electric grid.2 Applicant appeals the Board’s May and June 2013 orders.

¶ 9. In reviewing decisions of the Public Service Board, “we defer to the Board’s expertise and informed judgment, and apply a strong presumption of validity to its orders.” Grice v. Vt. Elec. Power Co., 2008 VT 64, ¶ 7, 184 Vt. 132, 956 A.2d 561 (quotations omitted). “Absent a compelling indication of error, we will not disturb an agency’s interpretation of statutes within its particular area of expertise.” In re Verizon New Eng., Inc., 173 Vt. 327, 334-35, 795 A.2d 1196, 1202 (2002). However, “we do not abdicate our responsibility to examine a disputed statute independently and ultimately determine its meaning.” In re MacIntyre Fuels, Inc., 2003 VT 59, ¶ 7, 175 Vt. 613, 833 A.2d 829 (mem.). Our “paramount goal” in construing a statute is to give effect to the intent of the Legislature. Murdoch v. Town of Shelburne, 2007 VT 93, ¶ 5, 182 Vt. 587, 939 A.2d 458 (mem.). We will apply the plain meaning of a statute where it is clear and unambiguous. In re Verizon New Eng., 173 Vt. at 335, 795 A.2d at 1202.

¶ 10. In this case, there is a “compelling indication of error.” Id. at 334-35, 795 A.2d at 1202. The Board’s conclusion that the Bennington and Apple Hill projects constitute a single plant is contrary to the plain language of the statute. Section 8002(14) defines a plant as follows:

[180]*180“Plant” means an independent technical facility that generates electricity from renewable energy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2014 VT 29, 95 A.3d 999, 196 Vt. 175, 2014 WL 1328175, 2014 Vt. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-programmatic-changes-to-the-standard-offer-program-vt-2014.